MEMORANDUM To: SFSWMA Joint Powers Board Members From: Randall Kippenbrock, P.E., Executive Director RLK Date: October 12, 2026 Subject: Request for Approval of Amendment No. 1 to the Professional Services Agreement with Parkhill of Rio Rancho, NM, for Design, Bid, and Construction Management Services for a New Maintenance Shop and Administration Building at the Caja del Rio Landfill (RFP No. 25098) SUMMARY The Agency requests that the Board approve Amendment No. 1 (Amendment) to the Professional Services Agreement (Agreement) with Parkhill, Smith & Cooper, Inc. d/b/a Parkhill of Rio Rancho, NM, for on-call engineering services (RFP No. 25098). The Amendment adds design, bidding, and construction management for a new maintenance shop and administration building at Caja del Rio Landfill, covering Tasks 2–6: schematic design, design development, construction documents, bid services, and construction-phase A/E services. The Amendment does not include the following services required to complete the project: site survey, geotechnical report, inspection services, and construction material testing. The Amendment extends the term of the Agreement through October 16, 2027. Pursuant to Article 5 of the Agreement, the Agreement may be renewed annually, subject to Board approval, for a total term not to exceed four years. The Amendment increases compensation by $718,200, for a total not to exceed $744,918.75. Funding is available in 8100851.572960 (WIP Design) through a budget increase of $718,200 from 816.100700 (Capital Improvement Reserve Fund). The Amendment also provides Parkhill’s scheduled hourly billing rates for 2026. The probable project cost for the new maintenance shop and administration building is $13.2 million, with a project duration of 20 months. BACKGROUND On October 16, 2025, the Board approved an Agreement with Parkhill for on-call engineering services for the Agency for $26,718.75. The Agreement’s Scope of Services, under Task 1, includes the conceptual design of a new maintenance shop and an administration building at the Caja del Rio Landfill as follows: • Task 1 – Conceptual Design / Site Evaluation o Needs Assessment o Conceptual Design o Budget ACTION REQUESTED The Agency requests Board approval of Amendment No. 1 to the Agreement with Parkhill for on- call engineering services associated with Tasks 2-6. The Agency requests Board approval to extend the Agreement term through October 16, 2027. The Agency requests Board approval to increase compensation by $718,200, for a total not to exceed $744,918.75. The Agency also requests approval of a budget increase to 8100851.572960 (WIP Design) from 816.100700 (Capital Improvement Reserve Fund Balance) in the amount of $718,200. Attachments: 1) Budget Adjustment Request 2) Amendment No. 1 to the Agreement with Parkhill 3) Professional Services Agreement with Parkhill M:\Memo\Memo.101226.1 ATTACHMENT 1 Budget Adjustment Request DATE {enter as positive #} {enter as positive #} JUSTIFICATION: (use additional page if needed) --Attach supporting documentation/memo Fund Balance Fund(s) Affected Increase/(Decrease) 816 (718,200) TOTAL: (718,200) Thomasina Chavez 10/13/2026 Prepared By {print name} Date Budget Officer Date JPB Division Director Signature {optional} Date Approval Date Finance Director { ≤ $5,000} Date Agenda Item #: Department Director Signature Date City Manager { ≤ $60,000} Date 8100851 655816 Cash is available in 816.100700 {Use this form for Finance Committee/ City Council agenda items ONLY} CITY COUNCIL APPROVAL 718,200$ -$ Amendment No. 1 to the Professional Services Agreement with Parkhill of Rio Rancho, NM, {Complete section below if BAR results for Design, Bid, and Construction Management Services for a New Maintenance Shop and in a net change to ANY Fund} Administration Building at the Caja del Rio Landfill (RFP No. 25098); (718,200) REVENUES Transfer In to ORG 810 (from ORG 816) Transfer out of ORG 816 (to ORG/Fund 810) 8160890 755810 718,200 EXPENDITURES {enter as positive #} {enter as negative #} WIP Design 8100851 572960 718,200 DEPARTMENT / DIVISION NAME SFSWMA 10/13/2026 ITEM DESCRIPTION ORG OBJECT PROJECT INCREASE DECREASE BUDGET AMENDMENT RESOLUTION (BAR) Log # {Finance use only } : Batch # {Finance use only } : City of Santa Fe, New Mexico ATTACHMENT 2 Amendment No. 1 to the Agreement with Parkhill SANTA FE SOLID WASTE MANAGEMENT AGENCY AMENDMENT No. 1 PROFESSIONAL SERVICES AGREEMENT WITH PARKHILL (On-Call Engineering Services - 2025) This AMENDMENT No. 1 ("Amendment") to the PROFESSIONAL SERVICES AGREEMENT, dated October 16, 2025 ("Agreement"), is made and entered into between the Santa Fe Solid Waste Management Agency ("Agency") and Parkhill, Smith & Cooper, Inc. d/b/a Parkhill ("Contractor"). The date of this Amendment shall be the date this Amendment is executed by the Agency. RECITALS Under the terms of the Agreement, Contractor has agreed to provide on-call engineering services (RFP No. 25098). Pursuant to Article 19, Amendment of the Agreement, and for good and valuable consideration, the receipt and sufficiency of which are acknowledged by the parties, the Agency and Contractor agree as follows: 1. SCOPE OF SERVICES Article 1, Scope of Services of the Agreement is hereby amended to include Task 2 (Schematic Design), Task 3 (Design Development), Task 4 (Construction Documents), Task 5 (Bid Phase Services), and Task 6 (Construction A/E Phase Services) as described in Exhibit A attached hereto. 