Attachment A Conditions of Approval and Technical Corrections 1. Table of Conditions of Approval 2. Table of Technical Corrections 3. Development Review Team Compiled Comments Case #2025-11753 & 11756 Planning Commission June 4, 2026 Land Use Department Case #2025-11753 & 11756 Planning Commission Staff Report 1802 Cerrillos Development Plan & Special Use Permit Conditions of Approval & Technical Corrections Conditions of Approval # Condition of Approval Dept. or Division To be completed: 1 DP-100: I don’t see PUD as part of your zoning on the City GIS. Please provide the PUD ordinance if located within one. Planning Prior to Public Hearing (COMPLETED) 2 Create a cover sheet for development plan (use page 1 of the attached template for reference on what should be included) Planning Prior to Public Hearing (COMPLETED) 3 Consolidate all lots of Block 2 in “The Capital Land and Townsite Co. Addition to Santa Fe NM” Planning Prior to Recordation 4 Consolidate Lots 13-20 of Block 3 in “The Capital Land and Townsite Co. Addition to Santa Fe NM” Planning Prior to Recordation 5 Provide proof of ownership of the alley in Block 3 Planning Prior to Public Hearing (COMPLETED) 6 Provide appropriate documentation connecting Lot 1 to the rest of the Development Plan in perpetuity Planning Prior to Recordation 7 Edit application letters and responses to approval criteria for both applications to make sure all references are to the old code sections & change all ‘CUA’ references to Special Use Permit (SUP). This is because your application was received before the new code became effective. Planning Prior to Public Hearing (COMPLETED) 8 Sign dimensions proposed in architectural plans are too large per 14-8.10(G)(8)(a): “For C-2, SC, and I properties located within the Cerrillos Road highway corridor protection district, the following standards shall apply: For one business establishment on a legal lot of record, not more than three signs are allowed, no one of which shall exceed fifty (50) square feet in area in corridor zone one. The total allowable sign area for all three signs shall not exceed one hundred fifty (150) square feet.” Revise sign sizing to meet this code criteria. Planning At time of Sign Permit 9 Delete list of Conditions of Approval on DP-102101 for now. I will let you know what conditions should be on there after we go to Planning Commission Planning Prior to Public Hearing (COMPLETED) 10 Fence around Site 2 mini storage units shall provide a visual buffer or screen and be constructed of opaque materials per SFCC 14-6.2(D)(3). Provide an elevation/detail of the proposed fencing material. Planning Prior to Recordation 11 Is fence 6 or 8 feet tall? DP says 6 ft and architectural plans say 8ft. Please revise to match. Planning Prior to Public Hearing (COMPLETED) 12 Architectural plans need to be updated to match revised building placement on Site 2 for setbacks. Site 2 setbacks are incorrectly described in “Site Plan Data” on A.101. “Side (South)” should say “Side (West).” Please also remove 15’ west side setback line on drawings for site 2. Planning Prior to Public Hearing (COMPLETED) Case #2025-11753 & 11756 Planning Commission June 4, 2026 Land Use Department Case #2025-11753 & 11756 Planning Commission Staff Report 1802 Cerrillos Development Plan & Special Use Permit Conditions of Approval # Condition of Approval Dept. or Division To be completed: 13 Architectural plans showing the layout/number of storage units on each floor is missing in new set. Please add this back in. Planning Prior to Public Hearing (COMPLETED) 14 A mural is included in the architectural renderings, but not architectural elevations. Please revise to match Planning Prior to Public Hearing (COMPLETED) 15 Provide architectural elevations for buildings 2, 3, and 4 Planning Prior to Public Hearing (COMPLETED) 16 Is this project planned to be built in phases? If so, provide a phasing plan. Planning Prior to Public Hearing (COMPLETED) 17 Please clarify ‘by others’ site work on plans to identify who will perform the work. Planning Prior to Public Hearing (COMPLETED. Applicant is to do work) 18 An approved Water Plan will be required for all new public water infrastructure and fire services. Water Engineeri ng Prior to Public Hearing (COMPLETED) 19 An approved Agreement to Construct and Dedicate (ACD) will be required with the Water Division for all new public water infrastructure and fire services. Water Engineeri ng Prior to Building Permit 20 A separate irrigation meter will be required if the total landscaped area is 1,000 square feet or greater. An approved backflow prevention device shall be installed beyond the meter on any new irrigation service. Water Engineeri ng At Time of Development 21 Any re-grading of site over existing water mains shall maintain a minimum of 4 feet of cover and not exceed 5 feet of cover. Depth of existing main to be adjusted to maintain a minimum of 4 feet of cover and not exceed 5 feet of cover if site grading impacts these depth requirements. Water Engineeri ng At Time of Development 22 An approved Development Water Budget including a 9.8% contingency per SFCC 14-7.7 will be required. A technical evaluation request for a Development Water Budget needs to be submitted to the City Water Division for review. Water Resource s Prior to Public Hearing (COMPLETED) 23 An applicant may choose to develop a detailed, alternative Development Water Budget for the development project supported by reliable data that demonstrates that the anticipated annual water use will be less than if based on the Water Division’s standard formulas per SFCC 14-7.7(D) (2). Water Resource s Prior to Public Hearing (COMPLETED) 24 An Agreement to Construct and Dedicate (ACD) from the Water Division will be required for all new public water infrastructure or fire services. An approved Development Water Budget, including Landscape Irrigation Budget and a 9.8% Contingency is required prior to processing the ACD. Water Resource s Prior to Building Permit 25 Each lot shall be served by separate water service at the time of development. Water Resource s Prior to Building Permit Case #2025-11753 & 11756 Planning Commission June 4, 2026 Land Use Department Case #2025-11753 & 11756 Planning Commission Staff Report 1802 Cerrillos Development Plan & Special Use Permit Conditions of Approval # Condition of Approval Dept. or Division To be completed: 26 An agreement for metered service (AMS) will be required to install new services, including water offset fees. Water Resource s Prior to Building Permit 27 Developer should provide certification that its engineers have provided NMDOT project development engineers opportunity to review site plans in accordance with the departments proposed redesign and reconstruction of Cerrillos Rd. Traffic Prior to Public Hearing (COMPLETED) 28 A detailed signage and striping plan for all required on-street signage, pavement markings, and any related regulatory/directional sign shall be submitted for review and approval by Public Works Traffic Prior to Building Permit 29 No further review required unless a future proposed utility plan exceeds 550-linear feet of utility lines Archaeol ogy - 30 Shall reference correct year of IFC (C-100) and Appendix B for average-sprinkler reduction (FC-101) Fire Prior to Public Hearing (COMPLETED) 31 The public right-of-way will be constructed in accordance with the approved Public Works project S100681 (NM 14/Cerrillos Road), including a 5-foot stamped concrete buffer and a full 6-foot sidewalk. Parks and Open Space Prior to Public Hearing (COMPLETED) 32 Provide discussion in the drainage narrative of how the stormwater will be directed to the ponding areas. Include how water will be directed from roof drains. Terrain Managem ent Prior to Recordation 33 Provide flow directional arrows on grading and drainage plan especially showing flow from roof drains to ponding areas. Ponding area volumes must be established for each ponding area showing dimensions. Label each pond with a pond number and the volume. Depressed areas for all landscaped areas are encouraged, but the official ponding areas for the required storage must be verifiable in the future. The conveyance of water to those areas must be shown on the plans and verifiable in the future. Show curb cuts for water to enter landscaped areas. Terrain Managem ent Prior to Recordation 34 Include pond sections and show how ponds will overflow. Terrain Managem ent Prior to Recordation 35 Sidewalk should align with Cerrillos Road Plan specs and city street design standards which require 5’ landscape buffer between street and pedestrian path (See comments on plans for detail). Sidewalk width should be at least 6’, but also made as wide as possible on Cerrillos. FHWA and AASHTO guidance support a separated bike facility given the vehicle speeds and volumes here. By expanding the sidewalk to the minimum for a shared use path (10’ ) this would better align with federal guidance. MPO Prior to Public Hearing (COMPLETED) Case #2025-11753 & 11756 Planning Commission June 4, 2026 Land Use Department Case #2025-11753 & 11756 Planning Commission Staff Report 1802 Cerrillos Development Plan & Special Use Permit Conditions of Approval # Condition of Approval Dept. or Division To be completed: 36 Driveway conflicts on NW Fourth street should be minimized by consolidating driveways or minimizing the driveway width to ensure one-way circulation MPO Prior to Public Hearing (COMPLETED) 37 Ensure safe pedestrian access to site from each street frontage and sidewalk and also between all 3 parcels. How are conflicts between cars and pedestrians crossing 4th from parking on site 1 to site 2 going to be managed and minimized? Crosswalk should be setback from driveways at least 20 ft. MPO Prior to Public Hearing (COMPLETED) 38 Pedestrian Access Routes should aim for right angles. Skewed angles can be challenging for wheelchairs to maneuver safely. Minimize awkward angles and ensure there is sufficient landing pad for maneuvering MPO Prior to Public Hearing (COMPLETED) 39 Provide conversations with NMDOT so City staff can better understand NMDOT recommendations for this project. MPO Prior to Public Hearing (COMPLETED) 40 Shall comply with the most currently adopted International Fire Code (IFC) and adopted city ordinances upon building permit approval Fire Prior to Building Permit 41 Shall maintain access to apparatus access roads in and around construction sites in compliance with IFC 2021, Chapter 33 Fire Safety, and During Construction and Demolition. Fire During Construction 42 Shall confirm construction timing coordination with NMDOT. Planning Prior to Building Permit 43 The applicant will provide a full Construction Staging Plan for Land Use approval. Given the proximity of the proposed worksite to high-traffic areas, a controlled construction plan is required prior to recordation. Planning Prior to Recordation 44 Prior to recordation of the Development Plan, the applicant shall submit a mural / public art plan for review and approval by the Land Use Department. The mural / public art plan shall include: (1) reproduction of the existing Empire Builders mural on the exterior of the building in a location visible to the public; (2) a second exterior mural in a location visible to the public, with the location to be agreed upon by the applicant and staff; and (3) confirmation that the artist or artists hired to complete both murals will be residents of Santa Fe. The mural / public art plan shall identify mural locations, dimensions, artist(s), materials, and maintenance responsibility. Final implementation shall be consistent with the approved Development Plan, applicable conditions of approval, and applicable City requirements. Planning Commission / Land Use Department Prior to Recordation Technical Corrections # Technical Correction Dept. or To be completed: Case #2025-11753 & 11756 Planning Commission June 4, 2026 Division 1 DP-100: Existing conditions plan should be line work, not an image (Images get difficult to read when copying) Planning Prior to Public Hearing (COMPLETED) 2 DP-100 – Overlays: Please also list Suburban Archaeological Review District Planning Prior to Public Hearing (COMPLETED) 3 DP-100 – Lot Size: please break the lot size into the 4 existing lots for clarity Planning Prior to Public Hearing (COMPLETED) 4 DP-100 – Legal Lot Information: Add book/page information for lots. Add Legal Lot information for 1750 Cerrillos Rd. Planning Prior to Public Hearing (COMPLETED) 5 DP-100: Delineate 200ft buffer around property Planning Prior to Public Hearing (COMPLETED) 6 DP-101: Cerrillos Rd is spelled wrong (also spelled wrong on other sheets) Planning Prior to Public Hearing (COMPLETED) 7 DP-101: Zoning description is incorrect Planning Prior to Public Hearing (COMPLETED) 8 DP-101: Clearly depict Site 1 and Site 2 on drawing Planning Prior to Public Hearing (COMPLETED) Case #2025-11753 & 11756 Planning Commission June 4, 2026 Land Use Department Case #2025-11753 & 11756 Planning Commission Staff Report 1802 Cerrillos Development Plan & Special Use Permit Technical Corrections # Technical Correction Dept. or Division To be completed: 9 DP-101: Legal Description and Site Area – description of 1750 Cerrillos Rd is missing from both of these sections Planning Prior to Public Hearing (COMPLETED) 10 DP-101: Building Height – building height must be included Planning Prior to Public Hearing (COMPLETED) 11 DP-101: Open Space – incorrect code citation. This code references South Highway Corridor Protection District, not Cerrillos Rd Overlay. Change to SFCC 14-7.5(D) Planning Prior to Public Hearing (COMPLETED) 12 Add descriptions/dimensions of all open space provided (might be easier to visually depict on a new sheet) Planning Prior to Public Hearing (COMPLETED) 13 DP-101: Add clarification on the calculation of number of parking spaces Planning Prior to Public Hearing (COMPLETED) 14 Add Case #2025-11753 & 11756 to all relevant sheets Planning Prior to Public Hearing (COMPLETED) 15 Add a column to architectural points analysis explaining how you met each point designation. Planning Prior to Public Hearing (COMPLETED) 16 DP-103: Parking – delete “parks & open space – as determined by the city” Planning Prior to Public Hearing (COMPLETED) 17 DP-101: Fill in floodplain note #17 Planning Prior to Public Hearing (COMPLETED) 18 Applicant and City Water staff will work together to address main looping during the review of the water plan (see attached memo) Water Engineeri ng Prior to water plan approval (COMPLETED) 19 Existing Drainage Plan (sheet C-302) has a drainage calc. table labeled “post-development stormwater calculations. Verify this the correct table for this sheet and relabel to pre- development stormwater calcs. Also question whether this is correct table, as the existing volumes are less than post- development volumes on next sheet, however site plan reduces impervious area Parks and Open Space Prior to Recordation 20 Please label each pond, provide drawings for each pond including inlet & outlet structures, storage volumes, location of sediment measuring post, and landscape materials. Ensure grading notes reflect plan. Parks and Open Space Prior to Recordation 21 Planting Note #1 (LP-501): This note should be revised to reference the City of Santa Fe landscape requirements rather than Doña Ana County landscape requirements. Parks and Open Space Prior to Recordation 22 Fencing oddly crosses retention pond (C-201) Parks and Open Space - 23 The dog park should be designed and constructed to capture the first flush of surface runoff in order to reduce water quality impacts. As currently depicted, the grading plan does not direct runoff in a manner that would enable the pond to function as intended (sheet -304) Parks and Open Space Prior to Recordation Case #2025-11753 & 11756 Planning Commission June 4, 2026 Land Use Department Case #2025-11753 & 11756 Planning Commission Staff Report 1802 Cerrillos Development Plan & Special Use Permit Technical Corrections # Technical Correction Dept. or Division To be completed: 24 Parking lot traffic islands appear to have 60 square feet of permeable surface. Code 14-8.4(H)(4)(IV) requires 90 square feet of permeable surface. Landscap ing Prior to Recordation 25 Austrian pine at the main building at the southwest parking space is located to close to the curb and gutter. This tree at that location will cause curb and gutter and parking lot damage. Adjust tree to the center of the landscape area or choose a better size tree for this location. Entrance trees into the parking area should be centered in the planters to prevent future parking lot, curb, and gutter damage. Landscap ing Prior to Recordation 26 The Landscape is bunched into the property boundaries, extend the Landscape to the perimeters of the proposed sidewalks at Berry Ave and Fifth St. Review for easements, before plant material and irrigation location placements. Landscap ing Prior to Recordation 27 Provide shrubs to the landscape for parking lot screening at Cerrillos Road, Fourth St., and Berry Ave. per city code 14- 8.4(H)(3). Landscap ing Prior to Recordation 28 Provide frontage landscaping for CRHC zone 1 as required pre code 14-5.5 - HIGHWAY CORRIDOR PROTECTION DISTRICTS (B) CRHC Cerrillos Road Highway Corridor Protection District at the northeast parking lot. Landscap ing Prior to Recordation 29 Provide shrub planting within the planter bed along the boundary wall at the northeast parking lot. Landscap ing Prior to Recordation 30 Review plantings at traffic sight triangles for height compliance for a 3–8-foot visibility window. Landscap ing Prior to Recordation 31 Utilize organic mulch within the landscape particularly at mass plantings. Provide wood mulch shredded or chipped 4-inches in depth without weed fabric. Landscap ing Prior to Recordation 32 Provide fencing information and detail. Landscap ing Prior to Recordation 33 Irrigation system design is incomplete. Provide the remaining zone layouts. Landscap ing Prior to Recordation 34 Provide the correct details from the LIDS manual for the Manual Drain, Backflow Preventer. Landscap ing Prior to Recordation 35 Provide a water budget for the first three months of the Turf establishment period. Landscap ing Prior to Recordation 36 Turf grass sod or turf grass seed mixes installed within the city limits shall contain no more than twenty-five percent Kentucky Bluegrass. Landscap ing Prior to Recordation 37 Photometrics do not meet Code requirements. See Article 14-8.6(D)(2) and revise for compliance. 74-points exceed the maximum illumination for any point. (Highlighted numbers attached are out of compliance) Landscap ing Prior to Recordation 38 Include attached notes Terrain Managem Prior to Recordation Case #2025-11753 & 11756 Planning Commission June 4, 2026 Land Use Department Case #2025-11753 & 11756 Planning Commission Staff Report 1802 Cerrillos Development Plan & Special Use Permit Technical Corrections # Technical Correction Dept. or Division To be completed: ent 39 Current analysis shows a violation: an increase in peak stormwater flows is not allowed per city code 14-8.2(D)(4)(b) (i) Terrain Managem ent Prior to Recordation 40 Include 2 additional drainage analysis for the 1-year, 1-hour, and 100-year, 24-hour, required to show compliance for any frequency storm event up to the 100-year, 24-hour. Please See city code 14-8.2(D)(4)(b)(i) “except as otherwise required by this Section 14-8.2, the stormwater runoff peak flow rate discharged from a site shall not exceed pre- development conditions for any frequency storm event up to the one percent chance, twenty-four-hour storm event at each discharge point;” Terrain Managem ent Prior to Recordation 41 Show on the drainage and terrain management plans: roof drain pattern and downspouts/canales, and means of stormwater conveyance (swales, catch basins, storm drainpipe, curb cuts, etc.) to stormwater control features Terrain Managem ent Prior to Recordation 42 Please provide more information on how runoff Coefficients were selected from the NMDOT Manual, include the figure/table number, cover type, % impervious cover, etc. Terrain Managem ent Prior to Recordation 43 Please Verify how the runoff volumes are calculated, The Rational Method is not an acceptable method to calculate runoff volume per NMDOT Drainage Design Manual, July 2018, section 403, Limitations: “Runoff volumes may not be computed with the Rational Formula Method or Modified Rational Formula Method (not included in this Drainage Design Manual”. Terrain Managem ent Prior to Recordation 44 Include an acceptable runoff volume analysis for stormwater quality volume for a 0.68-inch (90% percentile, or roughly the 1-year, 1-hour storm) event. This runoff volume must be contained/retained on site, to reduce pollution per EPA NPDES MS4, see city code 14-8.2(A)(13). This volume must infiltrate in 24 hours per city code 14- 8.2(D)(4)(c)(ii), It is encouraged that the Stormwater quality volume design is incorporated into the landscape, to also comply with landscape code rainwater harvesting requirements 14-8.4(E)(1) “The landscaping plan shall include passive water harvesting for landscape irrigation purposes as a minimum requirement” the minimum recess depth for retention and water harvesting areas is 6 inches. Terrain Managem ent Prior to Recordation February 27, 2026 Case # 2025-11753 & 2025-11756 Lisa Martinez B Constructiv LLC 3201-C Zafarano Dr #111 Santa Fe, NM 87507 Joseph Karnes Sommer Karnes & Associates, LLP 125 Lincoln Ave #221 Santa Fe, NM 87501 Dear Lisa & Joseph, Your application was received on December 19, 2025 for: Case #2025-11753 & 2025-11756. 