Date: September 3, 2026 To: BDD Board From: Bradley Prada, BDD Facilities Manager Re: BDD Facilities Manager Monthly Update to the BDD Board This report outlines current progress on key facility projects and staffing as of September 2026. Updates include continued progress on the Design/Build project, insights from active Ranney well and San Juan-Chama Project site visits, and ongoing recruitment efforts. • Design/Build project The project team, comprising WWE, AECOM, and BDD staff, is finalizing the draft contract for the 30% design phase and anticipates completion prior to launching negotiations with the team selected through the RFQ process. • Ranney Well Site Visit BDD staff, WWE, and AECOM toured an active Ranney well construction site to evaluate construction methodologies and operational mechanics. Insights gained from this visit will directly inform the ongoing feasibility assessment. • San Juan Chama Project Tour BDD staff participated in an interagency tour of the SJCP diversions and contributing watershed. The site visits provided valuable coordination opportunities with various statewide governing agencies regarding long-term water conveyance and management. • Current Job Vacancy Updates BDD personnel are collaborating closely with City HR staff to fill open positions. Title Status Accounting Manager Candidate accepted, waiting on start date PUD Operator Ladder Posted, Closes 8/30/26 Automation & Security Administrator Completed interviews, none selected, waiting on Reposting Journeyman Electrician Waiting on Reclass