2. COMPENSATION Article 3, Compensation of the Agreement, is hereby amended to increase the amount of compensation by a total of Seven Hundred Eighteen Thousand Two Hundred Dollars and No Cents ($718,200.00) so that Article 3 reads in its entirety as follows: Parkhill Professional Services Agreement for On-Call Engineering Services – Amendment No. 1 2 A. The Agency shall pay to Contractor in full payment for services rendered, including applicable gross receipts taxes, a sum not to exceed Seven Hundred Forty-Four Thousand Nine Hundred Eighteen Dollars and Seventy-Five Cents ($744,918.75). DESCRIPTION AMOUNT ORIGINAL CONTRACT $26,718.75 AMENDMENT NO. 1 $718,200.00 CONTRACT TO DATE $744,918.75 B. Contractor shall be responsible for payment of New Mexico gross receipts taxes due to the State of New Mexico on the sums payable under this Agreement. C. Compensation shall be paid only for services performed in accordance with the fee schedule set forth in Exhibit A, attached hereto. D. Payment shall be made upon receipt and approval by the Agency of reasonably detailed invoices describing the services performed. Invoices shall be rendered not more than once each month. Detailed invoices containing reimbursement expenses shall be itemized. E. Contractor shall submit invoices to the Agency via mail or email as follows: Santa Fe Solid Waste Management Agency Attn: Accounts Payable 149 Wildlife Way Santa Fe, NM 87506 Email: AccountsPayable@sfswma.org 3. TERM AND EFFECTIVE DATE Article 5, Term and Effective Date of the Agreement, is amended to extend the term of the Agreement, so that Article 5 reads in its entirety as follows: A. This Agreement shall be effective when signed by the Agency and terminate on October 16, 2027, unless it is terminated sooner pursuant to Article 6 below. Parkhill Professional Services Agreement for On-Call Engineering Services – Amendment No. 1 3 B. Pursuant to the limitations on multi-term contracts for professional services codified in NMSA 1978, Section 13-1-150, this Agreement may not exceed four years, including all extensions and renewals. Subject to that limitation, the Agreement can be renewed annually if agreed upon by the Agency and Contractor and approved by the Joint Powers Board. 4. AGREEMENT IN FULL FORCE Except as specifically provided in this Amendment, the Agreement remains and shall remain in full force and effect in accordance with its terms. IN WITNESS WHEREOF, the parties have executed this Amendment as of the dates set forth below. SANTA FE SOLID WASTE MANAGEMENT AGENCY: ________________________ __________________ Lisa Cacari Stone Date: Joint Powers Board CONTRACTOR: ________________________ __________________ Frank Pugsley, P.E. Date: Director of Environmental / Partner Parkhill APPROVED AS TO FORM: ________________________ __________________ Nancy R. Long Date: Agency Attorney Parkhill Professional Services Agreement for On-Call Engineering Services – Amendment No. 1 4 EXHIBIT A Scope of Services for Parkhill Parkhill Professional Services Agreement for On-Call Engineering Services – Amendment No. 1 5 Parkhill Professional Services Agreement for On-Call Engineering Services – Amendment No. 1 6 Parkhill Professional Services Agreement for On-Call Engineering Services – Amendment No. 1 7 Parkhill Professional Services Agreement for On-Call Engineering Services – Amendment No. 1 8 Parkhill Professional Services Agreement for On-Call Engineering Services – Amendment No. 1 9 Parkhill Professional Services Agreement for On-Call Engineering Services – Amendment No. 1 10 Parkhill Professional Services Agreement for On-Call Engineering Services – Amendment No. 1 11 Parkhill Professional Services Agreement for On-Call Engineering Services – Amendment No. 1 12 ATTACHMENT 3 Professional Services Agreement with Parkhill Page 1 of 11 SANTA FE SOLID WASTE MANAGEMENT AGENCY PROFESSIONAL SERVICES AGREEMENT PARKHILL (On-Call Engineering Services – 2025) This PROFESSIONAL SERVICES AGREEMENT(“Agreement”) is made and entered into this 16th day of October 2025 by and between the Santa Fe Solid Waste Management Agency (“Agency”) and Parkhill, Inc., a Texas Corporation (“Contractor”) for on-call engineering services (RFP No. 25098) as described in Exhibit A and below. 1. SCOPE OF SERVICES The professional services subject to this Agreement are set forth in the Scope of Services attached hereto as Exhibit A. 2. STANDARDS OF PERFORMANCE; LICENSES A. Contractor represents that it possesses the experience and knowledge necessary to perform the services described in this Agreement. B. Contractor agrees to obtain and maintain throughout the term of this Agreement all applicable professional and business licenses required by law for itself and its employees, agents, representatives and subcontractors. 