1750 and1802 Cerrillos Rd, 3 RD Berry Ave, and 1361 Fourth St Development Plan and Special Use Permit. B Constructiv LLC and Sommer Karnes & Associates LLP, “Agents” for Amatren, LLC, Owner and Applicant (“Applicant”), request approval of a Development Plan and Special Use Permit to redevelop the properties listed above into a self- storage facility with community office and gathering spaces. The property is zoned C-2 (General Commercial) and is within the Suburban Archaeological Review District. (Alexa Hempel, Case Manager, anhempel@santafenm.gov). This application has been reviewed by Planning Division staff (Staff) and the City’s Development Review Team (DRT). Attached are the initial DRT review comments including conditions of approval and technical corrections. Additional corrections may follow throughout the development review and permitting processes. I would like to highlight and summarize the following key items. Those items in green font must be completed prior to planning commission. Items in black will need to be completed at later dates (refer to attachments), but it is in your best interest to begin working on them sooner rather than later. February 25, 2026 Initial Review Memo for 1802 Cerrillos Rd Page 2 of 7 A. Initial Staff & DRT Review Summary Your development plan and special use permit applications have been reviewed by the DRT and the following necessary revisions have been identified: 1. Planning a. DP-100: I don’t see PUD as part of your zoning on the City GIS. Please provide the PUD ordinance if located within one. b. Create a cover sheet for development plan (use page 1 of the attached template for reference on what should be included) c. Sign dimensions proposed in architectural plans are too large per 14-8.10(G)(8)(a): “For C-2, SC, and I properties located within the Cerrillos Road highway corridor protection district, the following standards shall apply: For one business establishment on a legal lot of record, not more than three signs are allowed, no one of which shall exceed fifty (50) square feet in area in corridor zone one. The total allowable sign area for all three signs shall not exceed one hundred fifty (150) square feet.” Revise sign sizing to meet this code criteria d. Consolidate all lots of Block 2 in “The Capital Land and Townsite Co. Addition to Santa Fe NM” e. Consolidate Lots 13-20 of Block 3 in “The Capital Land and Townsite Co. Addition to Santa Fe NM” f. Provide proof of ownership of the alley in Block 3 g. Provide appropriate documentation connecting Lot 1 to the rest of the Development Plan in perpetuity h. Edit application letters and responses to approval criteria for both applications to make sure all references are to the old code sections & change all ‘CUA’ references to Special Use Permit (SUP). This is because your application was received before the new code became effective. i. DP-100: Existing conditions plan should be line work, not an image (Images get difficult to read when copying) j. DP-100 – Overlays: Please also list Suburban Archaeological Review District k. DP-100 – Lot Size: please break the lot size into the 4 existing lots for clarity l. DP-100 – Legal Lot Information: Add book/page information for lots. Add Legal Lot information for 1750 Cerrillos Rd. m. DP-100: Delineate 200ft buffer around property n. DP-101: Cerrillos Rd is spelled wrong (also spelled wrong on other sheets) o. DP-101: Zoning description is incorrect p. DP-101: Clearly depict Site 1 and Site 2 on drawing q. DP-101: Legal Description and Site Area – description of 1750 Cerrillos Rd is missing from both of these sections r. DP-101: Building Height – building height must be included s. DP-101: Open Space – incorrect code citation. This code references South Highway Corridor Protection District, not Cerrillos Rd Overlay February 25, 2026 Initial Review Memo for 1802 Cerrillos Rd Page 3 of 7 t. Add descriptions/dimensions of all open space provided (might be easier to visually depict on a new sheet) u. DP-101: Add clarification on the calculation of number of parking spaces v. Add Case #2025-11753 & 11756 to all relevant sheets w. Add a column to architectural points analysis explaining how you met each point designation 2. Fire a. Shall reference correct year of (IFC) (C-100) and Appendix B for average- sprinkler reduction (FC-101) 3. Archaeology a. No further review is required unless a future proposed utility plan exceeds 550-linera feet of utility lines 4. ADA a. Must remove and replace all damaged existing sidewalks. b. Must relocate northeast fire hydrant out of sidewalk path on Cerrillos Rd. c. Must remove and replace all existing, abandoned curb cuts/drive entrances and replace with barrier curb. SFCC 23-3.5 d. ADA Parking stalls and aisles must be added to east parking lot for buildings 2, 3, for the offices and restrooms. e. Remove City of Albuquerque Civil Details Sheets # C-506, and # C-507 and add NMDOT Series 608 in place. f. Must bring Existing Corner curb ramps to ADA compliance. 5. MPO a. Sidewalk should align with Cerrillos Road Plan specs and city street design standards which require 5’ landscape buffer between street and pedestrian path (See comments on plans for detail). Sidewalk width should be at least 6’, but also made as wide as possible on Cerrillos. FHWA and AASHTO guidance support a separated bike facility given the vehicle speeds and volumes here. By expanding the sidewalk to the minimum for a shared use path (10’ ) this would better align with federal guidance. b. Driveway conflicts on NW Fourth street should be minimized by consolidating driveways or minimizing the driveway width to ensure one-way circulation c. Ensure safe pedestrian access to site from each street frontage and sidewalk and also between all 3 parcels. How are conflicts between cars and pedestrians crossing 4th from parking on site 1 to site 2 going to be managed and minimized? d. Pedestrian Access Routes should aim for right angles. Skewed angles can be challenging for wheelchairs to maneuver safely. Minimize awkward angles and ensure there is sufficient landing pad for maneuvering e. Make changes as shown in redlines on plans (attached) 6. Traffic a. See attached letter from Wilson & Company dated 2/20/26 certifying its concurrence with the developer’s “Initial Traffic Assessment” (ITA). February 25, 2026 Initial Review Memo for 1802 Cerrillos Rd Page 4 of 7 b. Developer should provide certification that its engineers have provided NMDOT project development engineers opportunity to review site plans in accordance with the department’s proposed redesign and reconstruction of Cerrillos Rd c. A detailed signage and striping plan for all required on-street signage, pavement markings, and any related regulatory/directional signs shall be submitted for review and approval by Public Works 7. Parks & Open Space a. The public right-of-way will be constructed in accordance with the approved Public Works project S100681 (NM 14/Cerrillos Road), including a 5-foot stamped concrete buffer and a full 6-foot sidewalk. b. Existing Drainage Plan (sheet C-302) has a drainage calc. table labeled “post- development stormwater calculations. Verify this the correct table for this sheet and relabel to pre-development stormwater calcs. Also question whether this is correct table, as the existing volumes are less than post-development volumes on next sheet, however site plan reduces impervious area. c. Please label each pond, provide drawings for each pond including inlet & outlet structures, storage volumes, location of sediment measuring post, and landscape materials. Ensure grading notes reflect plan. d. Planting Note #1 (LP-501): This note should be revised to reference the City of Santa Fe landscape requirements rather than Doña Ana County landscape requirements. e. Fencing oddly crosses retention pond (C-201) f. The dog park should be designed and constructed to capture the first flush of surface runoff in order to reduce water quality impacts. As currently depicted, the grading plan does not direct runoff in a manner that would enable the pond to function as intended (sheet -304) 8. Terrain Management/Engineering a. Provide discussion in the drainage narrative of how the stormwater will be directed to the ponding areas. Include how water will be directed from roof drains. b. Provide flow directional arrows on grading and drainage plan especially showing flow from roof drains to ponding areas. Ponding area volumes must be established for each ponding area showing dimensions. Label each pond with a pond number and the volume. Depressed areas for all landscaped areas are encouraged, but the official ponding areas for the required storage must be verifiable in the future. The conveyance of water to those areas must be shown on the plans and verifiable in the future. Show curb cuts for water to enter landscaped areas. c. Include pond sections and show how ponds will overflow. d. Include attached notes. e. A financial guarantee will be required for all public and quasi-public infrastructure. The guarantee must be in place prior to recordation of development plan. f. Current analysis shows a violation: an increase in peak stormwater flows is not allowed per city code 14-8.2(D)(4)(b)(i) g. Include 2 additional drainage analysis for the 1-year, 1-hour, and 100-year, 24- hour, required to show compliance for any frequency storm event up to the 100- year, 24-hour. Please See city code 14-8.2(D)(4)(b)(i) “except as otherwise required by this February 25, 2026 Initial Review Memo for 1802 Cerrillos Rd Page 5 of 7 Section 14-8.2, the stormwater runoff peak flow rate discharged from a site shall not exceed pre- development conditions for any frequency storm event up to the one percent chance, twenty-four-hour storm event at each discharge point;” h. Show on the drainage and terrain management plans: roof drain pattern and downspouts/canales, and means of stormwater conveyance (swales, catch basins, storm drainpipe, curb cuts, etc.) to stormwater control features i. Please provide more information on how runoff Coefficients were selected from the NMDOT Manual, include the figure/table number, cover type, % impervious cover, etc. j. Please Verify how the runoff volumes are calculated, The Rational Method is not an acceptable method to calculate runoff volume per NMDOT Drainage Design Manual, July 2018, section 403, Limitations: “Runoff volumes may not be computed with the Rational Formula Method or Modified Rational Formula Method (not included in this Drainage Design Manual”. k. Include an acceptable runoff volume analysis for stormwater quality volume for a 0.68-inch (90% percentile, or roughly the 1-year, 1-hour storm) event. This runoff volume must be contained/retained on site, to reduce pollution per EPA NPDES MS4, see city code 14-8.2(A)(13). This volume must infiltrate in 24 hours per city code 14-8.2(D)(4)(c)(ii), It is encouraged that the Stormwater quality volume design is incorporated into the landscape, to also comply with landscape code rainwater harvesting requirements 14-8.4(E)(1) “The landscaping plan shall include passive water harvesting for landscape irrigation purposes as a minimum requirement” the minimum recess depth for retention and water harvesting areas is 6 inches. 9. Landscaping/Irrigation/Lighting a. Parking lot traffic islands appear to have 60 square feet of permeable surface. Code 14-8.4(H)(4)(IV) requires 90 square feet of permeable surface. b. Austrian pine at the main building at the southwest parking space is located to close to the curb and gutter. This tree at that location will cause curb and gutter and parking lot damage. Adjust tree to the center of the landscape area or choose a better size tree for this location. Entrance trees into the parking area should be centered in the planters to prevent future parking lot, curb, and gutter damage. c. The Landscape is bunched into the property boundaries, extend the Landscape to the perimeters of the proposed sidewalks at Berry Ave and Fifth St. Review for easements, before plant material and irrigation location placements. d. Provide shrubs to the landscape for parking lot screening at Cerrillos Road, Fourth St., and Berry Ave. per city code 14-8.4(H)(3). e. Provide frontage landscaping for CRHC zone 1 as required pre code 14-5.5 - HIGHWAY CORRIDOR PROTECTION DISTRICTS (B) CRHC Cerrillos Road Highway Corridor Protection District at the northeast parking lot. f. Provide shrub planting within the planter bed along the boundary wall at the northeast parking lot. g. Review plantings at traffic sight triangles for height compliance for a 3–8- foot visibility window. February 25, 2026 Initial Review Memo for 1802 Cerrillos Rd Page 6 of 7 h. Utilize organic much within the landscape particularly at mass plantings. Provide wood mulch shredded or chipped 4-inches in depth without weed fabric. i. Provide fencing information and detail. j. Irrigation system design is incomplete. Provide the remaining zone layouts. k. Provide the correct details from the LIDS manual for the Manual Drain, Backflow Preventer. l. Provide a water budget for the first three months of the Turf establishment period. m. Turf grass sod or turf grass seed mixes installed within the city limits shall contain no more than twenty-five percent Kentucky Bluegrass. n. Photometrics do not meet Code requirements. See Article 14-8.6(D)(2) and revise for compliance. 74-points exceed the maximum illumination for any point. (Highlighted numbers attached are out of compliance) 10. Water Engineering a. An approved Water Plan will be required for all new public water infrastructure and fire services. b. An approved Agreement to Construct and Dedicate (ACD) will be required with the Water Division for all new public water infrastructure and fire services. c. A separate irrigation meter will be required if the total landscaped area is 1,000 square feet or greater. An approved backflow prevention device shall be installed beyond the meter on any new irrigation service. d. Any re-grading of site over existing water mains shall maintain a minimum of 4 feet of cover and not exceed 5 feet of cover. Depth of existing main to be adjusted to maintain a minimum of 4 feet of cover and not exceed 5 feet of cover if site grading impacts these depth requirements e. Applicant and City Water staff will work together to address main looping during the review of the water plan (see attached memo) 11. Water Resources a. An approved Development Water Budget including a 9.8% contingency per SFCC 14-7.7 will be required. A technical evaluation request for a Development Water Budget needs to be submitted to the City Water Division for review. b. An applicant may choose to develop a detailed, alternative Development Water Budget for the development project supported by reliable data that demonstrates that the anticipated annual water use will be less than if based on the Water Division’s standard formulas per SFCC 14-7.7(D)(2). c. An Agreement to Construct and Dedicate (ACD) from the Water Division will be required for all new public water infrastructure or fire services. An approved Development Water Budget, including Landscape Irrigation Budget and a 9.8% Contingency is required prior to processing the ACD. d. Each lot shall be served by separate water service at the time of development. e. An agreement for metered service (AMS) will be required to install new services, including water offset fees. 12. Wastewater a. Response will be sent separately February 25, 2026 Initial Review Memo for 1802 Cerrillos Rd Page 7 of 7 Please review all attached Staff and DRT comments, revise your submittals to address those items in green and resubmit for review. Once revised submittals are accepted, a public hearing date may be scheduled. Please let me know if you have any questions or concerns. Thank you, Alexa Hempel Senior Planner, Planning and Land Use Department Attachments: 1. Planning DRT Memo 2. Fire DRT Memo 3. Archaeology DRT Memo 4. ADA DRT Memo 5. MPO 6. Traffic DRT Memo 7. Parks & Open Space DRT Memo 8. Terrain Management/Engineering DRT memo 9. Landscaping/Irrigation/Lighting DRT Memo 10. Water Engineering DRT Memo 11. Water Resources DRT Memo 12. Wastewater DRT Memo – will be sent separately Form Updated: April 2024 Development Review Team (DRT) Comment Form DRT Review Schedule – 9-12+ weeks* Initial DRT Comments are due to the case planner within three weeks of the DRT Application Intake meeting. Initial DRT review should confirm that the application is complete (i.e. Water Budget has been submitted) and/or identify additional submittals or corrections (i.e. Water Budget needs revision). The case planner will review and convey all Initial DRT Comments to the applicant via a Review Memo. The applicant must respond to all Initial DRT Comments and submit a revised application for Final Review. Final DRT Comments are due to the case planner within two weeks of receipt of the revised application. The case planner will review and convey all Final DRT Comments to the applicant in a Final Review Memo. The complete DRT Review Timeline can range from 9-12+ weeks, depending on the complexity and quality of the application and the total number of applications under review. Review Memo Revised Application Final DRT Comments Timing of Conditions of Approval + Technical Corrections While all DRT conditions of approval and technical corrections must be met by the applicant, the timing of compliance varies. In the “Must be completed by” column in the following tables, please time your conditions of approval and technical corrections to the following development review stages: a. Prior to Public Hearing – these conditions/technical corrections must be addressed before the case may move forward to the public hearing phase of the Development Review Process. b. Prior to Recordation – these conditions/technical corrections may be resolved after the public hearing but must be addressed before the Development Plan or Subdivision plat is recorded. c. Prior to Building Permit Approval – these conditions/technical corrections can be addressed during the building permit review process, but prior to issuance of the permit. d. During Construction – these conditions/technical corrections can be addressed during construction. Development Review Process Flow Chart *See the 2024 Development Review Schedule for details DRT Review Timeline: Initial DRT Comments Final Review Memo Application Received DRT Application Intake DRT Initial Review Comments Due 2/9/26 2/20/26 Form Updated: April 2024 Date: 2/10/26 DRT Member: Alexa Hempel Dept/Div: Current Planning Case No.: #2025-11753/11756 Case Planner: Alexa Hempel Conditions of Approval and Technical Corrections Tables Review by this division/department has determined that this application will meet applicable standards if the following Conditions of Approval and Technical Corrections are met: Case # Conditions of Approval: Must be completed by: Applicant response**: 1. DP-100: I don’t see PUD as part of your zoning on the City GIS. Please provide the PUD ordinance if located within one. Prior to Public Hearing 2. Create a cover sheet for development plan (use page 1 of the