Form Updated: April 2024 Development Review Team (DRT) Comment Form DRT Review Schedule – 9-12+ weeks* Initial DRT Comments are due to the case planner within three weeks of the DRT Application Intake meeting. Initial DRT review should confirm that the application is complete (i.e. Water Budget has been submitted) and/or identify additional submittals or corrections (i.e. Water Budget needs revision). The case planner will review and convey all Initial DRT Comments to the applicant via a Review Memo. The applicant must respond to all Initial DRT Comments and submit a revised application for Final Review. Final DRT Comments are due to the case planner within two weeks of receipt of the revised application. The case planner will review and convey all Final DRT Comments to the applicant in a Final Review Memo. The complete DRT Review Timeline can range from 9-12+ weeks, depending on the complexity and quality of the application and the total number of applications under review. Timing of Conditions of Approval + Technical Corrections While all DRT conditions of approval and technical corrections must be met by the applicant, the timing of compliance varies. In the “Must be completed by” column in the following tables, please time your conditions of approval and technical corrections to the following development review stages: a. Prior to Public Hearing – these conditions/technical corrections must be addressed before the case may move forward to the public hearing phase of the Development Review Process. b. Prior to Recordation – these conditions/technical corrections may be resolved after the public hearing but must be addressed before the Development Plan or Subdivision plat is recorded. c. Prior to Building Permit Approval – these conditions/technical corrections can be addressed during the building permit review process, but prior to issuance of the permit. d. During Construction – these conditions/technical corrections can be addressed during construction. Development Review Process Flow Chart *See the 2024 Development Review Schedule for details DRT Review Timeline: Application Received DRT Application Intake DRT Initial Review Comments Due Sept 10, 2026 Sept 10, 2026 September 29, 2026 Initial DRT Comments Review Memo Revised Application Final DRT Comments Final Review Memo Form Updated: April 2024 Date: October 28, 2026 DRT Member: Dept/Div: Case No.: Geronimo Griego, Fire Marshal Fire Department/ Fire Marshal’s Office 2026-013291. 2395 Richards Ave, Micro Community (Revised)Case Planner: Joel Cruz-Haber, Senior Planner Conditions of Approval and Technical Corrections Tables Review by this division/department has determined that this application will meet applicable standards if the following Conditions of Approval and Technical Corrections are met: Case # Conditions of Approval: Must be completed by: Applicant response**: 1. Shall comply with the most currently adopted International Fire Code (IFC) and adopted city ordinances upon building permit approval. Prior to Recordation 2. 3. 4. 5. 6. Technical Corrections: Must be completed by: Applicant response**: 1. 2. 3. 4. **The Applicant must respond to the condition of approval or technical correction, indicating they have met the requirement and providing a reference in their revised submittals. If the applicant has not met the requirement, they must indicate as much and provide a response. The applicant should be aware that the following code provisions or other requirements will apply to future phases of development of this project: 1. All corrections were made on submission (Dated: 10/23/2026 and on Page AS-102 of Exhibit A) 2. CID & Building Classification: Confirm State CID review for City property and clarify if units are permitted as temporary or permanent structures. Explanation of Conditions or Corrections (if needed):