3. COMPENSATION A. The Agency shall pay to Contractor in full payment for services rendered, including applicable gross receipts taxes, a sum not to exceed Twenty-Six Thousand Seven Hundred Eighteen Dollars and Seventy-Five Cents ($26,718.75). B. Contractor shall be responsible for payment of gross receipts taxes levied by the State of New Mexico on the sums payable under this Agreement. C. Payment shall be made upon receipt and approval by the Agency of detailed invoices containing a report of services completed. Compensation shall be paid only for Page 2 of 11 services performed per the fee schedule set forth in the Scope of Services attached hereto in Exhibit A. D. Detailed invoices containing reimbursement expenses shall be itemized. E. Contractor shall submit invoices to the Agency via mail or email as follows: Santa Fe Solid Waste Management Agency Attn: Accounts Payable 149 Wildlife Way Santa Fe, NM 87506 Email: AccountsPayable@sfswma.org 4. APPROPRIATIONS The terms of this Agreement are contingent upon sufficient appropriations to and authorization from the Joint Powers Board for the Agency for the performance of this Agreement. If sufficient appropriations are not made or authorization provided, this Agreement shall terminate upon written notice from the Agency to Contractor. The Agency shall be responsible for charges incurred up to the date of notification under this Article per Article 6 of this Agreement. The Agency’s decision as to whether sufficient appropriations are available shall be accepted by Contractor and shall be final. 5. TERM AND EFFECTIVE DATE A. This Agreement shall be effective when signed by the Agency and terminate on October 16, 2026, unless terminated sooner pursuant to Article 6 below. B. Pursuant to the limitations on multi-term contracts for professional services codified in NMSA 1978, Section 13-1-150, this Agreement may not exceed four years, including all extensions and renewals. Subject to that limitation, the Agreement can be renewed annually if agreed upon by the Agency and Contractor and approved by the Joint Powers Board. Page 3 of 11 6. TERMINATION A. The Agency may terminate this Agreement upon ten (10) days' written notice to Contractor. If the Agency terminates the Agreement: 1) Contractor shall render a final report of the services performed up to the date of termination and shall turn over to the Agency original copies of all work product, research, or papers prepared for the services covered by this Agreement. The Agency shall pay Contractor for services rendered and expenses incurred under this Article, including for preparation of the final report. 2) If compensation is not based upon hourly rates for services rendered, the Agency shall pay Contractor for the reasonable value of services satisfactorily performed through the date Contractor receives notice of such termination for which compensation has not already been paid. 3) If compensation is based upon hourly rates and expenses, Contractor shall be paid for services rendered and expenses incurred through the date Contractor receives notice of such termination. 7. STATUS OF CONTRACTOR; RESPONSIBILITY FOR PAYMENT OF EMPLOYEES AND SUBCONTRACTORS A. Contractor, its agents, and its employees are independent contractors performing professional services for the Agency and are not employees of the Agency. B. Contractor, its agents, and its employees shall not accrue leave, retirement, insurance, bonding, or any other benefits afforded to employees of the Agency and shall not be permitted to use Agency vehicles in the performance of this Agreement. Page 4 of 11 C. Contractor shall be solely responsible for payment of wages, salaries, and benefits to any and all employees or subcontractors Contractor retains to perform any of its obligations pursuant to this Agreement. 8. CONFIDENTIALITY Any confidential information provided to or developed by Contractor in the performance of this Agreement shall be kept confidential and shall not be made available to any individual or organization by Contractor without the Agency’s prior written approval. 9. OWNERSHIP OF WRITTEN PRODUCTS All reports, documents or other written material (“written products” herein) developed by Contractor in the performance of this Agreement shall be and remain the property of the Agency without restriction or limitation upon its use or dissemination by the Agency. Contractor may take and retain copies of such written products as desired, but no such written products shall be the subject of a copyright application by Contractor. 10. CONFLICT OF INTEREST Contractor warrants that it presently has no interest and shall not acquire any interest, direct or indirect, that would conflict in any manner or degree with its performance of its obligations pursuant to this Agreement. Contractor further agrees that it shall not employ or Agreement with anyone in the performance of this Agreement that has any such conflict of interest. 11. ASSIGNMENT; SUBCONTRACTING Contractor shall not assign or transfer any rights, privileges, obligations or other interests under this Agreement, including any claims for money due, without the Agency’s prior written consent. Contractor shall not subcontract any portion of the services to be performed under this Agreement without the Agency’s prior written approval. Page 5 of 11 12. RELEASE Contractor, upon acceptance of final payment of the amount due under this Agreement, releases the Agency, its officers, and its employees from all liabilities, claims, and obligations whatsoever arising from or under this Agreement. Contractor agrees not to purport to bind the Agency to any obligation not assumed herein by the Agency unless Contractor has express written authority to do so, and then only within the strict limits of that authority. 