attached template for reference on what should be included) Prior to Public Hearing 3. Sign dimensions proposed in architectural plans are too large per 14-8.10(G)(8)(a): “For C-2, SC, and I properties located within the Cerrillos Road highway corridor protection district, the following standards shall apply: For one business establishment on a legal lot of record, not more than three signs are allowed, no one of which shall exceed fifty (50) square feet in area in corridor zone one. The total allowable sign area for all three signs shall not exceed one hundred fifty (150) square feet.” Revise sign sizing to meet this code criteria. At time of Sign Permit 4. Consolidate all lots of Block 2 in “The Capital Land and Townsite Co. Addition to Santa Fe NM” Prior to Recording Development Plan 5. Consolidate Lots 13-20 of Block 3 in “The Capital Land and Townsite Co. Addition to Santa Fe NM” Prior to Recording Development Plan 6. Provide proof of ownership of the alley in Block 3 Prior to Planning Commission 7. Provide appropriate documentation connecting Lot 1 to the rest of the Development Plan in perpetuity Prior to Recording Development Plan 8. Edit application letters and responses to approval criteria for both applications to make sure all references are to the old code sections & change all ‘CUA’ references to Special Use Permit (SUP). This is because your application was received before the new code became Prior to Public Hearing Form Updated: April 2024 effective. Technical Corrections: Must be completed by: Applicant response**: 1. DP-100: Existing conditions plan should be line work, not an image (Images get difficult to read when copying) Prior to Public Hearing 2. DP-100 – Overlays: Please also list Suburban Archaeological Review District Prior to Public Hearing 3. DP-100 – Lot Size: please break the lot size into the 4 existing lots for clarity Prior to Public Hearing 4. DP-100 – Legal Lot Information: Add book/page information for lots. Add Legal Lot information for 1750 Cerrillos Rd. Prior to Public Hearing 5. DP-100: Delineate 200ft buffer around property Prior to Public Hearing 6. DP-101: Cerrillos Rd is spelled wrong (also spelled wrong on other sheets) Prior to Public Hearing 7. DP-101: Zoning description is incorrect Prior to Public Hearing 8. DP-101: Clearly depict Site 1 and Site 2 on drawing Prior to Public Hearing 9. DP-101: Legal Description and Site Area – description of 1750 Cerrillos Rd is missing from both of these sections Prior to Public Hearing 10. DP-101: Building Height – building height must be included Prior to Public Hearing 11. DP-101: Open Space – incorrect code citation. This code references South Highway Corridor Protection District, not Cerrillos Rd Overlay Prior to Public Hearing 12. Add descriptions/dimensions of all open space provided (might be easier to visually depict on a new sheet) Prior to Public Hearing 13. DP-101: Add clarification on the calculation of number of parking spaces Prior to Public Hearing 14. Add Case #2025-11753 & 11756 to all relevant sheets Prior to Public Hearing 15. Add a column to architectural points analysis explaining how you met each point designation. Prior to Public Hearing **The Applicant must respond to the condition of approval or technical correction, indicating they have met the requirement and providing a reference in their revised submittals. If the applicant has not met the requirement, they must indicate as much and provide a response. The applicant should be aware that the following code provisions or other requirements will apply to future phases of development of this project: 1. [list any additional items] Form Updated: April 2024 2. Explanation of Conditions or Corrections (if needed): Form Updated: April 2024 (see following pages for notes required) PROJECT NAME DEVELOPMENT PLAN CITY OF SANTA FE APPROVALS NOTARIZED STORMWATER AGREEMENT Approval by Santa Fe Planning Commission at their meeting of , 20 , as Case No. . STORMWATER AGREEMENT: PROPERTY OWNERS(S) HEREBY AGREE THAT ALL STORMWATER EASEMENTS AND ANY OTHER DRAINAGE AND STORMWATER MANAGEMENT IMPROVEMENTS ARE ON PRIVATE PROPERTY AND WILL BE MAINTAINED AND KEPT FULLY FUNCTIONAL AS ORIGINALLY DESIGNED AND CONSTRUCTED WITHIN PRIVATE PROPERTY BOUNDATIES BY THE PROPERTY OWNER AND SUBSEQUENT HEIRS, ASSIGNS, AND FUTURE OWNERS. THE CITY IS HEREBY GRANTED THE FOLLOWING: (1) ACCESS FOR INSPECTION OF SAID IMPROVEMENTS: (2) IN THE EVENT OF DRAINAGE AND STORMWATER MANAGEMENT IMPROVEMENT MAINTENANCE DEFICIENCY AND AFTER TEN (10) DAYS WRITTEN NOTICE TO THE REPECTIVE PROPERTY OWNER, TO ENTER ENTER AND RETORE FULL FUNCTIONAL CAPACTIY OF THE DRAINAGE AND STORMWATER MANAGEMENT IMPROVEMENTS; AND, (3) TO LIEN THE PROPERTY FOR BOTH DIRECT AND INDIRECT COSTS ASSOCIATED WITH SUCH WORK. BY SIGNATURE AFFIXED TO THIS INSTRUCMENT, THE PROPERTY OWNER(S) APPROVE AND AGREE THAT THIS AGREEMENT IS BINDING PERPETUALLY, RUNNING WITH THE LAND ON PRESENT AND FUTURE OWNERS, HEIRS, AND ASSIGNS. OWNER'S PRINTED NAME OWNER'S SIGNATURE / DATE THE FOREGOING INSTRUMENT WAS ACKNOWLEDGED BEFORE ME THIS DAY OF . 20 (OR EQUAL). NOTARY PUBLIC MY COMMISSION EXPIRES City Jurisdiction including Section, Township and Range Planning Commission Chairperson Date CASE # Planning Commission Secretary Date Approved by the City of Santa Fe Land Use Department: City Planner Date City Engineer of Land Use Date AFFIDAVIT KNOW ALL PERSONS BY THESE PRESENTS THAT THE UNDERSIGNED OWNERS HAVE CAUSED THIS FINAL DEVELOPMENT PLAN TO BE PREPARED. ALL THAT APPEARS ON THIS PLAN IS MADE WITH THE FREE CONSENT AND IN ACCORDANCE WITH THE DESIRES OF THE OWNER. [OWNER] THE FOREGOING WAS SWORN, ACKNOWLEDGED AND SUBSCRIBED BEFORE ME BY THIS DAY OF , 20 . NOTARY PUBLIC MY COMMISSION EXPIRES CITY OF SANTA FE DRAINAGE NOTES: 1. NO VARIANCES ARE APPROVED FOR THIS DEVELOPMENT PLAN. THE CITY CODE AND APPLICATION CHAPTERS SHALL GOVERN AND APPLY TO THIS DEVELOPMENT PLAN IN ITS ENTIRETY. 2. CITY OF SANTA FE DRAINAGE: 2.1. SUBJECT TO THE APPROVAL OF THE CITY OF SANTA FE PERMIT AND DEVELOPMENT REVIEW DIVISION STAFF, STORM DRAINAGE AND EROSION SEDIMENT CONTROL IMPROVEMENTS SHALL BE EXECUTED IN CONJUNCTION WITH THE CONSTRUCTION OF EACH SEGMENT OF ROADS AND UTILITIES. THESE IMPROVEMENTS SHALL BE COMPLETED AND INSPECTED PRIOR TO THE ISSUANCE OF BUILDING PERMITS. 2.2. MAINTENANCE OF PRIVATE DRAINAGE EASEMENTS AND DRAINAGE FACILITIES IS THE RESPONSIBILITY OF THE OWNER. THE CITY OF SANTA E IS HEREBY GRANTED THE RIGHT TO ACCESS AND INSPECT THE EASEMENT AND DRAINAGE FACILITIES AT THE DISCRETION OF PERSONS OR PROPERTY RESULTING FROM THE CITY'S REASONABLE EXERCISE TO THEIR ACCESS AND INSPECTION RIGHTS. COUNTY OF SANTA FE } SS STATE OF NEW MEXICO I HEREBY CERTIFY THAT THIS INSTRUMENT WAS FILED AND RECORDED ON THIS DAY OF , 20 , AT O'CLOCK M, AND WAS DULY RECORDED IN BOOK PAGE OF THE RECORDS OF SANTA FE COUNTY. SHEET INDEX: DP-100 DEVELOPMENT PLAN COVER SHEET WITNESS MY HAND AND SEAL OF OFFICE KATHARINE E. CLARK COUNTY CLERK, SANTA FE COUNTY DP-101 DEVELOPMENT PLAN NOTES AND CONDITIONS OF APPROVAL DP-102 EXISTING CONDITIONS PLAN North VICINITY MAP DEPUTY DP-103 PROPOSED DEVELOPMENT SITE PLAN OWNER / DEVELOPER: ARCHITECT: MEP ENGINEER: CASE #: 2025-010010 ABC HOLDINGS, LLC 1254 Easy Street Anywhere, NM 87654 XYZ Architecture 1234 Best Street Anywhere, NM 87654 MEP Engineering, Inc 52 Design Street Anywhere, NM 87654 ADDRESS: W E S Engineer Ratios 1:10, 1:20, 1:30, 1:40. 1:50 or 1:60 LINETYPE LEGEND PROPERTY LINE ROW LINE EASEMENT SETBACKS SURVEYOR: INC Surveys, LLC 432 Early Street Anywhere, NM 87654 PLANNER: Planning Expediting 234 Everest Street Anywhere, NM 87654 LANDSCAPE: Evergreen Landscape 12 Peony Street Anywhere, NM 87654 CIVIL ENG: Civil Engineering 25 Transect Street Anywhere, NM 87654 SHEET NAME: DEVELOPMENT PLAN COVER SHEET SHEET #: DP-100 SHEET # OF PROJECT NAME CONDITIONS OF APPROVAL CITY OF SANTA FE NOTES 1. COMPLIANCE WITH GUNNISON'S PRAIRIE DOG ORDINANCE SHALL BE COMPLETED PRIOR TO GRADING OPERATIONS. 2. FENCES, WALLS OR OTHER OBSTRUCTIONS SHALL NOT BE PLACED OR CONSTRUCTED ACROSS PUBLIC SANITARY SEWER EASEMENTS. 3. UTILITY EXPANSION CHARGES SHALL BE PAID AT THE TIME OF BUILDING PERMIT APPLICATION FOR EACH LOT. CONTACT THE CITY OF SANTA FE PERMIT AND DEVELOPMENT REVIEW DIVISION TO PAY THESE CHARGES. 4. EACH LOT SHALL BE SERVED THROUGH A SEPARATE SEWER AND WATER SERVICE. 5. ALL PROPOSED CHANGES TO THE APPROVED IMPROVEMENT PLANS SHALL RECEIVE PRIOR APPROVAL BY THE CITY OF SANTA FE LAND USE DEPARTMENT. 6. COMPLY WITH THE CURRENT COSF WATER CONSERVATION STAGE. 7. PROPERTY DEVELOPMENT IS REQUIRED TO COMPLY WITH THE PROVISIONSOF COSF ORDINANCE NO. 2008-02 (IMPACT FEES). 8. PROPERTY DEVELOPMENT, BOTH PUBLIC AND PRIVATE OWNERSHIP, SHALL COMPLY WITH THE COSF ORDINACNCE NO. 2002-20 (TERRAIN AND STORMWATER MANAGEMENT) AT THE TIME OF BUILDING PERMIT APPLICATION. 9. BUILDING SETBACKS SHALL APPLY TO ALL PERMANENT STRUCTURES, INCLUDING ACCESSORY STRUCTURES. 10. PROPERTY DEVELOPMENT IS REQUIRED TO COMPLY WITH APPLICABLE PROVISIONS OF CHAPTER 14, LAND DEVELOPMENT CODE, SFCC 1987 AND SUBSEQUENT AMENDMENT. 11. PROPERTY DEVELOPMENT IS REQUIRED TO COMPLY WITH THE PROVISIONS OF EACH APPLICABLE CITY OF SANTA FE ORDINACNCE ADOPTED PRIOR TO FINAL PLAT RECORDING WITH THE COUNTY CLERK OR SUBMITTAL WITH BUILDING PERMIT APPLICATION THAT MODIFIES ANY PROVISIONS OF REQUIREMENTS CALLED FOR IN CHAPTER 14, LAND DEVELOPMENT CODE, SFCC 1987 AND SUBSEQUENTAMENDMENTS. 12. PROPERTY DEVELOPMENT IS SUBJECT TO THE PROVISIONS OF SECTION 14-8 4(F) (5). "PLANT MATERIAL STANDARDS", WHEREIN PRESERVATION OF SIGNIFICANT TREES IS REQUIRED. 13. FIRE DEPARTMENT ACCESS SHALL BE MAINTAINED THROUGHOUT ALL DEVELOPMENT CONSTRUCTION PHASES AS PER IFC14-19.1 14. AN APPROVED WATER SUPPLY FOR FIRE PROTECTION, EITHER TEMPORARY OR PERMANENT SHALL BE MADE AVAILABLE AS SOON AS COMBUSTIBLE MATERIAL ARRIVES ON THE SITE AS PER IFC 14-12.1. 15. PERMANENT TRAFFIC CONTROL DEVICES SHALL BE INSTALLED PER APPROVED. 16. ALL IMPROVEMENTS NOT MAINTAINED AND OPERATED BY PUBLIC UTILITIES OR GOVERNMENTAL BODIES WHICH AFFECT THE GENERAL WELL BEING OF THIS DEVELOPMENT WILL BE OWNED AND MAINTAINED BY THE HOMEOWNERS ASSOCIATION. 17. THIS PARCEL LIES WITHIN ZONE "X" AREAS OUTSIDE THE 0.2% ANNUAL CHANCE FLOODPLAIN AS PER F.I.R.M. PANEL# DATED . 18. FURTHER SUBDIVISION OF LOTS IS PROHIBITED. 19. THE LOTS SHOWN HEREON ARE SUBJECT TO THE DECLARATION OF COVENANTS, CONDITIONS, AND RESTRICTIONS FOR HOMEOWNERS' ASSOCIATION, INC. RECORDED IN THE RECORDS OF SANTA FE COUNTY, NEW MEXICO ON THE DAY OF 2025 AS NSTRUMENT # . 20. THIS DEVELOPMENT SHALL COMPLY WITH THE MOST CURRENT REQUIREMENTS OF THE AMERICAN WITH DISABILITIES ACT (ADA). DRAINAGE FACILITIES DESIGN NOTE ALL STORM WATER DETENTION / RETENTION AREAS SHALL DRAIN WITHIN 24 HOURS OF A STORM EVENT AS PER ARTICLE 14-8.2(D)(4)(c)(i) PUBLIC UTILITY EASEMENTS PUBLIC UTILITY EASEMENTS SHOWN ON THIS PLAT ARE GRANTED FOR THE COMMON AND JOINT USE OF: A. PUBLIC SERVICE COMPANY OF NEW MEXICO CORPORTATION, (PNM ELECTRIC) FOR INSTALLATION, MAINTENANCE, AND SERVICE OF OVERHEAD AND UNDERGROUND ELECTRICAL LINES, TRANFORMERS, AND OTHER EQUIPMENT AND RELATE FACILITIES REASONABLY NECESSARY TO PROVIDE ELECTRICAL SERVICES. B. NEW MEXICO GAS COMPANY (NMGCO) FOR INSTALLATION, MAINTENANCE, AND SERVICE OF NATURAL GAS LINES, VALVES AND OTHER EQUIPMENT AND FACILITIES REASONABLY NECESSARY TO PROVIDE NATURAL GAS SERVICES. C. LUMEN TECHNOLOGIES FOR THE INSTALLATION, MAINTENANCE, AND SERVICE OF SUCH LINES, CABLE, AND OTHER RELATED EQUIPMENT AND FACILITIES REASONABLY NECESSARY TO PROVIDE COMMUNICATION SERVICES. D. XFINITY &/OR LUMEN TECHNOLOGIES FOR THE INSTALATION, MAINTENANCE, AND SERVICE OF SUCH LINES, CABLE, AND OTHER RELATED EQUIPMENT AND FACILITIES REASONABLY NECESSARY TO PROVIDE CABLE SERVICES. E. CITY OF SANTA FE (PUBLIC WATER AND PRIVATE SEWER) FOR THE INSTALLATION, MAINTENANCE AND SERVICE OF LIES AND OTHER EQUIPMENT AND FACILITIES REASONABLY NECESSARY TO PROVIDE SERVICES TO PUBLIC UTILITY EASEMENTS. INCLUDED IS THE RIGHT TO BUILD, REBUILD, CONSTRUCT, RECONSTRUCT, LOCATE,RELOCATE, WITHIN THE EASEMENT, CHANGE, REMOVE, REPLACE, MODIGY, RENEW, OPERATE AND MAINTAIN FACILITIES FOR PURPOSES DESCRIBED ABOVE, TOGETHER WITH FREE ACCESS TO, FROM, AND OVER SAID EASEMENTS, WITH THE RIGHT AND PRIVILEGE OF GOING UPON, OVER AND ACROSS ADJOINING LANDS OF GRANTER FOR THE PURPOSE SET FORTH HEREIN AND WITH THE RIGHT TO UTILIZE THE RIGH-OF-WAY AND EASEMENT TO EXTEND SERVICES TO CUSTOMERS OF GRANTEE, INCLUDING SUFFICIENT WORKING AREA SPACE FOR ELECTRIC TRANSFORMERS, WITH THE RIGHT AND PRIVILEGE TO TRIM AND REMOVE TREES, SHRUBS, OR BUSHES WHICH INTERFERE WITH THE PURPOSES SET FORTH HEREIN. NO BUILDING, SIGN, POOL (ABOVEGROUND OR SUBSURFACE), HOT TUB, CONCRETE OR WOOD POOL DECKING, OR OTHER STRUCTURE SHALL BE ERECTED OR CONSTRUCTED ON SAID EASEMENTS, NOR SHALL ANY WELL BE DRILLED OR OPERATED THEREON. EASEMENTS FOR ELECTRIC, TRANSFORMERS / SWITCHGEARS, AS INSTALLED, SHALL EXTEND TEN (10) FEET IN FRONT OF TRANSFORMER / SWITCHGEAR GEARS AND FIVE (5) FEET ON EACH SIDE. A. QWEST CORP, D/B/A CENTURYLINK QC FOR INSTALLATION, MAINTENANCE AND SERVIE OF ALL BURIED AND AERIAL COMMUNICATION LINES AND OTHER RELATED EQUIPMENT AND FACILITIES REASONABLY NECESSARY TO PROVIDE COMMUNICATION SERVICES, INCLUDING BUT NOT LIMITED TO ABOVE GROUND PEDESTAL AND CLOSURES. THIS PLAT HAS BEEN APPROVED FOR EASEMENT PURPOSES ONLY. THE SIGNING OF THIS PLAT DOES NOT IN ANY WAY GUARANTEE TELEPHONE SERVICES TO THE DEVELOPMENT. UTILITY DISCLAIMER: IN APPROVING THIS PLAT, PUBLIC SERVICE COMPANY OF NEW MEXICO (PNM) AND NEW MEXICO GAS COMPANY (NMGC) DID NOT CONDUCT A TITLE SEARCH OF THE PROPERTIES SHOWN HEREON. CONSEQUENTLY, PNM AND NMGC DO NOT WAIVE OR RELEASE ANY EASEMENT OR EASEMENT RIGHTS WHICH MAY HAVE BEEN GRANTED BY PRIOR PLAT, REPLAT OR OTHER DOCUMENT AND WHICH ARE NOT SPECIFICALLY DESCRIBED AND SHOWN ON THIS PLAT. DUST CONTROL ALL ON-SITE SOIL DISTURBING CONSTRUCTION ACTIVITIES SHALL BE ADDRESSED AND PROVIDE MEASURES TO MITIGATE OR CONTROL DUST FROM BEING TRANSPORTED OFFSITE AND POLLUTING NEIGHBOING PROPERTIES. ANY PERSON, OWNER, CONTRACTOR OR OPERATOR WHO CONDUCTS EARTHMOVING AND/OR DUST GENERATING ACTIVITIES IS RESPONSIBLE FOR IMPLEMENTING BEST MANAGEMENT PRACTICES (BMPS) IN ORDER TO MITIGATE OFF-PROPERTY TRANSPORT OF FUGITIVE DUST EMISSIONS. A PLAN, OR STORMWATER PREVENTION PLAN (SWPP) WHEN APPLICABLE, LISTING BEST MANAGEMENT PRACTICES (BMPS), SHALL BE PROVIDED TO THE CITY ENGINEER, OR THEIR DESIGNEE FOR REVIEW AND APPROVAL. THE APPROVED BMPS SHALL BE APPLIED TO THE GRADED AND/OR DISTURBED SOIL IN ORDER TO STABILIZE THE SITE. THE INITIAL BMP SHALL ADDRESS HOW THE CONTRACTOR WILL MINIMIZE THE AMOUNT OF DISTURBED SOIL, AND HOW THE CONTRACTOR WILL STABILIZE THE DISTURBED SURFACE AREA EXPOSED TO WIND OR VEHICLE TRAFFIC DURING CONSTRUCTION. CONDITIONS OF APPROVAL WATER DIVISION: 1. AN APPROVED WATER PLAN WILL BE REQUIRED FOR ALL NEW PUBLIC WATER INFRASTRUCTURE AND FIRE SERVICES. 2. AN APPROVED AGREEMENT TO CONSTRUCT AND DEDICATE (ACD) WILL BE REQUIRED FOR NEW PUBLIC WATER INFRASTRUCTURE AND FIRE SERVICES 3. ANY RE-GRADING OF SITE OVER EXISTING WATER MAINS SHALL MAINTAIN A MINIMUM OF 4 FEET OF COVER AND NOT EXCEED 5 FEET OF COVER. DEPTH OF EXISTING MAIN TO BE ADJUSTED TO MAINTAIN A MINIMUM OF 4 FEET OF COVER AND NOT EXCEED 5 FEET OF COVER IF SITE GRADING IMPACTS THESE DEPTH REQUIREMENTS. 4. A SEPARATE IRRIGATION METER WILL BE REQUIRED IF THE TOTAL LANDSCAPED AREA IS 1,000 SQUARE FEET OR GREATER. AN APPROVED BACKFLOW PREVENTION DEVICE SHALL ALSO BE INSTALLED BEYOND THE METER ON ANY NEW IRRIGATION SERVICE. MPO: 1. ADD A MIDBLOCK PEDESTRIAN CROSSING OF SOUTH MEADOWS BETWEEN PRIMO COLORES AND GALLERIA GRANDE OR ANOTHER SIMILAR LOCATION. 2. REDUCE THE RIGHT TURN LANE LENGTHS FROM SOUTH MEADOWS TO AVENIDA DE LOS PRADOS AND CAMINO DEL LLANO TO A MAXIMUM OF 70 FEET. 3. COMBINE THE EXITING RIGHT AND LEFT LANES ON CAMINO DEL LLANO INTO ONE SINGULAR EXITING LANE IF THE INTERSECTION CAN STILL PERFORM WITH A LEVEL OF SERVICE OF E OR HIGHER. 4. REDUCE THE LANE WIDTHS OF THE 60' ROW SECTION TO 10'. 5. REDUCE CURB RADII AT INTERSECTIONS WITHOUT BULB-OUTS TO THE MINIMUM SIZE THAT STILL ALLOWS VEHICLES TO TURN WITHOUT CROSSING THE CENTERLINE. 6. ADD SPEED HUMPS TO THE NORTH/SOUTH STRETCH OF CAMINO DEL LLANO, INCLUDING A RAISED CROSSWALK AT AVENIDA DE LOS PRADOS 7. ADD A CROSSWALK ACROSS CAMINO DEL LLANO FOR FUTURE RESIDENTS OF THE CONDOS TO SAFELY CROSS. 8. REDUCE THE INTERNAL DEVELOPMENT STREET SPEED LIMIT TO 20 MPH 9. MEET WITH CITY TRAFFIC ENGINEER TO DISCUSS REASONING FOR A THREE-WAY STOP AT AVENIDA DE LOS PRADOS AND CALLE CAMPO, OR MAKE IT A TWO-WAY STOP. TERRAIN MANAGEMENT: 1. THERE ARE SERIOUS CONCERNS REGARDING THE PONDING AREA THAT WAS TO BE A WATER HARVESTING AMENITY TO INCLUDE RAIN GARDENS AND PERMACULTURE. THE LARGE OPEN POND DESIGN DOES NOT PRESENT ANY OF THE ORIGINAL OBJECTIVES. IN ADDITION, THERE ARE SIGNIFICANT CONCERNS WITH HOW THE HOMEOWNERS ASSOCIATION CAN MAINTAIN THE REQUIRED FEATURES IN THEIR DRAINAGE MAINTENANCE RESPONSIBILITIES. PRIOR TO PLANNING COMMISSION 2. INCLUDE MANAGEMENT OF STORMWATER BEFORE IT LEAVES THE PROPERTY AND GETS TO THE POND/RAIN GARDEN. THERE SHOULD BE MANAGEMENT OF STORMWATER THROUGHOUT THE PROJECT SUCH AS RAIN GARDENS FLOWING THROUGH THE PARKWAYS. 3. THE TERRAIN MANAGEMENT REPORT CONTAINS NO EASILY IDENTIFIABLE INFORMATION ON WHAT IMPERVIOUS AREAS WERE ASSUMED FOR ANY OF THE SITE. IS ONSITE PONDING REQUIRED FOR EACH LOT? WAS ANY IMPERVIOUS SURFACE INCLUDED FOR EACH LOT? WAS ANY IMPERVIOUS SURFACE FOR PHASE 2 INCLUDED IN THE CALCULATIONS? WHAT IS THE POND VOLUME REQUIRED? INCLUDE THESE DISCUSSIONS. 4. IT APPEARS THAT PARKING IS ONLY ALLOWED ON ONE SIDE OF THE STREET AND IS NOT ALLOWED ON CURVES. PLEASE INCLUDE NO PARKING SIGNS THROUGHOUT THIS DEVELOPMENT. INCLUDE SIGNS WITH DIRECTIONAL ARROWS FOR NO PARKING AND “NO PARKING BETWEEN SIGNS” FOR LONGER STRETCHES.PRIOR TO RECORDATION. 5. PROVIDE DETAIL OF POND OVERFLOW ARMORING ON BERM EVEN THOUGH IT SHOULDN'T OVERTOP UP TO THE 1000-YEAR STORM EVENT.3. PROVIDE DETAILS OF DRAINAGE UNDER SIDEWALKS AND THROUGH PLANTER STRIPS. 6. ROADWAYS MUST BE 2” OF SPIII UNDER 2” OF SPIV. 7. STRIPING AND LIGHTING: PLEASE CONFIRM WITH PUBLIC WORKS IF THEY AGREE WITH THE STRIPING BETWEEN PARKING AREAS AND ROADWAY. ALSO CONFIRM LIGHTING REQUIREMENTS. THERE SHOULD BE LIGHTING PROVIDED AT ALL INTERSECTIONS. 8. OTHER COMMENTS HAVE BEEN PROVIDED ON THE PLANS. WASTEWATER: 1. NEED TO ADD A NEW SHEET 4-11A WHICH SHOWS ALL THE LANDSCAPING TREES AND THE 20 FOOT WIDE SEWER EASEMENT WITHOUT ALL THE SOIL TYPES SO THAT WE CAN SEE THE PROXIMITY OF THE TREES TO BE PLANTED IN RELATION TO THE SEWER EASEMENT BOUNDARY WITHOUT ALL THE OTHER CLUTTER 2. SHOW THE LOCATION AND THE HORIZONTAL DISTANCES BETWEEN THE WATER, SEWER, AND STORMWATER SEWER IN THE TYPICAL ROADWAY SECTIONS FOR THE 50- AND 60-FOOT ROW 3. SHOW THE DISTANCES BETWEEN THE WATER, SEWER AND STORMWATER PIPES IN THE P&P SHEETS CASE #: 2025-010010 ADDRESS: SHEET NAME: DEVELOPMENT PLAN CONDITIONS & NOTES SHEET #: DP-101SHEET # OF Company Title Block with Company Name, Company Address, Sheet Title PROJECT NAME EXISTING CONDITIONS PLAN Company Title Block with Company Name, Company Address, Sheet Title PROPERTY INFORMATION ZONING: OVERLAYS: HISTORIC STATUS: NATIONAL REGISTRY: LOT SIZE: EXISTING STRUCTURE SQ. FT.: EXISTING UTILITIES: FLOOD ZONE: LEGAL LOT INFORMATION RECORDING INFORMATION DESCRIBING CITY RECOGNIZED LEGAL LOT OF RECORD North CASE #: 2025-010010 W E LINETYPE LEGEND ADDRESS: SHEET NAME: EXISTING CONDITIONS PLAN SHEET #: DP-102SHEET # OF PROPERTY LINE S ROW LINE EASEMENT Engineer Ratios 1:10, 1:20, 1:30, 1:40. 