Memo Attachment A - Proposed 2026 General Obligation Bond Program
Meeting ID
922
Agenda item ID
21974
SHA-256
652e69cbacc5eb4396f925a09c2a3cb6e56dbb0d63ffe262c3c337f9049d7a2f
Revision
1
First discovered
2026-09-14T22:35:36.777Z
Last checked
2026-09-14T22:58:37.811Z

Extracted text

Memo Attachment A: Proposed 2026 General Obligation Bond Program
Street, Sidewalk, and Pedestrian Accessibility Improvements
Proposed General Obligation Bond Project Summary
Maximum Bond Authorization: $11,250,000
The following projects represent the City’s anticipated initial investment priorities for the Street, Sidewalk,
and Pedestrian and Bicycle Accessibility General Obligation Bond. The project list may be modified by the
Governing Body as necessary based on funding availability, bid results, changing conditions, grant
opportunities, utility coordination, project delivery considerations, or other public needs, provided all
expenditures remain consistent with the purposes authorized by the bond.
Roadway Rehabilitation Projects (Approximately $10,000,000)
Council District Street Limits
District 2 Rodeo Road Yucca Street to Sawmill Road
District 4 Calle Atajo Rufina Street to Terminus
District 1 Alameda Street St. Francis Drive to Guadalupe Street
District 1 Alameda Street Guadalupe Street to Paseo de Peralta
District 1 Alameda Street Paseo de Peralta to Palace Avenue
District 3 Jemez Road Airport Road to Agua Fria Street
District 4 Center Drive Entire Length
District 3 Agua Fria Street Airport Road to Camino Juliana
District 4 Calle La Resolana Cerrillos Road to Siringo Road
District 3 Vuelta Dorado Entire Length
District 3 Calle Verde Entire Length
Sidewalk and Pedestrian and Bicycle Accessibility Improvements (Approximately $1,250,000)
Bond proceeds are anticipated to support the Complete Streets Division’s existing Sidewalk Rehabilitation
Program, including the construction, rehabilitation, replacement, and accessibility improvement of
sidewalks, curb ramps, pedestrian crossings, bicycle infrastructure and related infrastructure throughout the
City. Individual locations will be prioritized based on:
• ADA accessibility requirements
• Public safety
• Connectivity
• School and transit access
• Sidewalk and pedestrian infrastructure condition
• Emergency response needs
• Geographic equity