13. INSURANCE A. Contractor, at its own cost and expense, shall carry and maintain in full force and effect during the term of this Agreement commercial general liability insurance of $2,000,000 for each occurrence and $4,000,000 in general aggregate coverage for bodily injury and property damage liability, in a form and with an insurance company acceptable to the Agency. The required limits may be provided by a combination of general liability insurance and commercial umbrella liability insurance. The Agency shall be named as an additional insured under the insurance policy, and the policy shall provide that the Agency will be notified no less than 30 days before the policy is canceled for any reason. Contractor has furnished the Agency with a copy of a Certificate of Insurance or other evidence of Contractor’s compliance with the provisions of this Article as a condition of entering into this Agreement. B. Contractor shall carry and maintain professional liability insurance throughout the term of this Agreement for errors and omissions to cover no less than $2,000,000 for each claim. C. Contractor shall carry and maintain sufficient automobile liability insurance throughout the term of this Agreement to cover no less than $2,000,000 combined single limit Page 6 of 11 for each accident. The required limits may be provided by a combination of automotive liability insurance and commercial umbrella liability insurance. D. Contractor shall carry and maintain Workers’ Compensation insurance in accordance with New Mexico law to provide coverage for Contractor’s employees throughout the term of this Agreement. Contractor shall provide the Agency with evidence demonstrating that appropriate Workers’ Compensation insurance has been obtained. 14. INDEMNIFICATION Contractor shall indemnify, hold harmless and defend the Agency from all losses, damages, claims or judgments, including payment of all attorneys’ fees and costs on account of any suit, judgment, execution, claim, action, or demand whatsoever to the extent arising from the negligent acts, errors, or omissions, or willful and reckless disregard of obligations under this Agreement, in the performance of any services covered by this Agreement, whether occurring on Agency managed or owned property or otherwise, by Contractor or its employees, agents, representatives, or subcontractors, excepting only such liability that arises out of the Agency’s negligence. 15. NEW MEXICO TORT CLAIMS ACT Any liability incurred by the Agency in connection with this Agreement is subject to the immunities and limitations set forth in the New Mexico Tort Claims Act, NMSA 1978, Sections 41- 4-1 to 41-4-27. The Agency and its employees do not waive sovereign immunity, any available defense, or any limitation of liability recognized by law. No provision in this Agreement modifies or waives any provision of the New Mexico Tort Claims Act. 16. THIRD-PARTY BENEFICIARIES By entering into this Agreement, the parties do not intend to create any right, title, or interest in, or for the benefit of, any person other than the Agency and Contractor. No person shall claim any Page 7 of 11 right, title or interest under this Agreement or seek to enforce this Agreement as a third-party beneficiary. 17. RECORDS AND AUDIT Contractor shall maintain throughout the term of this Agreement and for a period of three years thereafter detailed records that indicate the date, time, and nature of services rendered. These records shall be subject to inspection by the Agency, the City of Santa Fe Finance Department, and the State Auditor. The Agency shall have the right to audit the billing before and after payment. Payment under this Agreement shall not foreclose the right of the Agency to recover excessive or illegal payments. 18. APPLICABLE LAW; CHOICE OF LAW; VENUE Contractor shall abide by all applicable federal and state laws and regulations, and all ordinances, rules and regulations of the Agency. In any action, suit, or legal dispute arising from this Agreement, Contractor agrees that the laws of the State of New Mexico shall govern. The parties agree that any action or suit arising from this Agreement shall be commenced in the First Judicial District Court, State of New Mexico. 19. AMENDMENT This Agreement shall not be altered, changed, or modified except by an amendment in writing executed by the parties. 20. SCOPE OF AGREEMENT This Agreement expresses the entire agreement and understanding between the parties with respect to the services set forth in the Scope of Services attached hereto as Exhibit A. No prior agreement or understanding, verbal or otherwise, of the parties or their agents shall be valid or enforceable unless embodied in this Agreement. Page 8 of 11 21. NON-DISCRIMINATION During the term of this Agreement, Contractor shall not discriminate against any employee or applicant for an employment position to be used in the performance of the services Contractor undertakes pursuant to this Agreement on the basis of ethnicity, race, age, religion, creed, color, national origin, ancestry, sex, gender, sexual orientation, physical or mental disability, medical condition, or citizenship status. 22. SEVERABILITY If one or more of the provisions of this Agreement or any application thereof is found to be invalid, illegal, or unenforceable in any respect, the validity, legality, and enforceability of the remaining provisions of the Agreement and any other application thereof shall not in any way be affected or impaired. 