1:50 or 1:60 SETBACKS PROJECT NAME SITE DEVELOPMENT PLAN SITE DATA & BUILDING INFO Company Title Block with Company Name, Company Address, Sheet Title PROJECT SITE: Acerage: 4.8 acres Flood Plain: N/A Flood Way Square Feet: N/A Net Acreage: 4.8 acres Peralta. Elsewhere in the subdistrict there are no required yards. SETBACK: Average of the Block ZONING: BCDMAR (Busines Capitol OPEN SPACE: District Marcy Subdistrict) 10% of the lot area OVERLAY ZONING: LANDSCAPE: Downtown and Eastside Historic District Landscape treatment required in yards and Historic Downtown Archaeological Review open space. Street trees and landscape District treatment required if planting strip exists. Asphalt or concrete pavement prohibited in BUILDINGS: planting strip. Building A: 8,000 Sq.Ft. Building B: 30,000 Sq.Ft. HEIGHT OF WALLS AND FENCES: Building C: 8,000 Sq.Ft. Maximum 4'. HEIGHT: PLACEMENT OF OFF STREET Marcy Subdistrict Maximum Height: 42' PARKING: Downtown and Eastside Historic District: Parking set to the rear of the property 14 Required parking for Building A: 14' Commercial Use: 350:1 Building B: 14' 46,000 gross square feet Building C: 14' 44 square feet Net leasable Required Parking - LOT COVERAGE: 132 Parking Spaces Marcy Subdistrict: No Requirement Provided Parking = 294 Parking Spaces BUILDING PLACEMENT: ADA Parking Spaces Front required yard equal to the average = 8 ADA Parking Spaces depth of existing front yards on the block ADA Van Accessible shall be required for (a) the east side of = 2 Parking Spaces Washington Avenue between Palace Avenue and Paseo de Peralta (Hillside); PORTALS IN THE ROW: and the west side of Grant Avenue None between Palace Avenue and Paseo de GUNNISON'S PRAIRIE DOG NOTE THE PROJECT SHALL COMPLY WITH THE PROVISIONS OF THE GUNNISON'S PRAIRIE DOG ORDINANCE (ARTICLE 14-8.12). DRAINAGE FACILITIES DESIGN NOTE ALL STORM WATER DETENTION / RETENTION AREAS SHALL DRAIN WITHIN 24 HOURS OF A STORM EVENT AS PER ARTICLE 14-8.2(D)(4)(c)(i) KEYED NOTES XX 1. PROPERTY LINE 12. PERIMETER FENCE / WALL 2. VEHICLE ENTRANCE 13. OPEN SPACE 3. FIRE HYDRANT 14. BIKE RACK 4. FIRELANE 15. WALL SIGN & ADDRESS 5. 5 FOOT CONCRETE WALK 16. EV CHARGING STATION North GENERAL NOTES 6. CONCRETE CURB & GUTTER 7. ASPHALT PAVEMENT 1. SOLID WASTER COLLECTION WILL BE PROVIDED BY THE CITY OF SANTA FE. 8. ADA COMPLIANT PARKING 9. ADA COMPLIANT RAMP 10. ADA CROSSWALK 11. REFUSE ENCLOSURE 2. EXTERIOR LUMINARIES SHALL COMPLY WITH CHAPTER 14-8.9 SFCC. 3. THE SITE SHALL COMPLY WITH INTERNATIONAL FIRE CODE (IFC) 2015. 4. THE FIRE DEPARTMENT ACCESS SHALL NOT BE LESS THAN 20' AND 26' AROUND THE RESIDENTIAL BUILDING. 5. THE SITE SHALL HAVE A WATER SUPPLY THAT MEETS FIR FLOW AND HAVE A DISTANCE TO THE NEAREST HYDRANT TO MEET IF REQUIREMENTS. 6. ALL FIRE DEPARTMENT ACCESS SHALL HAVE A GRADE NO GREATER THAN 10% . CASE #: 2025-0100107. FIRE LANE SURFACE SHALL BE ALL WEATHER AND SUPPORT 75,000 LBS. LEGEND DUST CONTROL ADDRESS: W E S LINETYPE LEGEND PROPERTY LINE ROW LINE 1 A ADA SPACE ADA ACCESS PATH BLDG NUMBER BLDG TYPE, REF ARCH PLANS 2 PEDESTRIAN CROSSWALK PARKING ROW COUNT BIKE RACK ALL ON-SITE SOIL DISTURBING CONSTRUCTION ACTIVITIES SHALL BE ADDRESSED AND PROVIDE MEASURES TO MITIGATE OR CONTROL DUST FROM BEING TRANSPORTED OFFSITE AND POLLUTING NEIGHBOING PROPERTIES. ANY PERSON, OWNER, CONTRACTOR OR OPERATOR WHO CONDUCTS EARTHMOVING AND/OR DUST GENERATING ACTIVITIES IS RESPONSIBLE FOR IMPLEMENTING BEST MANAGEMENT PRACTICES (BMPS) IN ORDER TO MITIGATE OFF-PROPERTY TRANSPORT OF FUGITIVE DUST EMISSIONS. A PLAN, OR STORMWATER PREVENTION PLAN (SWPP) WHEN APPLICABLE, LISTING BEST MANAGEMENT PRACTICES (BMPS), SHALL BE PROVIDED TO THE CITY ENGINEER, OR THEIR DESIGNEE FOR REVIEW AND APPROVAL. THE APPROVED BMPS SHALL BE APPLIED TO THE GRADED AND/OR DISTURBED SOIL IN ORDER TO STABILIZE THE SITE. THE INITIAL BMP SHALL ADDRESS HOW THE CONTRACTOR WILL MINIMIZE THE AMOUNT OF DISTURBED SOIL, AND HOW THE CONTRACTOR WILL STABILIZE THE DISTURBED SURFACE AREA EXPOSED TO WIND OR VEHICLE TRAFFIC DURING CONSTRUCTION. 1 SHEET NAME: SITE DEVELOPMENT PLAN SHEET #: DP-103 SHEET # OF EASEMENT Engineer Ratios 1:10, 1:20, 1:30, 1:40. 1:50 or 1:60 SETBACKS Form Updated: April 2024 Development Review Team (DRT) Comment Form DRT Review Schedule – 9-12+ weeks* Initial DRT Comments are due to the case planner within three weeks of the DRT Application Intake meeting. Initial DRT review should confirm that the application is complete (i.e. Water Budget has been submitted) and/or identify additional submittals or corrections (i.e. Water Budget needs revision). The case planner will review and convey all Initial DRT Comments to the applicant via a Review Memo. The applicant must respond to all Initial DRT Comments and submit a revised application for Final Review. Final DRT Comments are due to the case planner within two weeks of receipt of the revised application. The case planner will review and convey all Final DRT Comments to the applicant in a Final Review Memo. The complete DRT Review Timeline can range from 9-12+ weeks, depending on the complexity and quality of the application and the total number of applications under review. Initial DRT Comments Review Memo Revised Application Final DRT Comments Timing of Conditions of Approval + Technical Corrections While all DRT conditions of approval and technical corrections must be met by the applicant, the timing of compliance varies. In the “Must be completed by” column in the following tables, please time your conditions of approval and technical corrections to the following development review stages: a. Prior to Public Hearing – these conditions/technical corrections must be addressed before the case may move forward to the public hearing phase of the Development Review Process. b. Prior to Recordation – these conditions/technical corrections may be resolved after the public hearing but must be addressed before the Development Plan or Subdivision plat is recorded. c. Prior to Building Permit Approval – these conditions/technical corrections can be addressed during the building permit review process, but prior to issuance of the permit. d. During Construction – these conditions/technical corrections can be addressed during construction. Development Review Process Flow Chart *See the 2024 Development Review Schedule for details DRT Review Timeline: Final Review Memo Application Received DRT Application Intake DRT Initial Review Comments Due Form Updated: April 2024 Date: February 16, 2026 DRT Member: Geronimo Griego, Fire Marshal Dept/Div: Fire Prevention Division Case No.: 2025-11753_2025-11756_1802 Cerrillos_EmpireStorage_DP_SUP Case Planner: Conditions of Approval and Technical Corrections Tables Review by this division/department has determined that this application will meet applicable standards if the following Conditions of Approval and Technical Corrections are met: Case # Conditions of Approval: Must be completed by: Applicant response**: 1. Shall reference correct year of IFC (C-100) and Appendix B for average-sprinkler reduction (FC-101) Prior to Public Hearing 2. 3. 4. 5. 6. Technical Corrections: Must be completed by: Applicant response**: 1. 2. 3. 4. **The Applicant must respond to the condition of approval or technical correction, indicating they have met the requirement and providing a reference in their revised submittals. If the applicant has not met the requirement, they must indicate as much and provide a response. The applicant should be aware that the following code provisions or other requirements will apply to future phases of development of this project: 1. [list any additional items] 2. Explanation of Conditions or Corrections (if needed): IFC 2015 is the wrong referenced fire code. The city of Santa Fe most currently adopted fire code is IFC 2021. Also look at the most recently adopted fire code for the correct reference Appendix B Table B105.1 (1) Form Updated: April 2024 Form Updated: April 2024 Development Review Team (DRT) Comment Form DRT Review Schedule – 9-12+ weeks* Initial DRT Comments are due to the case planner within three weeks of the DRT Application Intake meeting. Initial DRT review should confirm that the application is complete (i.e. Water Budget has been submitted) and/or identify additional submittals or corrections (i.e. Water Budget needs revision). The case planner will review and convey all Initial DRT Comments to the applicant via a Review Memo. The applicant must respond to all Initial DRT Comments and submit a revised application for Final Review. Final DRT Comments are due to the case planner within two weeks of receipt of the revised application. The case planner will review and convey all Final DRT Comments to the applicant in a Final Review Memo. The complete DRT Review Timeline can range from 9-12+ weeks, depending on the complexity and quality of the application and the total number of applications under review. Review Memo Revised Application Final DRT Comments Timing of Conditions of Approval + Technical Corrections While all DRT conditions of approval and technical corrections must be met by the applicant, the timing of compliance varies. In the “Must be completed by” column in the following tables, please time your conditions of approval and technical corrections to the following development review stages: a. Prior to Public Hearing – these conditions/technical corrections must be addressed before the case may move forward to the public hearing phase of the Development Review Process. b. Prior to Recordation – these conditions/technical corrections may be resolved after the public hearing but must be addressed before the Development Plan or Subdivision plat is recorded. c. Prior to Building Permit Approval – these conditions/technical corrections can be addressed during the building permit review process, but prior to issuance of the permit. d. During Construction – these conditions/technical corrections can be addressed during construction. Development Review Process Flow Chart *See the 2024 Development Review Schedule for details DRT Review Timeline: Initial DRT Comments Final Review Memo Application Received DRT Application Intake DRT Initial Review Comments Due Form Updated: April 2024 Date: 02/16/2026 DRT Member: Paul A. Duran Dept/Div: Land Use/ HPD Case No.: #2025-11756 1802 Cerrillos Road Case Planner: Alexa N. Hempel Conditions of Approval and Technical Corrections Tables Review by this division/department has determined that this application will meet applicable standards if the following Conditions of Approval and Technical Corrections are met: Case # Conditions of Approval: Must be completed by: Applicant response**: 1. 14-4.2(D)(3) & 14-4.2(D)(4) 2. (3) Suburban Archaeological Review District 3. In this district, an archaeological clearance permit shall be required prior to approval of the final development plan or plat for the following projects: 4. (I)All annexations, rezonings, subdivisions, planned unit developments, or other development requiring approval by the Planning Commission, having over ten (10) acres 5. (II)All city projects over two (2) acres in size. 6. (III)All city park projects over one (1) acre in size. (4) Utility Mains An archaeological clearance permit is required for new construction of sewer mains or main lines of other utilities such as telephone lines, gas lines, and fiber optics, including the entire construction easement: (I) With an extension of sixty (50) feet or more if the main is in the historic downtown archaeological review district; (II) With an extension of five hundred fifty (550) or more if the main is in the river and trails or suburban archaeological review district. No further review required unless a future proposed utility plan exceeds 550- linear feet of utility lines. 7. 8. 9. 10. 11. Technical Corrections: Must be completed by: Applicant response**: 1. Form Updated: April 2024 2. 3. 4. **The Applicant must respond to the condition of approval or technical correction, indicating they have met the requirement and providing a reference in their revised submittals. If the applicant has not met the requirement, they must indicate as much and provide a response. The applicant should be aware that the following code provisions or other requirements will apply to future phases of development of this project: 1. [list any additional items] 2. Explanation of Conditions or Corrections (if needed): (see following pages for notes required) Form Updated: April 2024 Development Review Team (DRT) Comment Form DRT Review Schedule – 9-12+ weeks* Initial DRT Comments are due to the case planner within three weeks of the DRT Application Intake meeting. Initial DRT review should confirm that the application is complete (i.e. Water Budget has been submitted) and/or identify additional submittals or corrections (i.e. Water Budget needs revision). The case planner will review and convey all Initial DRT Comments to the applicant via a Review Memo. The applicant must respond to all Initial DRT Comments and submit a revised application for Final Review. Final DRT Comments are due to the case planner within two weeks of receipt of the revised application. The case planner will review and convey all Final DRT Comments to the applicant in a Final Review Memo. The complete DRT Review Timeline can range from 9-12+ weeks, depending on the complexity and quality of the application and the total number of applications under review. Review Memo Revised Application Final DRT Comments Timing of Conditions of Approval + Technical Corrections While all DRT conditions of approval and technical corrections must be met by the applicant, the timing of compliance varies. In the “Must be completed by” column in the following tables, please time your conditions of approval and technical corrections to the following development review stages: a. Prior to Public Hearing – these conditions/technical corrections must be addressed before the case may move forward to the public hearing phase of the Development Review Process. b. Prior to Recordation – these conditions/technical corrections may be resolved after the public hearing but must be addressed before the Development Plan or Subdivision plat is recorded. c. Prior to Building Permit Approval – these conditions/technical corrections can be addressed during the building permit review process, but prior to issuance of the permit. d. During Construction – these conditions/technical corrections can be addressed during construction. Development Review Process Flow Chart *See the 2024 Development Review Schedule for details DRT Review Timeline: Initial DRT Comments Final Review Memo Application Received DRT Application Intake DRT Initial Review Comments Due Form Updated: April 2024 Date: 2/16/2026 DRT Member: Teddy Padilla Dept/Div: Land Use/Technical Review Case No.: 2025-11753, 2025-11756 Case Planner: Alexa Hempel Conditions of Approval and Technical Corrections Tables Review by this division/department has determined that this application will meet applicable standards if the following Conditions of Approval and Technical Corrections are met: Case # Conditions of Approval: Must be completed by: Applicant response**: 1. 2. 3. 4. 5. 6. Technical Corrections: Must be completed by: Applicant response**: 1. Must remove and replace all damaged existing sidewalks. Prior to permit 2. Must relocate northeast fire hydrant out of sidewalk path on Cerrillos Rd. Prior to recordation 3. Must remove and replace all existing, abandoned curb cuts/drive entrances and replace with barrier curb. SFCC 23- 3.5 Prior to recordation 4. ADA Parking stalls and aisles must be added to east parking lot for buildings 2, 3, for the offices and restrooms. Prior to recordation 5. Remove City of Albuquerque Civil Details Sheets # C-506, and # C-507 and add NMDOT Series 608 in place. Prior to recordation 6. Must bring Existing Corner curb ramps to ADA compliance. Prior to recordation **The Applicant must respond to the condition of approval or technical correction, indicating they have met the requirement and providing a reference in their revised submittals. If the applicant has not met the requirement, they must indicate as much and provide a response. The applicant should be aware that the following code provisions or other requirements will apply to future phases of development of this project: 1. [list any additional items] 2. Form Updated: April 2024 Explanation of Conditions or Corrections (if needed): Form Updated: April 2024 (see following pages for notes required) Form Updated: April 2024 Development Review Team (DRT) Comment Form DRT Review Schedule – 9-12+ weeks* Initial DRT Comments are due to the case planner within three weeks of the DRT Application Intake meeting. Initial DRT review should confirm that the application is complete (i.e. Water Budget has been submitted) and/or identify additional submittals or corrections (i.e. Water Budget needs revision). The case planner will review and convey all Initial DRT Comments to the applicant via a Review Memo. The applicant must respond to all Initial DRT Comments and submit a revised application for Final Review. Final DRT Comments are due to the case planner within two weeks of receipt of the revised application. The case planner will review and convey all Final DRT Comments to the applicant in a Final Review Memo. The complete DRT Review Timeline can range from 9-12+ weeks, depending on the complexity and quality of the application and the total number of applications under review. Review Memo Revised Application Final DRT Comments Timing of Conditions of Approval + Technical Corrections While all DRT conditions of approval and technical corrections must be met by the applicant, the timing of compliance varies. In the “Must be completed by” column in the following tables, please time your conditions of approval and technical corrections to the following development review stages: a. Prior to Public Hearing – these conditions/technical corrections must be addressed before the case may move forward to the public hearing phase of the Development Review Process. b. Prior to Recordation – these conditions/technical corrections may be resolved after the public hearing but must be addressed before the Development Plan or Subdivision plat is recorded. c. Prior to Building Permit Approval – these conditions/technical corrections can be addressed during the building permit review process, but prior to issuance of the permit. d. During Construction – these conditions/technical corrections can be addressed during construction. Development Review Process Flow Chart *See the 2024 Development Review Schedule for details DRT Review Timeline: Initial DRT Comments Final Review Memo Application Received DRT Application Intake DRT Initial Review Comments Due 2/9/26 by SF MPO 2/9/26 by SF MPO Form Updated: April 2024 Date: 2/16/26 DRT Member: Erick Aune & Carrie Tremblatt Dept/Div: Santa Fe MPO Case No.: Case #2025-11753 Case Planner: Alexa Hampel Conditions of Approval and Technical Corrections Tables Review by this division/department has determined that this application will meet applicable standards if the following Conditions of Approval and Technical Corrections are met: Case # Conditions of Approval: Must be completed by: Applicant response**: 1. Sidewalk should align with Cerrillos Road Plan specs and city street design standards which require 5’ landscape buffer between street and pedestrian path (See comments on plans for detail). Sidewalk width should be at least 6’, but also made as wide as possible on Cerrillos. FHWA and AASHTO guidance support a separated bike facility given the vehicle speeds and volumes here. By expanding the sidewalk to the minimum for a shared use path (10’ ) this would better align with federal guidance. Prior to planning commission 2. Driveway conflicts on NW Fourth street should be minimized by consolidating driveways or minimizing the driveway width to ensure one- way circulation Prior to planning commission 3. Ensure safe pedestrian access to site from each street frontage and sidewalk and also between all 3 parcels. How are conflicts between cars and pedestrians crossing 4th from parking on site 1 to site 2 going to be managed and minimized? Prior to planning commission 4. Pedestrian Access Routes should aim for right angles. Skewed angles can be challenging for wheelchairs to maneuver safely. Minimize awkward angles and ensure there is sufficient landing pad for maneuvering Prior to planning commission 5. 6. Technical Corrections: Must be completed by: Applicant response**: 1. 2. 3. 4. **The Applicant must respond to the condition of approval or technical correction, indicating they have met the requirement and providing a reference in their revised submittals. If the applicant has not met the requirement, they must indicate as much and provide a response. Form Updated: April 2024 The applicant should be aware that the following code provisions or other requirements will apply to future phases of development of this project: 1. [list any additional items] 2. Explanation of Conditions or Corrections (if needed): 3. (see following pages for notes required) See City Street Standards below for sidewalk and landscaping buffer requirements Form Updated: April 2024 10' BUILDING SETBACK EMPIRE SELF STORAGE SITE PLAN This many driveways so close together presents more potenital for conflicts. Consolidate driveways or narrow access opening to ensure one way circulation. Pedestrian access path also needs to be maintained GENERAL NOTES 1. SOLID WASTER COLLECTION WILL BE PROVIDED BY THE CITY OF SANTA FE. 2. EXTERIOR LUMINARIES SHALL COMPLY WITH CHAPTER 14-8.9 SFCC. 3. THE SITE SHALL COMPLY WITH INTERNATIONAL FIRE CODE (IFC) 2015. 