23. NOTICES A. Any notices required to be given under this Agreement shall be in writing and served by personal delivery or by email, as provided below, to the parties at the following addresses: AGENCY: Mr. Randall Kippenbrock, P.E. Executive Director Santa Fe Solid Waste Management Agency 149 Wildlife Way Santa Fe, NM 87506 Email: rkippenbrock@sfswma.org CONTRACTOR: Mr. Frank Pugsley, P.E. Director of Environmental / Partner Parkhill 3000 Internet Blvd, Suite 550 Frisco, TX 75034 Email: Fpugsley@parkhill.com B. Notice sent by recognized overnight delivery service shall be effective only upon actual receipt thereof at the office of the addressee set forth above, and any such notice Page 9 of 11 delivered at a time outside of normal business hours shall be deemed effective at the opening of business on the next business day. C. Notice sent by email shall be effective only upon receipt of the original by delivery service unless written confirmation is sent by the recipient of the email stating that the notice has been received, in which case the notice shall be deemed effective as of the date specified in the confirmation. D. Any party may change its address for purposes of this Article by giving notice to the other party as herein provided. Delivery of any copies as provided herein shall not constitute delivery of notice hereunder. 24. COMPLIANCE WITH LAWS AND REGULATIONS; PROHIBITION OF BRIBES, GRATUITIES, AND KICKBACKS Contractor shall comply with all applicable federal, state, and local laws and regulations throughout the term of this Agreement. Contractor expressly acknowledges that the New Mexico Procurement Code, NMSA 1978, Sections 13-1-28 through 13-1-199, imposes civil and criminal penalties for its violation, and New Mexico criminal statutes impose penalties for bribes, gratuities, and kickbacks. Page 10 of 11 IN WITNESS WHEREOF, the parties have executed this Agreement on the date set forth below. SANTA FE SOLID WASTE MANAGEMENT AGENCY: ________________________ _________________ Lee Garcia Date: Chairperson, Joint Powers Board CONTRACTOR: ________________________ __________________ Frank Pugsley, P.E. Date Director of Environmental / Partner Parkhill APPROVED AS TO FORM: ________________________ __________________ Nancy R. Long Date: Agency Attorney Page 11 of 11 EXHIBIT A Scope of Services Caja Del Rio Landfill - Maintenance Shop and Administration Building Design 149 Wildlife Way, Santa Fe, NM 87506 PROJECT UNDERSTANDING It is our understanding that the Agency wishes to procure the following professional services for the Caja del Rio Landfill: Design, procurement/bidding, and construction phase services for a new Maintenance Shop. Design, procurement/bidding, and construction phase services for a new Administration Building. Based on our experience and the information provided through communication with the Agency, we have developed the following Proposal. SCOPE OF SERVICES PHASE 1 Task 01: Conceptual Design Parkhill will collaborate with the Agency to refine the scope for each of the two buildings by evaluating existing conditions, determining future space requirements, and recommend a proposed conceptual design with preliminary conceptual budgets for each facility. This task consists of: Task 1.1: Site Evaluation a. Data Collection. Collect base data including staffing levels, site/floor plans, and review existing projects and studies related to this Study (if available). b. Site Evaluation. Visit existing Site and review available data and drawings to evaluate site conditions and physical characteristics and identify constraints and opportunities that may impact development such as access, views, building organization, circulation, parking, topography, drainage, and available utilities. c. Site Plan Preparation. A basic site plan will be prepared from publicly available aerial imagery and parcel data for use as a base map for planning purposes. d. Task 1.1 Deliverables: Site Base Map. Task 1.2: Needs Assessment a. Staffing projections. Review and aggregate staffing projections provided by the Agency for the purpose of developing space requirements by position and department. b. Stakeholder Meetings. Obtain input from users through questionnaires and meetings regarding facility needs related to space, function and operations to establish design vision and performance criteria for each facility and department. c. Space Program. Prepare an architectural space program quantifying the spatial requirements for facilities and site development considering the intended functions by users. d. Task 1.2 Deliverables: Staffing Projections, Architectural Space Program. Task 1.3: Concept Design a. Evaluate alternatives and development options for capital improvements to address current and future facility needs including renovation, expansion/ additions, relocation, new facility construction, and land acquisition. b. Concept Plans. Prepare conceptual design drawings including diagrammatic blocking floor plans illustrating the layout of major functional spaces, and site master plans illustrating the layout of buildings, site access, circulation, parking, and other site development requirements. c. Task 1.3 Deliverables: Concept Plans. Task 1.4: Budget a. Budget. Develop a list of recommended improvements with preliminary conceptual budgets including construction and other soft costs. b. Task 1.4 Deliverables: Summary presentation report documenting analysis, findings, and recommendations of the study including site evaluation, need assessment, concept design, and master plan task deliverables. Meetings a. Kickoff