4. THE FIRE DEPARTMENT ACCESS SHALL NOT BE LESS THAN 20' AND 26' AROUND THE RESIDENTIAL 13 13 2 This is a 1 challenging 6 angle for wheelchair access 12 10 Street Standards requries landscaped buffer between street and sidewalk for arterials and collectors 1 8 through driveway 8 More thought needs to be put into access from parking on site 2 to site 1. Having overlflow parking on the opposite side of the street with no pedestrian crossing facilities creates new ped crossing demands that need to be accommodated BUILDING. 5. THE SITE SHALL HAVE A WATER SUPPLY THAT MEETS FIR FLOW AND HAVE A DISTANCE TO THE NEAREST HYDRANT TO MEET IF REQUIREMENTS. 6. ALL FIRE DEPARTMENT ACCESS SHALL HAVE A GRADE NO GREATER THAN 10% . 7. FIRE LANE SURFACE SHALL BE ALL WEATHER AND SUPPORT 75,000 LBS. KEYED NOTES XX 1. PROPERTY LINE 2. EXISTING PUBLIC SIDEWALK 2 2 1 5 1 6 8 1 4 12 2 4 3 8 64' ROW 6 1 3. PROPOSED BUILDING 4. PROPOSED FENCING 5. PROPOSED ASPHALT PARKING 6. PROPOSED 6' CONCRETE SIDEWALK 7. PROPOSED CONCRETE ADA PARKING 8. PROPOSED CONCRETE CURB AND GUTTER 9. PROPOSED ADA CURB RAMP 10. PROPOSED BIKE RACKS 11. PROPOSED DOG PARK 3 3 1 6 10 3 10 14 4 5 16 15 8 2 6 12 17 9 3 12. PROPOSED DRIVEPAD 13. PROPOSED PUBLIC SIDEWALK CONNECTION 14. PROPOSED BOLLARDS, TYP. 15. PROPOSED CONCRETE WHEEL STOPS, TYP. 16. PROPOSED SITE LIGHTING PER ELECTRICAL PLANS 17. PROPOSED VEHICLE GATE 18. PROPOSED PUBLIC SIDEWALK LEGEND 8 5 9 12 7 7 4 8 11 4 1 18 12 PROPERTY LINES EASEMENTS 1 2 8 4 PROPOSED FENCE 8 1 18 2 2 4 1 18 18 BERRY AVE 2 2 PROPOSED SITE LIGHTING PROPOSED BUILDING PROPOSED CONCRETE PROPOSED ASPHALT PARKING CASE #: 0 30' SCALE: 1" = 30' 60' ADDRESS: 1802 CERRILLOS RD. SANTA FE, NM 87505 1361 FOURTH ST. SANTA FE, NM 87505 1750 CERRILLOS RD. SANTA FE, NM 87505 3 RD BERRY AVE. SANTA FE, NM 87505 SHEET NAME: SHEET #: SITE PLAN C-201SHEET # OF FIFTH ST 64.35' SITE PLAN 4 3" 28" 3 EMPIRE SELF STORAGE SIGNING AND STRIPING - ADA PLAN NOTES FOR PAVEMENT MARKINGS 1. ALL PAVEMENT MARKINGS SHALL CONFORM TO THE CURRENT EDITION OF THE MUTCD. 2. THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE LAYOUT AND INSTALLATION OF PAVEMENT MARKINGS ON FINAL SURFACE COURSE. THE LAYOUT OF ALL PAVEMENT MARKINGS SHALL BE APPROVED BY THE PROJECT MANAGER PRIOR TO THE APPLICATION OF MATERIALS. skewed angles should be avoided for Ped Access route. At the very least ensure sufficient landing areas for maneuvering safely ADA curb ramps are needed at intersections and should align with ped access route ACCESIBLE PEDESTRIAN ROUTE ACCESIBLE PEDESTRIAN ROUTE 7 1 7 7 7 6 1 7 0 30' SCALE: 1" = 30' 60' 3. ALL LANE DIMENSIONS ARE FROM CENTER OF LANE STRIPE, CENTER OF DOUBLE LANE STRIPE, FACE OF CURB, OR EDGE OF PAVEMENT UNLESS OTHERWISE NOTED. NOTES FOR PERMANENT SIGNING 1. ALL SIGNS UNLESS OTHERWISE SPECIFIED, SHALL MEET THE REFLECTIVITY REQUIREMENTS IN THE TABLE ON SHEET C-18 FOR THE SHEETING, LEGEND, BORDER AND BACKGROUND. ONLY ALUMINUM PANEL SIGNS ARE PERMITTED. 2. ALL TRAFFIC CONTROL SIGNS AND DEVICES SHALL COMPLY WITH THE MANUAL ON UNIFORM TRAFFIC CONTROL DEVICES (MUTCD) CURRENT EDITION. 3. THE LATERAL CLEARANCE OF SIGNS SHALL BE NOT LESS THAN 2 FT. FROM THE FACE OF CURB OR SIDEWALK. 4. ALL SIGNING HARDWARE, INCLUDING BRACKETS, (FOR MOUNTING ALL STREET NAME SIGNS, ETC.) ARE CONSIDERED INCIDENTAL TO SIGN INSTALLATION AND THEREFORE NO ADDITIONAL PAYMENT SHALL BE MADE. GENERAL NOTES 1. AT TIME OF CONSTRUCTION, THE CONTRACTOR SHALL ENSURE ADA COMPLIANCE FOR CONSTRUCTION OF REQUIRED ADA ACCESSIBLE FEATURES AND APPURTENANCES, AS DETAILED IN, AND IN ADDITION TO, THE APPROVED CONSTRUCTION PERMIT DOCUMENTS. 2. IMPROVEMENTS SHALL COMPLY WITH ICC ANSI A117.1-2009 CHAPTERS 1-5 AND CHAPTER 7, MUTCD, DOJ, AND NM STATE STATUTE AND CODE SUCH AS THE NEW MEXICO ACCESSIBLE PARKING CHECKLIST, LATEST PUBLISHED VERSION. SIGNAGE WITH REQUIRED LANGUAGE PER THE NM ACCESSIBLE PARKING CHECKLIST IS REQUIRED AT ALL ADA PARKING SPACES. 3. ACCESSIBLE PARKING SPACES AND ACCESS AISLES SHALL NOT EXCEED 2% SLOPE IN ANY DIRECTION. 1%-1.5% IS THE PREFERRED TARGET SLOPE. connect sidewal7k to access route 7 ACCESIBLE PEDESTRIAN ROUTE 2 1 7 2 7 ACCESIBLE PEDESTRIAN ROUTE 7 4. ALL WALK SURFACES ALONG THE ACCESSIBLE PATH OF TRAVEL SHALL BE FIRM, STABLE AND SLIP RESISTANT. SIDEWALKS AND WALKWAYS ALONG THE ACCESSIBLE PATH OF TRAVEL SHALL NOT EXCEED 1:20 (5%) RUNNING SLOPES WITHOUT HANDRAIL(S) IN ACCORDANCE WITH CURRENT ANSI 117.1 STANDARDS 505 2015 IBC 1014. CROSS SLOPES SHALL NOT EXCEED 2% STAFF RECOMMENDS 1% TO 1.5% AS A TARGET CROSS SLOPE. 5. RAMPS WITHIN THE SITE SHALL HAVE 1:12 (8.33%) RUNNING SLOPE AND 1:48 (2%) CROSS SLOPE MAX. WITH A MAX. RISE OF 30" AND WITH 5' CLEAR LENGTH LANDINGS WHERE STRAIGHT. CHANGES IN DIRECTION SHALL COMPLY WITH 304.3. LANDING TYPICAL SLOPE IS 1.5% AND SHALL NOT EXCEED 2% RUNNING AND CROSS SLOPE. WALKWAYS SHALL PROVIDE 5’ DIAMETER TURNING SPACE EVERY 200 LINEAR FEET OF RUN. BERRY AVE 6. ENSURE ACCESSIBLE ROUTE(S) FROM ACCESSIBLE PARKING SPACE AISLE(S) TO BUILDING ENTRANCE ARE PROVIDED/MAINTAINED. KEYED NOTES XX 1. 4" SOLID WHITE, TYPICAL 2. ADA ACCESSIBLE PARKING, SEE DETAIL A 3. 4" SOLID BLUE, TYPICAL 4. ADA ACCESSIBLE PARKING SYMBOL, SEE DETAIL B 7 7 5. VAN ACCESSIBLE SIGN, SEE DETAIL C 7 6. PRECAST CONCRETE WHEEL STOP, SEE DETAIL D 7. ADA ACCESSIBLE CURB RAMP 5 5 3 3 * * BLUE * WHITE 3" STROKE WIDTH CASE #: ADDRESS: 8. DETECTABLE WARNING SURFACE 1802 CERRILLOS RD. SANTA FE, NM 87505 1361 FOURTH ST. SANTA FE, NM 87505 1750 CERRILLOS RD. SANTA FE, NM 87505 3 RD BERRY AVE. SANTA FE, NM 87505 C-203SHEET NAME: SHEET #: 4 4 3" 24" 3" SIGNING AND9.00' 5.22' 9.00' A ACCESSIBLE PARKING DETAIL B ADA ACCESSIBLE SYMBOL DETAIL C ADA PARKING LOT SIGN D PRECAST CONCRETE WHEEL STOP DETAIL C-15 SCALE: NTS C-15 SCALE: NTS C-15 SCALE: NTS C-15 SCALE: NTS STRIPING - ADA PLAN SHEET # OF 20' UTILITY EASEMENT BK. MISC. 180, PG. 500 12' UTILITY EASEMENT BK. MISC. 180, PG. 268 FIFTH ST 3" SIGNING AND STRIPING - ADA PLAN =� ROP. OP E RETAINING WAU lil FENCES' I ? 1� ""p""R'"o""p-""P_E"'o""E""s""TR-/A""N""'•�i PROP. FILL SLOPE SCREENINGFENCE, TYPE 1 PROP. -- �- CLCONST.�T.C.P.-s_· I--- ,, J - ----- - ,_ ' --------- ;- -- ( - - c:,c +:, -- - - - � CLINTERSECTION STA. 195+49.30 NM 14 = STA. 10+00.00 T0-03 1�- _L_ ...J.Jm:7"1z"j",-:,,i, ---- � :.L � Cl) - c:, c:, l!�ER�s"Ro".il �- "� _L_ PT 6834 98 6835.48 PT 6834 90 6835 40 NM 14 (CERRILLO$ RD.} I STA. 189+00.11 LT. TO-01 ISFFD EMERGENCY EXtn POINT FL.ELEV.ITC. ELEV. STA. 188+44.91 POINT FL ELEV. Iv. ELEV. PC 6834.56 683500 OFF. 35.87' RT. PC 6835.65 6836.15 1 6834.59 6834.91 FL = 6835.42' j,, STA 188+59.44 1 6835.44 6835.94 2 6834.80 6834.82 (TSC= 6835.921I \ OFF. 34.33' RT. 2 6835.37 6835.39 3 6834.95 683500 (SC:6835.441 FL = 6835.n•- 3 6835.32 6835.34 PT 6835.10 6835,4-4 STA 187+88.15 (TSC = 6836.271 PT 6835.28 6835 78 OFF. 34.41' RT. STA.188+39.49 ,... FL = 6834.53' � I 0-i OFF. 39.56' RT. 13 p:vr:::1. (TSC= 6835.031 12 FL= 6835.37I'""\ r:-, - r----------''---==o+-C4 l- =:�--,, ,_, f,1 �- -[l SO TF AF .. 13887. 9+ 79 "8R. 5T,4.L ...l.. _:!,!1:_:TB�C:_:=:._:6'.:'.83:'.:5'.::.3'.:9�?le.'.-\ ---\-.\-�t..! �:'�;;i;itn.t;PC;t�tftf�;;;i�;;;;�;;;;;;;��;;;;;;;;;; 9I -- ,-FL(T=S68C3=46.87374' .791 \ -2 /_ �,,,.--- I ;I� � 2 �-----------S-T_A._1_88+-35_.4_3-, / ��---- 0 � to © u0 i ,::il:ifi.JE'1 /11:3 /4 12' � _====r..,_�1=3=Jr=,====S=T:A:.:1::8:7!=+=87=.t6'L3 ...::.:;;:-� ""� 11 OSFTFA. 1468.801+'0R3T..42 � ill� �/1/ 1 0 .........;�· STA.188+59.44 � 3 f---OFF. 40.06' RT. PROP. 0 ,:;;;:, FL = 6834.94' 0 'x,_"' STA. 188�7.7_3 _ 0FF.41.00'RT-. ---------� ,H EXIST. SSW=6835.11' R.OW_) l!I (TBC=6834.96) #, I Pr I'---. / SSW= 6835.53'�/--,,..-"'--OFF. 42.45 RT. BSW =6836.35' R.O.W. STA. 187+94.85 J - \ \ STA. 188+38.03 ,,,,. f\.".'i. I >"" _,,,,- - - - - - - - T - -EXIST-. 1- OFF. 43 22' RT_, / r., OFF. 45.54' RT. - r'r / PROP.� R.O.W.- SSW= 6834 84' \V SW= 6835.36' -L ., .i,i / STA 188+42.93 T.C.P. STA 187+9826 l \ II � c.. @ �J OFF.45.93'RT. / OFF 4B.12·Rr � l�· _ ir-=='L P_T...., ..., ,.-:--,� �" ' - .._ "i(PROP. SSW= 6835.44' t6. CONCRETEBARRIER CURBANOGUTTER TYPE0 ;r')(24" 17. CONCRETESIDEWALK4" (VARIES). LEGEND -�--- PROP. PEDESTRIAN/BICYCLE RAILING z 0;:: <) ::> a:: 1- ( z/) . (/) o-.J <) ;:!: � !:!:! UJ '°�Cl �g Cl::; � (.) w � st � ::; z TSABETSAYE. NICOl.E Cra,ingFile: J:\30900156NM14 c.ERRILLOSROAO\D4ENGll'EERING •S100680\PLANS'-2_SHEETS\S10038t2MS001.0\"3 1.Jul-25 10:52 AM PROJECT DEVELOPED BY: WSP USA DRAWING SCALE: 1" = tO' SHEET NO. 2 - 48 Development Review Team (DRT) Comment Form Date: February 20, 2026 DRT Member: Leroy Pacheco, PE and Phil Gallegos, PE (Wilson & Company) Dept/Div: Public Works Department – Traffic Engineering Case No.: Case #2025-11753 (Development Plan) & Case #2025-11756 (Special Use Permit) 1802 Cerrillos Road (former Empire Builders Site) Case Planner: Alexa Hempel, LEED Green Associate, Senior Planner Conditions of Approval and Technical Corrections Tables Review by this division/department has determined that this application will meet applicable standards if the following Conditions of Approval and Technical Corrections are met: Case # Conditions of Approval: Must be completed by: Applicant response**: 1. See attached letter from Wilson & Company dated 2/20/26 certifying its concurrence with the developer’s “Initial Traffic Assessment” (ITA). N/A 2. Developer should provide certification that its engineers have provided NMDOT project development engineers opportunity to review site plans in accordance with the department’s proposed redesign and reconstruction of Cerrillos Road. Prior to Planning Commission 3. A detailed signage and striping plan for all required on-street signage, pavement markings, and any related regulatory/directional signs shall be submitted for review and approval by Public Works. Prior to Building Permit Technical Corrections: Must be completed by: Applicant response**: 1. 2. **The Applicant must respond to the condition of approval or technical correction, indicating they have met the requirement and providing a reference in their revised submittals. If the applicant has not met the requirement, they must indicate as much and provide a response. The applicant should be aware that the following code provisions or other requirements will apply to future phases of development of this project: 1. City of Santa Fe Building Code, Chapter 23-3.2 states that before commencement of any new construction, it is mandatory for the owner to obtain approval from the Public Works Department for any driveway curb cut or sidewalk crossing. This approval must be issued before a building permit for such new construction is approved. 2. Note as the public infrastructure plans move forward to building permit, these may be subject to additional reviews and possible corrections to meet Public Works Standards for roadways, ADA, signing, striping, lighting, etc. prior to building permit approval. Form Updated: April 2024 Memorandum To: Leroy Pacheco, PE COSF From: Philip A. Gallegos, PE, Senior Transportation Engineer CC: Date: 2/20/2026 Re: DXD Storage ITA Review Comments Wilson and Company has reviewed the ITA prepared by Sounder Miller and Associates for the DXD Empire Self Storage Development located at 1802 Cerrillos Road in Santa Fe, New Mexico. The ITE Trip Generation Handbook, 12th Edition was utilized for this ITA and the number of trips generated by this development are below the thresholds for a TIA as outlined in the City of Santa Fe TIA Guidelines. Therefore, I concur with the findings of the report. Please let me know if you have any questions or require further information. Sincerely, Philip A Gallegos, PE Senior Transportation Engineer 1 Form Updated: April 2024 Development Review Team (DRT) Comment Form DRT Review Schedule – 9-12+ weeks* Initial DRT Comments are due to the case planner within three weeks of the DRT Application Intake meeting. Initial DRT review should confirm that the application is complete (i.e. Water Budget has been submitted) and/or identify additional submittals or corrections (i.e. Water Budget needs revision). The case planner will review and convey all Initial DRT Comments to the applicant via a Review Memo. The applicant must respond to all Initial DRT Comments and submit a revised application for Final Review. Final DRT Comments are due to the case planner within two weeks of receipt of the revised application. The case planner will review and convey all Final DRT Comments to the applicant in a Final Review Memo. The complete DRT Review Timeline can range from 9-12+ weeks, depending on the complexity and quality of the application and the total number of applications under review. Review Memo Revised Application Final DRT Comments Timing of Conditions of Approval + Technical Corrections While all DRT conditions of approval and technical corrections must be met by the applicant, the timing of compliance varies. In the “Must be completed by” column in the following tables, please time your conditions of approval and technical corrections to the following development review stages: a. Prior to Public Hearing – these conditions/technical corrections must be addressed before the case may move forward to the public hearing phase of the Development Review Process. b. Prior to Recordation – these conditions/technical corrections may be resolved after the public hearing but must be addressed before the Development Plan or Subdivision plat is recorded. c. Prior to Building Permit Approval – these conditions/technical corrections can be addressed during the building permit review process, but prior to issuance of the permit. d. During Construction – these conditions/technical corrections can be addressed during construction. Development Review Process Flow Chart *See the 2024 Development Review Schedule for details DRT Review Timeline: Initial DRT Comments Final Review Memo Application Received DRT Application Intake DRT Initial Review Comments Due 2/9/26 by Parks and Open Space 2/9/26 by Parks and Open Space Form Updated: April 2024 Date: 2/18/26 DRT Member: Melissa McDonald, Parks and Open Space Division Director Zoë Isaacson, River and Watershed Manager Dept/Div: Parks & Open Space Division Case No.: Case #2025-11753 Case Planner: Alexa Hampel Conditions of Approval and Technical Corrections Tables Review by this division/department has determined that this application will meet applicable standards if the following Conditions of Approval and Technical Corrections are met: Case # Conditions of Approval: Must be completed by: Applicant response**: 1. The public right-of-way will be constructed in accordance with the approved Public Works project S100681 (NM 14/Cerrillos Road), including a 5-foot stamped concrete buffer and a full 6-foot sidewalk. Prior to building permit approval Prior to planning commission 2. 3. 4. 5. 6. Technical Corrections: Must be completed by: Applicant response**: 1. Existing Drainage Plan (sheet C-302) has a drainage calc. table labeled “post- development stormwater calculations. Verify this the correct table for this sheet and relabel to pre-development stormwater calcs. Also question whether this is correct table, as the existing volumes are less than post- development volumes on next sheet, however site plan reduces impervious area. Prior to development plan approval Prior to recordation 2. Please label each pond, provide drawings for each pond including inlet & outlet structures, storage volumes, location of sediment measuring post, and landscape materials. Ensure grading notes reflect plan. Prior to development plan approval Prior to recordation 3. Planting Note #1 (LP-501): This note should be revised to reference the City of Santa Fe landscape requirements rather than Doña Ana County landscape requirements. Prior to development plan approval Prior to recordation Form Updated: April 2024 4. Fencing oddly crosses retention pond (C-201) note 5. The dog park should be designed and constructed to capture the first flush of surface runoff in order to reduce water quality impacts. As currently depicted, the grading plan does not Prior to development plan approval Prior to recordation direct runoff in a manner that would enable the pond to function as intended (sheet -304) **The Applicant must respond to the condition of approval or technical correction, indicating they have met the requirement and providing a reference in their revised submittals. If the applicant has not met the requirement, they must indicate as much and provide a response. The applicant should be aware that the following code provisions or other requirements will apply to future phases of development of this project: 1. [list any additional items] 2. Explanation of Conditions or Corrections (if needed): Form Updated: March 2024 Development Review Team (DRT) Comment Form Date: 2/16/2026 DRT Member: Dee Beingessner, Joshua VanSlambrouck Dept/Div: Land Use Engineering Case No.: 1802 Cerrillos Rd Development Plan Case Planner: Alexa Hempel, Senior Planner Conditions of Approval and Technical Corrections Tables Review by this division/department has determined that this application will meet applicable standards if the following Conditions of Approval and Technical Corrections are met: Conditions of Approval: Must be completed by: Applicant Response**: 1. Provide discussion in the drainage narrative of how the stormwater will be directed to the ponding areas. Include how water will be directed from roof drains. All Comments are Prior to recordation 2. Provide flow directional arrows on grading and drainage plan especially showing flow from roof drains to ponding areas. Ponding area volumes must be established for each ponding area showing dimensions. Label each pond with a pond number and the volume. Depressed areas for all landscaped areas are encouraged, but the official ponding areas for the required storage must be verifiable in the future. The conveyance of water to those areas must be shown on the plans and verifiable in the future. Show curb cuts for water to enter landscaped areas. 3. Provide photometric plan 4. Include pond sections and show how ponds will overflow. Technical Corrections: Must be completed by: Applicant Response**: 1. Include attached notes. 2. A financial guarantee will be required for all public and quasi-public infrastructure. The guarantee must be in place prior to recordation of development plan. 3. Current analysis shows a violation: an increase in peak stormwater flows is not allowed per city code 14-8.2(D)(4) (b)(i) 4. Include 2 additional drainage analysis for the 1-year, 1- hour, and 100-year, 24-hour, required to show compliance for any frequency storm event up to the 100- year, 24-hour. Please See city code 14-8.2(D)(4)(b)(i) “except as otherwise required by this Section 14-8.2, the stormwater runoff peak flow rate discharged from a site shall not exceed pre- development conditions for any frequency storm event up to the one percent chance, twenty-four- hour storm event at each discharge point;” 5. Show on the drainage and terrain management plans: roof drain pattern and downspouts/canales, and means of Form Updated: March 2024 stormwater conveyance (swales, catch basins, storm drainpipe, curb cuts, etc.) to stormwater control features 6. Please provide more information on how runoff Coefficients were selected from the NMDOT Manual, include the figure/table number, cover type, % impervious cover, etc. 7. Please Verify how the runoff volumes are calculated, The Rational Method is not an acceptable method to calculate runoff volume per NMDOT Drainage Design Manual, July 2018, section 403, Limitations: “Runoff volumes may not be computed with the Rational Formula Method or Modified Rational Formula Method (not included in this Drainage Design Manual”. 8. Include an acceptable runoff volume analysis for stormwater quality volume for a 0.68-inch (90% percentile, or roughly the 1-year, 1-hour storm) event. This runoff volume must be contained/retained on site, to reduce pollution per EPA NPDES MS4, see city code 14- 8.2(A)(13). This volume must infiltrate in 24 hours per city code 14-8.2(D)(4)(c)(ii), It is encouraged that the Stormwater quality volume design is incorporated into the landscape, to also comply with landscape code rainwater harvesting requirements 14-8.4(E)(1) “The landscaping plan shall include passive water harvesting for landscape irrigation purposes as a minimum requirement” the minimum recess depth for retention and water harvesting areas is 6 inches. 9. **The Applicant must respond to the condition of approval or technical correction, indicating they have met the requirement and providing a reference in their revised submittals. If the applicant has not met the requirement, they must indicate as much and provide a response. The applicant should be aware that the following code provisions or other requirements will apply to future phases of development of this project: 1. [list any additional items] 2. Explanation of Conditions or Corrections (if needed): See following pages for notes required on plat or plans DRAINAGE FACILITIES MAINTENANCE NOTE ALL DRAINAGE FACILITIES SHALL BE MAINTAINED BY ALL PROPERTY OWNERS. THE PROPERTY OWNERS SHALL ALSO HAVE THE RESPONSIBILITY FOR MAINTENANCE OF THE PUBLIC DRAINAGE EASEMENT. INSPECTIONS SHALL BE CONDUCTED BY A REGISTERED PROFESSIONAL ENGINEER IN THE STATE OF NEW MEXICO OR OTHER QUALIFIED PERSON. INSPECTIONS SHALL BE CONDUCTED ON THE DRAINAGE FACILITIES IN ACCORDANCE WITH THE FOLLOWING SCHEDULE: Form Updated: March 2024 ON OR ABOUT MARCH 15, ON OR ABOUT SEPTEMBER 15, AND AFTER EACH STORM EVENT OF 1-INCH OR GREATER. MAINTENANCE OF THE DRAINAGE FACILITIES SHALL BE CONDUCTED AND DOCUMENTED BY THE ENGINEER OR QUALIFIED PERSON AND THE OWNER. THE OWNER SHALL MAINTAIN A FILE OF THE INSPECTIONS AND REMEDIAL ACTION CONDUCTED ON THE DRAINAGE FACILITIES. WORK SHALL BE CONDUCTED IN ACCORDANCE WITH THE ENGINEER’S RECOMMENDATIONS, AND SHALL INCLUDE, BUT IS NOT LIMITED TO THE FOLLOWING: A. FLUSH ALL CULVERTS, DROP INLETS AND DRAINAGE PIPES TO REMOVE SEDIMENT AND VEGETATION THAT PREVENTS OR HINDERS THE FLOW OF STORM WATER IN THE DRAINAGE STRUCTURE(S). B. REMOVE SEDIMENT IN PONDS THAT IS GREATER THAN 6-INCHES IN DEPTH, AND IF NECESSARY, RESEED WITH NATIVE GRASSES AND INSTALL FILTER FABRIC AND 3 TO 4 INCH COBBLE AS DIRECTED BY THE ENGINEER. C. INSPECT FOR SEDIMENTATION IN ALL SWALES, DITCHES, DRAINGE PONDS AND REMOVE AND STABILIZE AS NECESSARY. D. INSPECT FOR SOIL EROSION AT ALL DRAINAGE PONDS, CUT AND FILL SLOPES, AND REPAIR OR STABILIZE ACCORDINGLY. E. INSPECT THE STRUCTURAL INTEGRITY OF DRAINAGE PONDS, SLOPES, RIP- RAP, GABIONS, DROP INLETS, CULVERTS, ENERGY DISSIPATORS, AND RETAINING WALLS, ROCK PLATING, EROSION CONTROL MATS OR BLANKETS, AND REPAIR OR STABILIZE ACCORDINGLY. GUNNISON’S PRAIRIE DOG NOTE THE PROJECT SHALL COMPLY WITH THE PROVISIONS OF THE GUNNISION’S PRAIRIE DOG ORDINANCE (ARTICLE 14-8.12). DUST CONTROL NOTE All on-site soil disturbing construction activities shall be addressed and provide measures to mitigate or control dust from being transported offsite and polluting neighboring properties. Any person, owner, contractor or operator who conducts earthmoving and/or dust generating activities is responsible for implementing Best Management Practices (BMPs) in order to mitigate off-property transport of fugitive dust emissions. A plan, or storm water prevention plan (SWPPP) when applicable, listing the Best Management Practices (BMPs), shall be provided to the City Engineer, or their designee for review and Form Updated: March 2024 approval. The approved BMPs shall be applied to the graded and/or disturbed soil in order to stabilize the site. The initial BMP shall address how the Contractor will minimize the amount of disturbed soil, and how the Contractor will stabilize the disturbed surface area exposed to wind or vehicle traffic during construction. Some BMPs shall include:  The reduction of vehicle speeds: establish a maximum speed limit or install traffic calming devices to reduce speeds to a rate to mitigate off-property transport of dust entrained by vehicles.  The minimization of drop height: Drivers and operators shall unload truck beds and loader or excavator buckets slowly, and minimize drop height of materials to the lowest height possible, including screening operations.  High winds restriction: temporarily halt work activities during high wind events greater than 30 mph if operations would result in off-property transport.  Restrict access: restrict access to the work area to only authorized vehicles and personnel. In the event the above practices are ineffective to prevent off property transport, the owner or operator shall use at one or more of the following Best Management Practices (BMPs):  Wet suppression: apply water to disturbed soil surfaces, backfill materials, screenings, and other dust generating operations as necessary and appropriate considering current weather conditions, and prevent water used for dust control from entering any public right-of-way, storm water drainage facility, or watercourse.  Wind barrier: construct a fence or other type of wind barrier to prevent wind erosion of the graded or disturbed surface.  Vegetation: plant vegetation appropriate for retaining soils or creating a wind break.  Surface roughening: stabilize an active construction area during periods of inactivity or when vegetation cannot be immediately established.  Cover: install cover materials such as tackifiers, erosion control blankets, gravel, vegetation (when appropriate), cold-millings, etc. during periods of inactivity and properly anchor the cover.  Soil retention: stabilize disturbed or exposed soil surface areas that will be inactive for more than 30 days or while vegetation is being established. ENGINEER’S STORMWATER INFRASTRUCTURE CERTIFICATION I, the undersigned professional engineer in the State of New Mexico, do hereby certify that the record information shown hereon is based on actual field measurements and visual inspections performed by myself or under my direct supervision. I further certify that the record condition as of is in substantial compliance with the approved grading and drainage plan prepared by , dated . Signature NMPE # Date Form Updated: March 2024 Example for pond measurement post Form Updated: September 2023 Development Review Team (DRT) Comment Form Date: February 20, 2026 DRT Member: Lawrence Rivera Dept/Div: Landscape, Irrigation, and Outdoor Lighting Case No.: 2025-11753 Empire Storage Development Plan & 2025-11756 Special Use Permit Case Planner: Alexa Hempel, Senior Planner, anhempel@santafenm.gov, 505-955- 6661 DRT Review Schedule – 9-12+ weeks* Initial DRT Comments are due to the case planner within three weeks of the DRT Application Intake meeting. Initial DRT review should confirm that the application is complete (i.e. Water Budget has been submitted) and/or identify additional submittals or corrections (i.e. Water Budget needs revision). The case planner will review and convey all Initial DRT Comments to the applicant via a Review Memo. The applicant must respond to all Initial DRT Comments and submit a revised application for Final Review. Final DRT Comments are due to the case planner within two weeks of receipt of the revised application. The case planner will review and convey all Final DRT Comments to the applicant in a Final Review Memo. The complete DRT Review Timeline can range from 9-12+ weeks, depending on the complexity and quality of the application and the total number of applications under review. Review Memo Revised Application Final DRT Comments Timing of Conditions of Approval + Technical Corrections While all DRT conditions of approval and technical corrections must be met by the applicant, the timing of compliance varies. In the “Must be completed by” column in the following tables, please time your conditions of approval and technical corrections to the following development review stages: a. Prior to Public Hearing – these conditions/technical corrections must be addressed before the case may move forward to the public hearing phase of the Development Review Process. b. Prior to Recordation – these conditions/technical corrections may be resolved after the public hearing but must be addressed before the Development Plan or Subdivision plat is recorded. c. Prior Building Permit Approval – these conditions/technical corrections can be addressed during the building permit review process, but prior to issuance of the permit. d. At the time of development - Development Review Process Flow Chart Initial DRT Comments Final Review Memo Form Updated: September 2023 *See the 2024 Development Review Schedule for details Form Updated: September 2023 Conditions of Approval and Technical Corrections Tables Review by this division/department has determined that this application will meet applicable standards if the following Conditions of Approval and Technical Corrections are met: Conditions of Approval: Must be completed by: Applicant response**: 1. 2. 3. 4. 5. 6. Technical Corrections: Must be completed by: Applicant Response**: 1. Parking lot traffic islands appear to have 60 square feet of permeable surface. Code 14- 8.4(H)(4)(IV) requires 90 square feet of permeable surface. Prior to Recordation 2. Austrian pine at the main building at the southwest parking space is located to close to the curb and gutter. This tree at that location will cause curb and gutter and parking lot damage. Adjust tree to the center of the landscape area or choose a better size tree for this location. Entrance trees into the parking area should be centered in the planters to prevent future parking lot, curb, and gutter damage. 3. The Landscape is bunched into the property boundaries, extend the Landscape to the perimeters of the proposed sidewalks at Berry Ave and Fifth St. Review for easements, before plant material and irrigation location placements. 4. Provide shrubs to the landscape for parking lot screening at Cerrillos Road, Fourth St., and Berry Ave. per city code 14-8.4(H)(3). 5. Provide frontage landscaping for CRHC zone 1 as required pre code 14-5.5 - HIGHWAY CORRIDOR PROTECTION DISTRICTS (B) CRHC Cerrillos Road Highway Corridor Protection District at the northeast parking lot. 6. Provide shrub planting within the planter bed along the boundary wall at the northeast parking lot. 7. Review plantings at traffic sight triangles for height compliance for a 3–8-foot visibility window. 8. Utilize organic much within the landscape particularly at mass plantings. Provide wood mulch shredded or chipped 4-inches in depth without weed fabric. 9. Provide fencing information and detail. Form Updated: September 2023 10. Irrigation system design is incomplete. Provide the remaining zone layouts. 11. Provide the correct details from the LIDS manual for the Manual Drain, Backflow Preventer. 12. Provide a water budget for the first three months of the Turf establishment period. 13. Turf grass sod or turf grass seed mixes installed within the city limits shall contain no more than twenty-five percent Kentucky Bluegrass. 14. Photometrics do not meet Code requirements. See Article 14-8.6(D)(2) and revise for compliance. 74-points exceed the maximum illumination for any point. (Highlighted numbers attached are out of compliance) STAFF RESERVES THE RIGHT TO REQUIRE ADDITIONAL SUBMITTALS UPON RECEIVING REVISIONS. **The Applicant must respond to the condition of approval or technical correction, indicating they have met the requirement and providing a reference in their revised submittals. If the applicant has not met the requirement, they must indicate as much and provide a response. The applicant should be aware that the following code provisions or other requirements will apply to future phases of development of this project: 1. [list any additional items] 2. Explanation of Conditions or Corrections (if needed): (see following pages for notes required) 0.0 0.0 0. 1 0. 3 0.1 0. 2 0. 5 0. 8 0. 5 0. 8 1.0 1. 1.2 1. 1.3 1. 1.4 2. 1. 4 1. 5 1.8 1.7 1. 6 1. 7 1. 5 1. 7 1.4 1. 1. 4 1.6 1. 5 1.6 1. 5 1.6 1. 4 1. 7 1. 4 1. 9 1.3 1. 1.1 1. 0.9 1. 0. 6 0.7 0. 4 0.4 0.8 0.7 0.8 1. 6 2. 4 2. 1 0. 2 0. 2 0. 4 0.6 0. 6 0.8 0.9 1. 0 1. 1 0. 8 0.6 1.0 1. 5 1.7 2.6 1. 9 1. 9 1. 9 1.1 S SD 0. 8 1. 1 1. 6 2.2 S D 0.0 0.0 0.0 TELE 701.461.7222 112 No.Roberts Street, Suite 300, Fargo ND 58102 www.eapc.net CONSULTANTS 0.0 0.1 0.9 4.4 SB 6.9 0.5 0.0 0.1 1.0 SB 0.0 0.1 0.2 0.0 0.1 0.5 0.0 0.1 0.6 0.0 0.1 0.7 0.0 0.1 0.9 0.0 0.1 0.9 0.0 0.1 0.8 0.0 0.1 0.5 0.0 0.1 0.4 0.0 0.1 0.4 0.0 0.1 0.7 0.0 0.1 0.9 0.0 0.1 0.8 0.0 0.1 0.7 0.0 0.1 0.6 0.0 0.1 0.4 0.0 0.1 0.1 0.0 0.0 0.0 0.0 0.0 0.1 0.0 0.0 0.1 0.0 0.2 0.5 0.1 3.5 S B 3.6 0.1 1.6 0.7 0.1 0.1 0.1 0.1 0.4 0.5 0.5 0.6 0.7 0.8 0.8 0.8 0.9 1.1 1.2 0.8 1.1 1.4 1.8 0.7 1.0 1.6 2.0 0.3 0.0 0.6 0.0 1.1 0.0 1.5 0.0 DCLXIENDT SS F2 LAND, L.L.C 0.1 0.0 0.0 3.0 3.3 0.6 0.7 1.7 SB 5.0 5.6S B 2.7 1.2 3.6 3.1 2.6 1.8 3.2 S C 4.4 1.5 3.2 3.4 SC 2.1 1.9 1.9 2.0 3. S8 C 2.1 2.3 2.0 2.6 3.2 SC 1.7 1.7 2.9 SC 4.5 1.0 1.9 2.6 0.3 0.3 1.0 0.1 0.2 0.9 1.5 SB 3.0 0.7 1.9 2.9 1.0 3.8 SA9.6 0.4 0.8 2.3 0.3 0.4 0.1 0.1 0.1 0.1 0.1 0.6 0.6 0.7 0.9 0.9 0.9 1.3 1.3 1.3 2.2 2.1 1.8 2.5 2.4 2.0 1.7 S2 0.0 1.6 0.0 1.5 0.0 0.0 0.0 0.0 0.1 0.1 0.4 0.7 1.1 0.2 1.0 2.0 2.5 2.8 4.4 SC 3.8 3.7 4.5 SCE 2.8 2.5 2.8 SC 4.3 3.7 1.3 1.9 2.6 4.5 SC 1.6 0.5 1.0 2.8 SB 9.2 0.4 0.6 1.5 0.2 0.2 0.3 0.7 0.1 0.1 0.1 0.2 0.1 0.1 0.1 0.1 0.7 0.8 0.8 0.7 1.0 1.1 1.1 1.0 1.3 1.4 1.4 1.3 1.6 1.5 1.6 1.7 1.7 1.4 1.5 1.9 0.9 0.6 0.8 1.2 0.0 0.0 0.0 0.0 0.0 PROJECT DESCRIPTION EMPIRE SELF STORAGE 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.1 0.1 0.1 0.1 0.3 0.3 0.7 0.8 0.6 0.7 0.8 1.0 1.4 2.0 3.1 SCE 1.9 1.3 1.6 3.1 SC 3.2 2.5 2.4 SC 1.2 2.8 SC 3.7 2.0 0.8 1.3 2.9 SC 3.8 2.0 0.9 1.8 1.8 1.3 0.9 1.0 1.8 1.9 1.4 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.4 0.1 0.1 0.1 0.1 0.1 0.1 0.2 0.2 0.7 0.6 0.6 0.5 0.5 0.5 0.2 0.3 0.9 0.9 0.8 0.8 0.8 0.8 0.4 3.4 SA 1.3 1.4 1.3 1.2 1.1 1.0 2.0 2.3 2.0 1.6 1.4 2.2 2.6 2.3 1.8 1.4 1.5 0.0 1.6 S2 0.0 1.6 0.0 1.3 0.0 0.8 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.3 0.7 0.9 0.8 0.0 0.5 1.4 2.6 1.9 0.0 SD 1.6 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 CITY SANTA FE STATE NEW MEXICO ISSUE DATES 0.0 0.0 0.0 0.0 0.3 0.3 1.9 1.4 3.9 1.9 1.0 2.4 SCE SCE 4.3 3.7 SC SCE 0.9 SC 0.8 0.4 0.3 0.3 0.5 0.8 5.0 2.0 4.9 SF 2.2 SD SD 3.0 2.5 1.6 1.9 SD 2.7 1.8 2.1 1.7 1.7 1.2 1.5 0.0 0.0 0.0 0.0 0.2 0.7 0.8 0.8 1.7 3.0 3.5 2.1 1.6 1.9 2.5 2.6 1.9 2.1 2.9 3.6 2.5 2.3 2.9 3.8 2.7 2.2 2.5 2.7 1.7 0.7 0.4 1.3 2.3 2.0 0.8 1.8 3.0 1.9 1.6 1.9 1.8 1.2 1.1 1.0 1.1 1.7 2.8 S 0.0 0.0 0.0 0.1 0.3 0.4 0.6 1.1 1.3 1.3 1.3 1.1 1.1 1.2 1.4 1.4 1.4 1.5 1.5 1.6 1.7 1.9 1.7 1.7 1.5 1.5 1.4 1.4 1.1 0.7 0.4 1.7 SF 2.8 2.2 0.6 1.2 1.2 1.1 0.8 0.7 0.5 0.5 0.4 0.3 0.4 1.2 2.5 0.0 0.0 0.0 0.1 0.2 0.2 0.3 0.9 1.5 0.3 0.5 2.3 S12.4 0.4 0.5 1.7 1.4 0.3 0.2 1.4 0.2 1.4 0.3 1.7 0.4 2.4 S12.4 0.7 0.6 1.7 0.5 1.4 0.3 1.4 0.3 1.4 0.3 1.6 0.4 2.2 0.6 S2 1.4 0.5 1.8 0.5 1.2 0.3 0.8 0.2 0.6 0.1 0.2 0.1 1.1 0.7 1.6 SF 1.5 1.2 1.2 0.7 0.4 SD 0.9 0.0 0.0 0.3 0.2 1.0 0.4 1.4 0.4 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.2 0.2 0.2 0.2 0.2 0.1 0.2 0.2 0.1 0.1 0.2 0.2 0.1 0.1 0.3 0.3 0.3 0.2 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.0 0.3 0.2 7.1 SA 5.9 0.6 0.5 0.3 0.2 0.4 0.0 0.0 0.0 0.0 0.0 0.0 0.1 0.1 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 SD DEVELOPMENT PACKAGE 12/05/2025 MARK DESCRIPTION DATE 0.1 0.1 0.1 0.0 0.0 0.0 0.0 0.1 0.1 0.1 0.1 0.1 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 PROJECT NO: 20253380 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 DRAWN BY: KS 0.0 0.0 Statistics Description Symbol Avg Max Min Max/Min Avg/Min GENERAL NOTES CHECKED BY: MH COPYRIGHT: All plans, specifications, computer files, field data, notes and other documents and instruments prepared by EAPC as instruments of service shall remain the property of EAPC. EAPC shall retain all common law, statutory and other reserved rights, including the copyright there to. LIGHT SPILL AT PROPERY LINE (BLDG 1) 0.1 fc 4.4 fc 0.0 fc N/A N/A 1. ALL OUTDOOR LIGHTING MUST MEET CITY OF SANTA FE OUTDOOR LIGHTING CODE STAMP LIGHT SPILL AT PROPERY LINE (BLDGS 2, 3 & 4) SITE (BLDG 1) - FC @ GRADE SITE (BLDGS 2, 3 & 4) - FC @ GRADE 0.2 fc 1.4 fc 1.3 fc 1.7 fc 9.6 fc 7.1 fc 0.0 fc 0.0 fc 0.0 fc N/A N/A N/A N/A N/A N/A SECTION 14-8.9. Schedule Symbol Label S1 S2 SA SB Quantity 3 2 3 7 Manufacturer LITHONIA LITHONIA LITHONIA LITHONIA Catalog Number DSX0 LED P5 30K 80CRI TFTM MVOLT SPA HS (FINISH) / SSS 17.5' W/2.5' BASE DSX0 LED P5 30K 80CRI BLC4 MVOLT SPA (FINISH) / SSS 17.5' W/2.5' BASE DSXB LED 16C 350 30K SYM MVOLT (FINISH) DSXB LED 12C 350 30K ASY MVOLT (FINISH) Description AREA LUMINAIRE WITH P5 PERFORMANCE PACKAGE WITH FOWARD THROW OPTICS AND HOUSE SIDE SHIELD. MOUNTED @ 20'-0" AREA LUMINAIRE WITH P5 PERFORMANCE PACKAGE WITH TYPE 4 BACKLIGHT CONTROL. MOUNTED @ 20'-0" 3.' H D-SERIES BOLLARD WITH SYMMETRIC DISTRIBUTION 3' H. D-SERIES BOLLARD WITH ASYMMETRIC DISTRIBUTION Lamp LED - 3000K LED - 3000K LED - 3000K LED - 3000K Lumens Per Lamp 9026 7912 1558 1194 Lumen Multiplier 1 1 1 1 Light Loss Factor 0.91 0.91 0.91 0.91 Wattage 90.12 90.12 20 16 DRAWING TITLE PHOTOMETRICS 14 LITHONIA WDGE2 LED P2 30K 80CRI T3M MVOLT SRM (FINISH) WALL MOUNT WITH P2 PERFORMANCE PACKAGE - LED - 3000K - TYPE 3M. MOUNTED @ 8'-0" 1964 1 0.91 18.9815 SCE 5 LITHONIA WDGE2 LED P2 30K 80CRI T3M MVOLT SRM E20WC (FINISH) WALL MOUNT WITH P2 PERFORMANCE PACKAGE, TYPE 3M OPTICS AND EM BATTERY PACK. MOUNTED @ 8'-0" LED - 3000K 1964 1 0.91 18.9815 0.0 0.0 0.1 0.1 0.3 0.5 0.7 0.8 0.9 2 5 1.0 1.1 9 0 1.1 1.3 1.4 1.3 1.2 1.4 1. 8 1.1 1.1 1.4 2. 1.4 2. 0 0 1.1 8 1.3 1.4 1.3 1.2 1.1 1.0 1.3 2. 0 1.0 7 0.9 3 0.8 0 0.6 0.4 1.2 2.3 1.4 2.6 0.3 0.4 0.3 0.3 0.3 0.2 0.3 0.3 0.3 0.3 0.5 0.9 0.8 1.3 1.0 0.0 3.5 0.0 0.0 0.0 0.0 0. 0. 