Meeting. One virtual meeting with staff advisory committee. b. Progress Meetings. Virtual, up to two per month. c. Stakeholder Meetings. Virtual, up to two meetings. d. Presentations. One virtual meeting to deliver the final summary presentation. Agency-provided Items a. The Agency will provide the following items required for the Project: i. Existing Site drawings such as surveys and site/floor plans. PHASE 2 (FUTURE PHASES) Task 02: Topographic Survey Parkhill, will perform or procure a detailed topographic survey of the Maintenance Shop and Administration Building site to establish accurate baseline conditions. The survey will include: Horizontal and vertical control based on local benchmarks. Elevations, contours, and grades to support earthwork calculations and drainage design. Location of existing utilities, pavement, and aboveground features. Documentation of site constraints (e.g., easements, right-of-way boundaries) if not available. This information will serve as the foundation for site design, ensuring that final construction documents reflect precise, real-world conditions. Task 03: Development of 30 Percent Drawings Following completion and approval of the Facilities Study, Parkhill will proceed with the development of a 30 percent plan set for the proposed Administration Building and Maintenance Shop at the Caja del Rio Landfill. This phase represents the initial transition from conceptual design to technical documentation and will establish the foundation for all subsequent design phases. The 30 percent plan set will translate the findings of the facilities study (including programmatic needs, site constraints, and conceptual layouts) into preliminary technical drawings, system narratives, and a refined cost estimate. This effort ensures that both the Agency and Parkhill share a unified understanding of the design intent, constructability, and overall project direction prior to advancing into detailed design. Key Objectives: Develop a Basis of Design summarizing project design criteria, building codes, and performance standards guiding the development of all design disciplines. Prepare preliminary site and civil plans that define building placement, vehicle and pedestrian traffic patterns, grading concepts, drainage patterns, and preliminary utility connections. Advance the architectural design developed during Phase 1 to depict floor plans, building elevations, and key sections that illustrate space layouts, functional adjacencies, and architectural character consistent with the conceptual design. Establish preliminary structural, mechanical, and electrical system concepts, including major components, equipment locations, and preliminary distribution layouts. Identify preliminary materials, finishes, and system selections that reflect durability, maintainability, and sustainability. Develop an updated Opinion of Probable Cost (OPC) based on the 30 percent design drawings and narratives to confirm budget alignment. Conduct an Agency Review Workshop to present the 30 percent design package, receive feedback, and confirm approval to advance to the 60 percent design phase. Deliverables: Basis of Design Narrative outlining design criteria, assumptions, and system concepts. Preliminary Civil, Architectural, Structural, Mechanical, and Electrical Drawings representing approximately 30 percent completion. Preliminary Site Layout and Grading Plan showing major site features, circulation, and utility connections. Preliminary Materials and Systems Summary identifying proposed construction materials and major building systems. 30 percent EOPC with supporting assumptions and value-engineering notes. Agency Review Workshop including presentation materials, meeting minutes, and a written response log documenting comments and resolutions. Task 04: Development of 60 Percent Drawings At this stage, the design process will transition into detailed production. The 60 percent drawings will include at minimum: Site grading and drainage design Pavement sections and traffic routing Preliminary structural and architectural layouts Utility connections and relocations Preliminary details for systems and equipment The 60 percent design package will be submitted to the Agency for review and comment. This milestone provides a critical checkpoint for the Agency to confirm that the original design intent has been carried forward and meets expectations. Comments from this review will be used to refine the design prior to advancing to later phases. Task 05: Opinion of Probable Cost Cost control is a critical element throughout the project. Parkhill will prepare and update the Opinion of Probable Cost at each major design stage. The estimate will: Draw upon manufacturer quotes for equipment and specialty items. Incorporate local supplier pricing for materials and commodities. Reference bid data from similar maintenance shop and administration building projects completed in the region. By maintaining an evolving estimate, we will align design decisions with the Agency’s budget expectations and ensure fiscal accountability. Task 06: Constructability Review At the 60 percent completion stage, a constructability review will test the contract documents by applying the principle of the four C's. A construction contract that is on schedule and within budget should evolve from documents that are: Clear - The terms are unambiguous and meanings and intent are without confusion. Complete - All relevant details are included, material descriptions are specific, contract clauses accommodate pertinent considerations, and duplications or gaps are avoided. The contractor does not have to guess what is to be constructed. Comprehensive - The contract provisions are broad enough to cover the Project, are effectively correlated, and give adequate attention to all parts of the Project. Comprehensible - The design is competently delineated in accordance with industry standards and is understandable, reasonable, and intelligible. The Parkhill Constructability Review Team is made up of construction specialists and senior engineers/architects; in concert with experienced engineers and inspectors who understand the unique requirements of solid waste Maintenance Shop and Administration Buildings. For instance, standard industrial concrete floors for the maintenance work bays will not provide sufficient wearability for solid waste manipulation and must be enhanced with both structural and surface enhancements. The Team will complete this essential task prior to finalizing the design of the Project. Task 07: Development of 90 Percent Drawings and Project Technical Specifications At this stage, Parkhill will advance the design effort into near-final documentation. The objective is to deliver a comprehensive package that is essentially ready for bidding, while still allowing the Agency a final opportunity to provide input prior to completion. Key Activities: Final Integration of Disciplines: Civil, structural, architectural, mechanical, and electrical designs will be fully coordinated to eliminate conflicts between systems. This includes grading plans, building sections, foundation details, mechanical room layouts, and electrical one-line diagrams as necessary. Detailed Facility Design: The layout will incorporate final decisions on equipment types, structural materials, and operational spaces such as maintenance shop work floor, load-out bay, and vehicle circulation routes. Technical Specifications: Complete contract specifications will be prepared in industry standard format, covering all materials, workmanship standards, and performance requirements. Particular attention will be given to the unique needs of maintenance shop and administration building operations, including high-wear concrete specifications, HVAC and ventilation systems, and traffic control devices. Procurement and Contract Forms: The 90 percent package will include draft Bid Forms, Agreements, Bonds, and General Conditions, ensuring the Agency can proceed seamlessly to the procurement stage. Deliverables: 90 percent complete drawing set (all disciplines). Draft Project Manual with specifications and contract forms. Updated cost estimate for budget confirmation. Task 08: Final Construction Documents The 90 percent documents will be submitted to the Agency for review, providing a final opportunity for stakeholders to verify alignment with project goals and operational requirements. Parkhill will then integrate all Agency comments and finalize the Final Construction Document package. Key Activities: Agency Review Coordination: Facilitate workshops or review meetings with Agency staff to discuss and clarify design decisions, with a focus on operational efficiency, maintenance requirements, and regulatory compliance. Resolution of Comments: Each Agency comment will be documented, tracked, and addressed. Where alternative solutions exist, Parkhill will provide recommendations with pros/cons for Agency decision-making. Final Package Production: Incorporation of all revisions into the final construction drawings and Project Manual. This ensures the bid package is complete, consistent, and ready for public advertisement. Deliverables: Final sealed drawings ready for bidding and construction. Final specifications and bid documents (Project Manual) ready for bidding and construction. Final Engineering Opinion of Probable Cost. Task 09: Procurement Support The procurement process requires active management to ensure competitiveness and transparency while providing bidders with sufficient clarity to prepare accurate proposals. Parkhill will support the Agency through every step. Should the project proceed through the traditional procurement process Parkhill will provide the following services: Key Activities: Bid Document Distribution: Make final plans and specifications available through standard plan rooms, Agency procurement portals, and directly to prospective bidders (if required). Pre-Bid Conference: Organize and lead a pre-bid meeting to explain project requirements, walk bidders through the site, and respond to technical questions. Addenda Preparation: Draft and issue addenda to clarify or modify documents as needed, ensuring bidders have the latest information. Bidder Support: Provide timely responses to Requests for Information (RFIs) from contractors and suppliers. Bid Evaluation: Open bids with Agency representatives, tabulate results, verify contractor qualifications, and confirm completeness of bids. Recommendation of Award: Provide a written recommendation for award to the lowest responsible and responsive bidder, with rationale for Agency decision-making. Contract Execution Support: Assist the Agency with contract finalization, bonds, and insurance verification prior to issuing the Notice to Proceed. Deliverables: Pre-bid conference summary and attendance record. Addenda (as