1 S 2.9 0.3 0.0 0.0 0 0.0 SC 9 LITHONIA WDGE2 LED P2 30K 80CRI T4M MVOLT SRM (FINISH) WALL MOUNT WITH P2 PERFORMANCE PACKAGE - LED - 3000K - TYPE 4M. MOUNTED @ 8'-0" 1922 1 0.91 18.9815 1 PHOTOMETRICS SITE PLAN E.101 1" = 30'-0" 53 ALUZ A5-ZOZO-FLT 24" 27K-GSFL-3W WET (LENGTH) / RSS 10'-0" POLE STRING / FESTOON LIGHTS. MOUNTED @ 8'-0" LED - 2700K 247 1 0.91 3.08 E.101 Revit Version: 2025 Plot Date: 12/8/2025 10:44:41 AM SD SF TELE 701.461.7222 112 No.Roberts Street, Suite 300, Fargo ND 58102 www.eapc.net CONSULTANTS CLIENT DXD SS F2 LAND, L.L.C PROJECT DESCRIPTION EMPIRE SELF STORAGE CITY SANTA FE STATE NEW MEXICO ISSUE DATES SD DEVELOPMENT PACKAGE 12/05/2025 MARK DESCRIPTION DATE PROJECT NO: 20253380 DRAWN BY: KS CHECKED BY: MH COPYRIGHT: All plans, specifications, computer files, field data, notes and other documents and instruments prepared by EAPC as instruments of service shall remain the property of EAPC. EAPC shall retain all common law, statutory and other reserved rights, including the copyright there to. STAMP DRAWING TITLE LIGHTING CUT SHEETS Revit Version: 2025 Plot Date: 12/8/2025 10:44:43 AM E.102 TELE 701.461.7222 112 No.Roberts Street, Suite 300, Fargo ND 58102 www.eapc.net CONSULTANTS CLIENT DXD SS F2 LAND, L.L.C PROJECT DESCRIPTION EMPIRE SELF STORAGE CITY SANTA FE STATE NEW MEXICO ISSUE DATES SD DEVELOPMENT PACKAGE 12/05/2025 MARK DESCRIPTION DATE PROJECT NO: 20253380 DRAWN BY: KS CHECKED BY: MH COPYRIGHT: All plans, specifications, computer files, field data, notes and other documents and instruments prepared by EAPC as instruments of service shall remain the property of EAPC. EAPC shall retain all common law, statutory and other reserved rights, including the copyright there to. STAMP DRAWING TITLE LIGHTING CUT SHEETS Revit Version: 2025 Plot Date: 12/8/2025 10:44:44 AM E.103 TELE 701.461.7222 112 No.Roberts Street, Suite 300, Fargo ND 58102 www.eapc.net CONSULTANTS CLIENT DXD SS F2 LAND, L.L.C PROJECT DESCRIPTION EMPIRE SELF STORAGE CITY SANTA FE STATE NEW MEXICO ISSUE DATES SD DEVELOPMENT PACKAGE 12/05/2025 MARK DESCRIPTION DATE PROJECT NO: 20253380 DRAWN BY: KS CHECKED BY: MH COPYRIGHT: All plans, specifications, computer files, field data, notes and other documents and instruments prepared by EAPC as instruments of service shall remain the property of EAPC. EAPC shall retain all common law, statutory and other reserved rights, including the copyright there to. STAMP DRAWING TITLE LIGHTING CUT SHEETS Revit Version: 2025 Plot Date: 12/8/2025 10:44:45 AM E.104 Form Updated: April 2024 Development Review Team (DRT) Comment Form DRT Review Schedule – 9-12+ weeks* Initial DRT Comments are due to the case planner within three weeks of the DRT Application Intake meeting. Initial DRT review should confirm that the application is complete (i.e. Water Budget has been submitted) and/or identify additional submittals or corrections (i.e. Water Budget needs revision). The case planner will review and convey all Initial DRT Comments to the applicant via a Review Memo. The applicant must respond to all Initial DRT Comments and submit a revised application for Final Review. Final DRT Comments are due to the case planner within two weeks of receipt of the revised application. The case planner will review and convey all Final DRT Comments to the applicant in a Final Review Memo. The complete DRT Review Timeline can range from 9-12+ weeks, depending on the complexity and quality of the application and the total number of applications under review. Review Memo Revised Application Final DRT Comments Timing of Conditions of Approval + Technical Corrections While all DRT conditions of approval and technical corrections must be met by the applicant, the timing of compliance varies. In the “Must be completed by” column in the following tables, please time your conditions of approval and technical corrections to the following development review stages: a. Prior to Public Hearing – these conditions/technical corrections must be addressed before the case may move forward to the public hearing phase of the Development Review Process. b. Prior to Recordation – these conditions/technical corrections may be resolved after the public hearing but must be addressed before the Development Plan or Subdivision plat is recorded. c. Prior to Building Permit Approval – these conditions/technical corrections can be addressed during the building permit review process, but prior to issuance of the permit. d. During Construction – these conditions/technical corrections can be addressed during construction. Development Review Process Flow Chart *See the 2024 Development Review Schedule for details DRT Review Timeline: Initial DRT Comments Final Review Memo Application Received DRT Application Intake DRT Initial Review Comments Due Form Updated: April 2024 Date: 02/09/2026 DRT Member: Clinton Peterson Dept/Div: Public Utilities/Water Division Case No.: 2025-11753 and #2025- 11756 Case Planner: Alexa Hempel Conditions of Approval and Technical Corrections Tables Review by this division/department has determined that this application will meet applicable standards if the following Conditions of Approval and Technical Corrections are met: Case # 2025-11753 and #2025-11756 Conditions of Approval: Must be completed by: Applicant response**: 1. An approved Water Plan will be required for all new public water infrastructure and fire services. Prior to Public Hearing 2. An approved Agreement to Construct and Dedicate (ACD) will be required with the Water Division for all new public water infrastructure and fire services. Prior to Building Permit Approval 3. A separate irrigation meter will be required if the total landscaped area is 1,000 square feet or greater. An approved backflow prevention device shall be installed beyond the meter on any new irrigation service. At the time of development 4. Any re-grading of site over existing water mains shall maintain a minimum of 4 feet of cover and not exceed 5 feet of cover. Depth of existing main to be adjusted to maintain a minimum of 4 feet of cover and not exceed 5 feet of cover if site grading impacts these depth requirements. At the time of development Technical Corrections: Must be completed by: Applicant response**: 1. Applicant and City Water staff will work together to address main looping during the review of the water plan (see attached memo) Prior to water plan approval **The Applicant must respond to the condition of approval or technical correction, indicating they have met the requirement and providing a reference in their revised submittals. If the applicant has not met the requirement, they must indicate as much and provide a response. The applicant should be aware that the following code provisions or other requirements will apply to future phases of development of this project: 1. [list any additional items] 2. Form Updated: April 2024 Explanation of Conditions or Corrections (if needed): (see following pages for notes required) Form Updated: April 2024 City of Santa Fe Water Division Looping Requirement The mission of the Water Division is to provide a safe, reliable, and resilient water supply to meet Santa Fe’s needs. In design of the City’s water distribution system, relevant pieces of this mission are achieved by, among other things, following best practices of looping water lines and avoiding dead end lines. These key distribution design paradigms help maintain water quality (safe) and provide redundancy of supply (reliable). Water distribution lines are installed by developers to Water Division specifications and standards and subsequently maintained by the Water Division. The Water Division does not generally install new extensions to water distribution lines. Based on the location of this development, there is a possibility that the Water Division will require multiple points of connection to the public water system, or to “loop” the line. Primary reasons for looping water main extensions are as follows: - To reduce risk to the health and safety of our customers. Dead-end mains have less water turnover than looped mains, thus increasing the risk of bacteria development from stagnant water. Looping mains within the system when possible is a way to provide better water quality to our customers. - Looping mains together provides better flows for fire hydrants in the event of an emergency. - Looping provides redundancy in the event of a main break. The details of our line extension policy can be found in Chapter 25, Exhibit A, Rule 19 of the City of Santa Fe City Code, available online. Design criteria and construction standards are available on the Water Division’s website. Comments from Water Division engineers are generally provided as part of the water plan review process following the submission of a first draft of the proposed water plan. The Water Division Engineering Section also meets weekly to discuss topics related to current developments, and developers working on projects with the City may join these meetings to discuss project details, including looping requirements. If you are interested in attending a weekly meeting or if you have any questions about the water plan review process, feel free to contact a Water Division Engineer. Development Review Team Comment Form Date: February 24, 2026 Staff person: Alan G. Hook Dept/Div: Public Utilities/ Water Division Case: Case #2025-11753 & #2025-11756 1802 Cerrillos Road Case Mgr: Alexa Hempel Review by this division/department has determined that this application will meet applicable standards if the following are met: Conditions of Approval: Must be completed by: 1 An approved Development Water Budget including a 9.8% contingency per SFCC 14-7.7 will be required. A technical evaluation request for a Development Water Budget needs to be submitted to the City Water Division for review. Prior to Planning Commission packet submittal. 2. An applicant may choose to develop a detailed, alternative Development Water Budget for the development project supported by reliable data that demonstrates that the anticipated annual water use will be less than if based on the Water Division’s standard formulas per SFCC 14-7.7(D)(2). Prior to Planning Commission packet submittal. 3 An Agreement to Construct and Dedicate (ACD) from the Water Division will be required for all new public water infrastructure or fire services. An approved Development Water Budget, including Landscape Irrigation Budget and a 9.8% Contingency is required prior to processing the ACD. Prior to Recordation of Development Plan or Plat. 4 Each lot shall be served by separate water service at the time of development. Prior to construction permit approval. 5 An agreement for metered service (AMS) will be required to install new services, including water offset fees. Prior to construction permit approval. The applicant should be aware that the following city code provisions or other requirements will apply to future phases of development of this project: A. Water rights proposed to be transferred to the city's water system for dedication to a development shall be tendered to the City of Santa Fe at whichever review stage is applicable and occurs first in the review of a particular development, according to the following requirements per SFCC 25-12.4: 1) Not later than sixty (60) days after the final land use approval of the final development plan by the planning and land use department, the planning commission or the governing body. B. A construction permit application shall not be approved until the applicant has dedicated water to meet the approved development water budget for the development project plus a 9.8 percent contingency that covers water utility delivery requirements, as documented by the Water Division designation form and complied with the conditions thereof per SFCC 14-7.7 E1. ACD PACKET CHECK-OFF SHEET This sheet contains a list of required information for processing Agreements to Construct and Dedicate Public Improvements (ACD). *Please submit this sheet with the packet. Check if submitted: [X] Developer Information Sheet [X] Utility Service Application [ ] Utility Contractor Price Quote [X] Copy of Plat [ ] Approved Water Plan Drawing Number [X] Approved Development Water Budget, including Landscape Irrigation Budget and a 9.8% Contingency [N/A] Fee Waiver Application Approved by the Office of Affordable Housing [N/A] SFHP, Not Applicable COUNTY PROJECTS ONLY: [ ] City Council Approval Date NOTE: Applications will NOT be accepted for submittal unless ALL applicable items on this check list are completed and/or attached. DEVELOPER INFORMATION SHEET Developer's Name: DXD SS F2 Land, LLC Address: P.O. Box 5587 Telephone #: (505) 303-0779 Contact Person: Lisa D. Martinez, Land Use Planning Consultant to Empire Self Storage Legal Description of Property: 1802 Cerrillos, 1750 Cerrillos, 1361 Fourth Street, 3RD Berry Avenue – See attached Legal Description/LegalLot of Record Documentation for each parcel Plat Recording Date (month, day & year): Parcel 1: July 22, 1998; Parcel 2: March 31, 1978; Parcel 3: July 22, 1998; Condemnation Parcel 4-1: July 22, 1998; Condemnation Parcel 4-4: July 22, 1998 Record Book #: Parcel 1: Book 391, Page 028 Document No. 1033,815; Parcel 2: Book 62, Page 7 Document No. 417,951; Parcel 3: Book 391, Page 028 Document No. 1033,815; Condemnation Parcel 4-1: Book 391, Page 028; Condemnation Parcel 4-4: Book 391, Page 028; ALSO SEE ATTACHED LEGAL LOT OF RECORD DOCUMENTATION: The Capital Land and Townsite Co. Adidtion Plat dated June 18, 1909 and recorded in Book 1 at Page 119 establishes a legal lot of record for each of the four parcels identified above. Record Page #: See Above Present Owner of Property (exactly as shown): Amatren LLC Project Name: Empire Self Storage Proposed Date of Completion (month & year): November 1, 2027 Developer Engineer Name: Souder, Miller & Associates Address: 5454 Venice Avenue NE, Suite D Albuquerque, NM 87113 Telephone #: (505) 299-0942 Contact Person: Developer Water Utility Contractor Name: TBD Address: Telephone #: Contact Person: Construction Starting Date: October 1, 2026 Type of Business Entity (NM Corporation, General Partnership, LLC, Individual, etc.): LLC NOTE: 1. Developer must fill out all the information above. 2. A Performance Bond from the Contractor, Certificate of Insurance and a check in the amount listed on Page 2 of Agreement to be supplied by the Developer. 3. SDCW requires contractor bid sheets (use SDCW format) 4. Developer is responsible for advising SDCW on proposed changes in start date to ensure availability of SDCW construction Inspector. SDCW USE ONLY Date Received: Project Name: Fire Hydrants: YES or NO CITY or COUNTY Quantity: Drawing #: W.O. #: Inspector: Revised September 11, 2014 4 UTILITY SERVICE APPLICATION *Fill in all highlighted fields on this application. Applicant must sign and date application. Check one only: Water Service Technical Evaluation Request Agreement for Metered Service (AMS) _X Agreement to Construct and Dedicate Public Improvements (ACD) Annexation Application Water Budget Water Offset Program/Water Rights Compliance Evaluation Request Applicant Name: Empire Self Storage Project Address: 1750/1802 Cerrillos Rd, 1361 Fourth St., 3RD Berry Ave Santa Fe, NM. 87505 _ *Required - Attach a Plat of the Property (legal lot of record and proposed development) Plat Filing Information: Year Book 1 Page 119 Township, Range, Section: See attached LLOR Docs. Location: (check one only) Inside Corporate City Limits X Outside Corporate City Limits Property Uniform Property Code: 1802 Cerrillos: 10685824, 1750 Cerrillos: 16008891, 1361 Fourth Street: 18312262, 3RD Berry Avenue: 12776860 Existing Well: Yes No X Legal Description including lot size: 2.72 Acres Short Description of Project: The aforementioned properties are proposed to be utilized by DXD Self Storage as a redevelopment of the former Empire Builders building and two adjacent lots. It is proposed as a mixed use project, including a 3-story (basement + two levels above grade), 95,400 GSF Class A self-storage facility, community office spaces, and an indoor/outdoor gathering area. The two adjacent lots will complement the anchor use by including a + 13,500 sf public dog park, additional creative workshop and storage spaces, and a new parking area to serve tenants and visitors. Construction Start Date: _October 1, 2026 *RESIDENTIAL PROJECT - Complete the following 1. Type of project: (i.e. Single Family Residence, Subdivision, Lot split, Apartments) 2. Total number of lots approved on final plat/development plan: 3. Total number of homes existing or under construction: 4. Size of service requested: (5/8”, 3/4”, 1” or 2”) *Please fill in all categories below that apply for which water service is requested: --- COMPLETED BY APPLICANT --- Number of Lots or Units Water Use Factors Annual Water Demand Single Family Dwelling Unit, lot size less than 6,000 sq. ft. .15 afy per d.u. Single Family Dwelling Unit, lot size 6,000-10,890 sq. ft .17 afy per d.u. Single Family Dwelling Unit, lot size greater than 10,890 sq. ft. .25 afy per d.u. Mobile Home (in Mobile home park) .17 afy per d.u. --- COMPLETED BY STAFF --- WORK ORDER # Revised September 11, 2014 5 Total Total Residential Water Demand AFY UTILITY SERVICE APPLICATION *COMMERCIAL PROJECT - Complete the following Type of Project: (i.e. Office, Retail, Mixed, etc.) Mixed-Use Total gross floor area of building: 95,400 GSF Class A Self-Storage; + 12,758 SF Workshops Total area of lot, tract or parcel: 2.72 acres Automatic Fire Sprinkler System: Yes Building Construction Type: Building Square Footage: + 95,400 GSF Class A Self-Storage; & + 12,758 SF Workshops Site Plan Attached: X Yes No *Please check all use categories below that are planned for the building and the gross floor areas of each use within the proposed building. ---- COMPLETED BY APPLICANT ---- Check Type of Use Gross Floor Area Commercial _X Office–Non-medical (within Storage Building: Community Room 900 SF; Community Restroom 100 SF; Building 2 Workshop 3705 SF; Building 2 Offices (incl. Restroom) 575 SF; Building 3 Workshop 5,840 SF; Building 4 Workshop 2,328 SF; Restroom/MEP 310 SF; Parcel 1: Subtotal 95,400; Parcel 2: 12,758 Total: 108,158 SF Medical Office Office – City/State Research and Development Lab Manufacturing – Goods Manufacturing – Consumables Laundromat, Commercial Laundromat, Other Drycleaner Plant Nursery _ Gyms with showers Gyms without showers Salons ---- COMPLETED BY STAFF ---- Water Use Factors Annual Water Demand (0.70 afy per 10,000 s.f.) (0.72 afy per 10,000 s.f.) (0.58 afy per 10,000 s.f.) (1.18 afy per 10,000 s.f.) See attached alt. calc. (0.21 afy per site) (2.33 afy per site) (0.78 afy per machine) (0.22 afy per machine) (0.41 afy per site) (0.56 afy per 10,000 s.f.) (8.94 afy per site) (0.77 afy per site) (0.21 afy per site) Accessory Dwelling Unit .09 afy per d.u. Apartment/Condominium .16 afy per d.u. Senior Complex .12 afy per d.u. Revised September 11, 2014 6 UTILITY SERVICE APPLICATION Car Wash (full service) Car Wash (limited service) Auto Repair Car Rental Car Sales X Self Storage (Upper Level 30,500 SF; Ground Level 29,500 SF; Lower Level 34,400 SF) Wholesale, Warehousing Industrial, Manufacturing Church w/ day care or school) Church w/o day care or school) Hotel No. of rooms Motel No. of rooms Public Services School, Elementary (5.66 afy per Site) (0.94 afy per Wash Bay) (0.12 afy per site) (0.12 afy per site) (0.07 afy per 10,000 s.f.) (0.13 afy per site) (0.4 afy per 10,000 s.f.) (applicant estimate of water us (1.3 afy per Site) (0.6 afy per Site) (.13 afy per room) (.09 afy per room) (0.53 afy per 100 students) See attached alt. calc. e) School, Middle or Junior High (1.68 afy per 100 students) _ School Schools, Daycare (2.64 afy per 100 students) (0.85 afy per 100 kids) Places of Worship (0.15 afy per site) With Daycare and school (0.95 afy per site) X Parks (Dog Park) 2500 SF (1.48 afy per acre) See attached alt. calc. Other (not listed above) Please attach (with attachment) Pet Grooming (0.52 afy per site) Pet Daycare (0.11 afy per site) Retail, Large (0.45 afy per 10,000 s.f.) (Individual stores or shopping areas > 75,000 sq ft) Neighborhood Center/Medium Retail (0.43 afy per 10,000 s.f.) (Individual stores or shopping areas 75,000-25,000 sq ft) Retail, Small (0.06 afy per site) (Individual stores or shopping areas < 25,000 sq ft) Gallery (0.60 afy per site) Grocery Store (1.27 afy per 10,000 s.f.) Restaurant (full service) (0.02 afy per seat) Restaurant (limited service) (1.63 afy per Site) Gasoline Station w/ Car Wash (6.56 afy per Site) Gasoline Station (0.88 afy per Site) Revised September 11, 2014 7 water demand calculations and assumptions used Total Floor Area: 108,158 SF (Parcel 1 & Parcel 2); 2500 SF Dog Park Revised September 11, 2014 8 Total Commercial Water Demand 1.22 AFY (See Attached Alternate Water Use Calculation) Total Landscaping Water Demand 0.32 AFY (See Attached Alternate Water Use Calculation) 9.8% Contingency 0.15 AFY TOTAL PROJECT WATER DEMAND 1.69 AFY Revised September 11, 2014 9 OWNER: Amatren LLC (Frank W. Culver) Mailing Address: P.O. Box 5587 Phone Number: Mobile Number: (505) 690-4833 *Only If Applicable AGENTS: Lisa D. Martinez, B Constructiv LLC & Joseph Karnes, Sommer Karnes Assoc. Title: Land Use Planning Consultants to Empire Self Storage Mailing Address: 3201 C Zafarano Dr. #111 Santa Fe, NM. 87507 Phone Number: (505) 470-7888 Mobile Number: (505) 470-7888 Information Provided By: Check one: Owner Agent X Signature: Lisa D. Martinez Date: Initial Application: 12/7/2025 Technical Evaluation to be Sent to: Check one: Owner Agent X COMMENTS: APPLICANTS, PLEASE NOTE:  If the project is located within the Historic District and a hotbox for a backflow preventer is required, the Historic Preservation Division must be contacted at (505) 955-6605 to coordinate the hotbox location.  