required). Bid tabulation and evaluation report. Award recommendation. Task 10: Construction Phase Services Construction phase services are critical to ensure that the project is built in accordance with the design intent, budget, and schedule. Parkhill will provide technical expertise and contract administration throughout the construction process. Key Activities: Pre-Construction Services: Facilitate the pre-construction meeting with the general contractor, review project schedule, establish communication protocols, and confirm submittal requirements. Shop Drawing & Submittal Review: Review and approve contractor submittals for compliance with the design, including structural steel, precast elements, electrical systems, and specialty equipment. Construction Observation: Provide periodic site visits during critical construction activities to observe progress, identify deviations, and resolve field issues. Our team will document observations through field reports with photos and recommendations. Progress Meetings: Attend regular progress meetings with the contractor and Agency staff to review schedule, cost, and quality issues. Change Management: Evaluate contractor change order requests and provide recommendations to the Agency regarding cost and time impacts. Quality Assurance: Ensure workmanship, materials, and construction methods meet specifications. Special inspections (such as concrete testing, weld inspections, etc.) will be coordinated as needed. Final Observation: Conduct pre-final and final walkthroughs, prepare punch lists, and verify completion of all work. Project Closeout: Review and approve as-built drawings, verify O&M manuals, and recommend final acceptance. Deliverables: Pre-construction meeting summary. Periodic field reports with photos and observations. Submittal review log. Change order evaluations. Punch list documentation and final acceptance letter. Approved as-built drawings. COMPENSATION Our fee for the Scope of Services described above is based on a not-to-exceed fee and will be billed on a time and materials method on a monthly basis. Parkhill’s current hourly rate schedule is provided as Exhibit A. Invoices will reflect the prevailing NMGRT rate at the time of invoicing. Our Opinion of Probable Cost (OPC) provided as Table 1 is structured to identify an itemized cost of tasks and services. Table 1 Santa Fe Solid Waste Management Agency Caja del Rio Landfill Maintenance Shop and Administration Building Construction Engineering Opinion of Probable Cost Task Number Task Professional Labor Expenses Subcontractor Not-To- Exceed Fee 01 Conceptual Design $25,000 $0 $0 $25,000.00 NMGRT (6.8750%): $1,718.75 Project Total (including NMGRT): $26,718.75 New Mexico State law requires Gross Receipts Tax and excise tax to be added to all labor costs. All New Mexico Gross Receipts tax will be in addition to the fees enclosed and will be a reimbursable expense. Invoices will reflect the prevailing NMGRT rate at the time of invoicing. SCHEDULE Based on the proposed scope of Phase 1 services, we anticipate a three (3) month project duration. Client: Project: Agreement Date: Location: CLASSIFICATION HOURLY RATE CLASSIFICATION HOURLY RATE CLASSIFICATION HOURLY RATE $67.00 Architect $166.00 Architect $259.00 $78.00 Civil Engineer $203.00 Civil Engineer $282.00 Electrical Engineer $198.00 Electrical Engineer $281.00 $108.00 Interior Designer $148.00 Interior Designer $211.00 Landscape Architect $160.00 Landscape Architect $226.00 $115.00 Mechanical Engineer $189.00 Mechanical Engineer $268.00 Structural Engineer $196.00 Structural Engineer $252.00 $127.00 Survey Tech $152.00 Professional Land Surveyor $235.00 Other Professional $146.00 Other Professional $219.00 $138.00 Architect $202.00 Architect $330.00 Architect $135.00 Civil Engineer $237.00 Civil Engineer $340.00 Civil Engineer $147.00 Electrical Engineer $232.00 Electrical Engineer $334.00 Electrical Engineer $150.00 Interior Designer $162.00 Interior Designer $241.00 Interior Designer $128.00 Landscape Architect $173.00 Landscape Architect $290.00 Landscape Architect $128.00 Mechanical Engineer $222.00 Mechanical Engineer $317.00 Mechanical Engineer $141.00 Structural Engineer $226.00 Structural Engineer $334.00 Structural Engineer $141.00 Survey Tech $185.00 Professional Land Surveyor $285.00 Survey Tech $120.00 Other Professional $172.00 Other Professional $277.00 Other Professional $126.00 Architect $246.00 Architect $146.00 Civil Engineer $281.00 Civil Engineer $165.00 Electrical Engineer $279.00 Electrical Engineer $170.00 Interior Designer $195.00 Interior Designer $135.00 Landscape Architect $211.00 Landscape Architect $135.00 Mechanical Engineer $266.00 Mechanical Engineer $162.00 Structural Engineer $250.00 Structural Engineer $160.00 Professional Land Surveyor $210.00 Survey Tech $130.00 Other Professional $192.00 Other Professional $133.00 The Schedule of Charges is incorporated into the Agreement for Services provided, effective January 1, 2025 through December 31, 2025. After December 31, 2025, invoices will reflect the Schedule of Charges currently in effect. SUPPORT STAFF II SUPPORT STAFF III SUPPORT STAFF IV SUPPORT STAFF V PROFESSIONAL LEVEL II PROFESSIONAL LEVEL V SUPPORT STAFF VI Parkhill Hourly Rate Schedule January 1, 2025 through December 31, 2025 SUPPORT STAFF I PROFESSIONAL LEVEL III PROFESSIONAL LEVEL VI PROFESSIONAL LEVEL I PROFESSIONAL LEVEL IV PROFESSIONAL LEVEL VII