Ordinance 2008-53, prohibits new connections outside the presumptive city limits including the Agua Fria traditional historic community (AFTHC) unless specific conditions are met. Applications for service outside the presumptive city limits and AFTHC must include documentation showing these conditions are met or the application will be rejected. The documents required are shown below: o A map of the proposed project in relation to the existing city limits and the presumptive city limits. o A detailed description of the proposed development including the type and size of proposed land uses. o The health, safety and welfare or other legal reason for the connection. o A site water budget. o Documentation from the County of Santa Fe that county water service is not available, if applicable. o Documentation from the wastewater division regarding sewer availability. o A certified Santa Fe Homes Proposal as set forth in Section 14-8.11 SFCC 1987 if applicable. Form Updated: April 2024 Development Review Team (DRT) Comment Form DRT Review Schedule – 9-12+ weeks* Initial DRT Comments are due to the case planner within three weeks of the DRT Application Intake meeting. Initial DRT review should confirm that the application is complete (i.e. Water Budget has been submitted) and/or identify additional submittals or corrections (i.e. Water Budget needs revision). The case planner will review and convey all Initial DRT Comments to the applicant via a Review Memo. The applicant must respond to all Initial DRT Comments and submit a revised application for Final Review. Final DRT Comments are due to the case planner within two weeks of receipt of the revised application. The case planner will review and convey all Final DRT Comments to the applicant in a Final Review Memo. The complete DRT Review Timeline can range from 9-12+ weeks, depending on the complexity and quality of the application and the total number of applications under review. Review Memo Revised Application Final DRT Comments Timing of Conditions of Approval + Technical Corrections While all DRT conditions of approval and technical corrections must be met by the applicant, the timing of compliance varies. In the “Must be completed by” column in the following tables, please time your conditions of approval and technical corrections to the following development review stages: a. Prior to Public Hearing – these conditions/technical corrections must be addressed before the case may move forward to the public hearing phase of the Development Review Process. b. Prior to Recordation – these conditions/technical corrections may be resolved after the public hearing but must be addressed before the Development Plan or Subdivision plat is recorded. c. Prior to Building Permit Approval – these conditions/technical corrections can be addressed during the building permit review process, but prior to issuance of the permit. d. During Construction – these conditions/technical corrections can be addressed during construction. Development Review Process Flow Chart *See the 2024 Development Review Schedule for details DRT Review Timeline: Initial DRT Comments Final Review Memo Application Received DRT Application Intake DRT Initial Review Comments Due 2/9/26 2/20/26 Form Updated: April 2024 Date: 2/10/26 DRT Member: Alexa Hempel Dept/Div: Current Planning Case No.: #2025-11753/11756 Case Planner: Alexa Hempel Conditions of Approval and Technical Corrections Tables Review by this division/department has determined that this application will meet applicable standards if the following Conditions of Approval and Technical Corrections are met: Case # Conditions of Approval: Must be completed by: Applicant response**: 1. Sign dimensions proposed in architectural plans are too large per 14-8.10(G)(8)(a): “For C-2, SC, and I properties located within the Cerrillos Road highway corridor protection district, the following standards shall apply: For one business establishment on a legal lot of record, not more than three signs are allowed, no one of which shall exceed fifty (50) square feet in area in corridor zone one. The total allowable sign area for all three signs shall not exceed one hundred fifty (150) square feet.” Revise sign sizing to meet this code criteria. At time of Sign Permit 2. Consolidate all lots of Block 2 in “The Capital Land and Townsite Co. Addition to Santa Fe NM” Prior to Recording Development Plan 3. Consolidate Lots 13-20 of Block 3 in “The Capital Land and Townsite Co. Addition to Santa Fe NM” Prior to Recording Development Plan 4. Provide appropriate documentation connecting Lot 1 to the rest of the Development Plan in perpetuity Prior to Recording Development Plan 5. Delete list of Conditions of Approval on DP-102 for now. I will let you know what conditions should be on there after we go to Planning Commission Prior to Planning Commission 6. Fence around Site 2 mini storage units shall provide a visual buffer or screen and be constructed of opaque materials per SFCC 14- 6.2(D)(3). Provide an elevation/detail of the proposed fencing material. Prior to Recordation 7. Is fence 6 or 8 feet tall? DP says 6 ft and architectural plans say 8ft. Please revise to match. Prior to Planning Commission 8. Architectural plans need to be updated to match revised building placement on Site 2 for setbacks. Prior to Planning Commission 9. Architectural plans showing the layout/number Prior to Planning Form Updated: April 2024 of storage units on each floor is missing in new set. Please add this back in. Commission 10. A mural is included in the architectural renderings, but not architectural elevations. Please revise to match Prior to Planning Commission 11. Provide architectural elevations for buildings 2, 3, and 4 Prior to Planning Commission 12. Is this project planned to be built in phases? If so, provide a phasing plan. Prior to Planning Commission Technical Corrections: Must be completed by: Applicant response**: 1. DP-103: Open Space – incorrect code citation. Change to SFCC 14-7.5(D) Prior to Planning Commission 2. Add descriptions/dimensions of all open space provided (might be easier to visually depict on a new sheet) Prior to Planning Commission 3. DP-103: Parking – delete “parks & open space – as determined by the city” Prior to Planning Commission 4. DP-101: Fill in floodplain note #17 Prior to Planning Commission **The Applicant must respond to the condition of approval or technical correction, indicating they have met the requirement and providing a reference in their revised submittals. If the applicant has not met the requirement, they must indicate as much and provide a response. The applicant should be aware that the following code provisions or other requirements will apply to future phases of development of this project: 1. [list any additional items] 2. Explanation of Conditions or Corrections (if needed): (see following pages for notes required) Form Updated: April 2024 Development Review Team (DRT) Comment Form DRT Review Schedule – 9-12+ weeks* Initial DRT Comments are due to the case planner within three weeks of the DRT Application Intake meeting. Initial DRT review should confirm that the application is complete (i.e. Water Budget has been submitted) and/or identify additional submittals or corrections (i.e. Water Budget needs revision). The case planner will review and convey all Initial DRT Comments to the applicant via a Review Memo. The applicant must respond to all Initial DRT Comments and submit a revised application for Final Review. Final DRT Comments are due to the case planner within two weeks of receipt of the revised application. The case planner will review and convey all Final DRT Comments to the applicant in a Final Review Memo. The complete DRT Review Timeline can range from 9-12+ weeks, depending on the complexity and quality of the application and the total number of applications under review. Initial DRT Comments Review Memo Revised Application Final DRT Comments Timing of Conditions of Approval + Technical Corrections While all DRT conditions of approval and technical corrections must be met by the applicant, the timing of compliance varies. In the “Must be completed by” column in the following tables, please time your conditions of approval and technical corrections to the following development review stages: a. Prior to Public Hearing – these conditions/technical corrections must be addressed before the case may move forward to the public hearing phase of the Development Review Process. b. Prior to Recordation – these conditions/technical corrections may be resolved after the public hearing but must be addressed before the Development Plan or Subdivision plat is recorded. c. Prior to Building Permit Approval – these conditions/technical corrections can be addressed during the building permit review process, but prior to issuance of the permit. d. During Construction – these conditions/technical corrections can be addressed during construction. Development Review Process Flow Chart *See the 2024 Development Review Schedule for details DRT Review Timeline: Final Review Memo Application Received DRT Application Intake DRT Initial Review Comments Due Form Updated: April 2024 Date: April 7, 2026 DRT Member: Geronimo Griego, Fire Marshal Dept/Div: Fire Prevention Division Case No.: 2025-11753_2025-11756_1802 Cerrillos_EmpireStorage_DP_SUP (Revised) Case Planner: Alexa Hempel-Senior Planner Conditions of Approval and Technical Corrections Tables Review by this division/department has determined that this application will meet applicable standards if the following Conditions of Approval and Technical Corrections are met: Case # Conditions of Approval: Must be completed by: Applicant response**: 1. Shall reference correct year of IFC (C-100) and Appendix B for average-sprinkler reduction (FC-101) Prior to Public Hearing 2. 3. 4. 5. 6. Technical Corrections: Must be completed by: Applicant response**: 1. 2. 3. 4. **The Applicant must respond to the condition of approval or technical correction, indicating they have met the requirement and providing a reference in their revised submittals. If the applicant has not met the requirement, they must indicate as much and provide a response. The applicant should be aware that the following code provisions or other requirements will apply to future phases of development of this project: 1. [list any additional items] 2. Explanation of Conditions or Corrections (if needed): IFC 2015 is the wrong referenced fire code. The city of Santa Fe most currently adopted fire code is IFC 2021. Also look at the most recently adopted fire code for the correct reference Appendix B Table B105.1 (1) Form Updated: April 2024 Form Updated: April 2024 Development Review Team (DRT) Comment Form DRT Review Schedule – 9-12+ weeks* Initial DRT Comments are due to the case planner within three weeks of the DRT Application Intake meeting. Initial DRT review should confirm that the application is complete (i.e. Water Budget has been submitted) and/or identify additional submittals or corrections (i.e. Water Budget needs revision). The case planner will review and convey all Initial DRT Comments to the applicant via a Review Memo. The applicant must respond to all Initial DRT Comments and submit a revised application for Final Review. Final DRT Comments are due to the case planner within two weeks of receipt of the revised application. The case planner will review and convey all Final DRT Comments to the applicant in a Final Review Memo. The complete DRT Review Timeline can range from 9-12+ weeks, depending on the complexity and quality of the application and the total number of applications under review. Review Memo Revised Application Final DRT Comments Timing of Conditions of Approval + Technical Corrections While all DRT conditions of approval and technical corrections must be met by the applicant, the timing of compliance varies. In the “Must be completed by” column in the following tables, please time your conditions of approval and technical corrections to the following development review stages: a. Prior to Public Hearing – these conditions/technical corrections must be addressed before the case may move forward to the public hearing phase of the Development Review Process. b. Prior to Recordation – these conditions/technical corrections may be resolved after the public hearing but must be addressed before the Development Plan or Subdivision plat is recorded. c. Prior to Building Permit Approval – these conditions/technical corrections can be addressed during the building permit review process, but prior to issuance of the permit. d. During Construction – these conditions/technical corrections can be addressed during construction. Development Review Process Flow Chart *See the 2024 Development Review Schedule for details DRT Review Timeline: Initial DRT Comments Final Review Memo Application Received DRT Application Intake DRT Initial Review Comments Due 2/9/26 by SF MPO 2/9/26 by SF MPO Form Updated: April 2024 Date: 2/16/26 4/16/26 DRT Member: Erick Aune & Carrie Tremblatt Dept/Div: Santa Fe MPO Case No.: Case #2025-11753 Case Planner: Alexa Hampel Conditions of Approval and Technical Corrections Tables Review by this division/department has determined that this application will meet applicable standards if the following Conditions of Approval and Technical Corrections are met: Case # Conditions of Approval: Must be completed by: Applicant response**: 1. Sidewalk should align with Cerrillos Road Plan specs and city street design standards which require 5’ landscape buffer between street and pedestrian path (See comments on plans for detail). Sidewalk width should be at least 6’, but also made as wide as possible on Cerrillos. FHWA and AASHTO guidance support a separated bike facility given the vehicle speeds and volumes here. By expanding the sidewalk to the minimum for a shared use path (10’ ) this would better align with federal guidance. Prior to planning commission 2. Driveway conflicts on NW Fourth street should be minimized by consolidating driveways or minimizing the driveway width to ensure one- way circulation Prior to planning commission 3. Ensure safe pedestrian access to site from each street frontage and sidewalk and also between all 3 parcels. How are conflicts between cars and pedestrians crossing 4th from parking on site 1 to site 2 going to be managed and minimized? Crosswalk should be setback from driveways at least 20 feet. Prior to planning commission 4. Pedestrian Access Routes should aim for right angles. Skewed angles can be challenging for wheelchairs to maneuver safely. Minimize awkward angles and ensure there is sufficient landing pad for maneuvering Prior to planning commission 5. Provide conversations with NMDOT so City staff can better understand NMDOT recommendations for this project. Prior to planning commission 6. Technical Corrections: Must be completed by: Applicant response**: 1. 2. 3. 4. Form Updated: April 2024 **The Applicant must respond to the condition of approval or technical correction, indicating they have met the requirement and providing a reference in their revised submittals. If the applicant has not met the requirement, they must indicate as much and provide a response. The applicant should be aware that the following code provisions or other requirements will apply to future phases of development of this project: 1. [list any additional items] 2. Explanation of Conditions or Corrections (if needed): 3. (see following pages for notes required) See City Street Standards below for sidewalk and landscaping buffer requirements Form Updated: April 2024 Form Updated: April 2024 Development Review Team (DRT) Comment Form Date: February 20, 2026 DRT Member: Leroy Pacheco, PE and Phil Gallegos, PE (Wilson & Company) Dept/Div: Public Works Department – Traffic Engineering Case No.: Case #2025-11753 (Development Plan) & Case #2025-11756 (Special Use Permit) 1802 Cerrillos Road (former Empire Builders Site) Case Planner: Alexa Hempel, LEED Green Associate, Senior Planner Conditions of Approval and Technical Corrections Tables Review by this division/department has determined that this application will meet applicable standards if the following Conditions of Approval and Technical Corrections are met: Case # Conditions of Approval: Must be completed by: Applicant response**: 1. See attached letter from Wilson & Company dated 2/20/26 certifying its concurrence with the developer’s “Initial Traffic Assessment” (ITA). N/A 2. Developer should provide certification that its engineers have provided NMDOT project development engineers opportunity to review site plans in accordance with the department’s proposed redesign and reconstruction of Cerrillos Road. Prior to Planning Commission 3. A detailed signage and striping plan for all required on-street signage, pavement markings, and any related regulatory/directional signs shall be submitted for review and approval by Public Works. Prior to Building Permit Technical Corrections: Must be completed by: Applicant response**: 1. 2. **The Applicant must respond to the condition of approval or technical correction, indicating they have met the requirement and providing a reference in their revised submittals. If the applicant has not met the requirement, they must indicate as much and provide a response. The applicant should be aware that the following code provisions or other requirements will apply to future phases of development of this project: 1. City of Santa Fe Building Code, Chapter 23-3.2 states that before commencement of any new construction, it is mandatory for the owner to obtain approval from the Public Works Department for any driveway curb cut or sidewalk crossing. This approval must be issued before a building permit for such new construction is approved. 2. Note as the public infrastructure plans move forward to building permit, these may be subject to additional reviews and possible corrections to meet Public Works Standards for roadways, ADA, signing, striping, lighting, etc. Form Updated: April 2024 prior to building permit approval. Memorandum To: Leroy Pacheco, PE COSF From: Philip A. Gallegos, PE, Senior Transportation Engineer CC: Date: 2/20/2026 Re: DXD Storage ITA Review Comments Wilson and Company has reviewed the ITA prepared by Sounder Miller and Associates for the DXD Empire Self Storage Development located at 1802 Cerrillos Road in Santa Fe, New Mexico. The ITE Trip Generation Handbook, 12th Edition was utilized for this ITA and the number of trips generated by this development are below the thresholds for a TIA as outlined in the City of Santa Fe TIA Guidelines. Therefore, I concur with the findings of the report. Please let me know if you have any questions or require further information. Sincerely, Philip A Gallegos, PE Senior Transportation Engineer 1 Development Review Team Comment Form Date: February 24, 2026 Staff person: Alan G. Hook Dept/Div: Public Utilities/ Water Division Case: Case #2025-11753 & #2025-11756 1802 Cerrillos Road Case Mgr: Alexa Hempel Review by this division/department has determined that this application will meet applicable standards if the following are met: Conditions of Approval: Must be completed by: 1 An approved Development Water Budget including a 9.8% contingency per SFCC 14-7.7 will be required. A technical evaluation request for a Development Water Budget needs to be submitted to the City Water Division for review. Prior to Planning Commission packet submittal. 2. An applicant may choose to develop a detailed, alternative Development Water Budget for the development project supported by reliable data that demonstrates that the anticipated annual water use will be less than if based on the Water Division’s standard formulas per SFCC 14-7.7(D)(2). Prior to Planning Commission packet submittal. 3 An Agreement to Construct and Dedicate (ACD) from the Water Division will be required for all new public water infrastructure or fire services. An approved Development Water Budget, including Landscape Irrigation Budget and a 9.8% Contingency is required prior to processing the ACD. Prior to Recordation of Development Plan or Plat. Prior to Building Permit 4 Each lot shall be served by separate water service at the time of development. Prior to construction permit approval. 5 An agreement for metered service (AMS) will be required to install new services, including water offset fees. Prior to construction permit approval. The applicant should be aware that the following city code provisions or other requirements will apply to future phases of development of this project: A. Water rights proposed to be transferred to the city's water system for dedication to a development shall be tendered to the City of Santa Fe at whichever review stage is applicable and occurs first in the review of a particular development, according to the following requirements per SFCC 25-12.4: 1) Not later than sixty (60) days after the final land use approval of the final development plan by the planning and land use department, the planning commission or the governing body. B. A construction permit application shall not be approved until the applicant has dedicated water to meet the approved development water budget for the development project plus a 9.8 percent contingency that covers water utility delivery requirements, as documented by the Water Division designation form and complied with the conditions thereof per SFCC 14-7.7 E1. Form Updated: March 2024 Development Review Team (DRT) Comment Form Date: 2/16/2026 DRT Member: Dee Beingessner, Joshua VanSlambrouck (Conditions and corrections in red text have yet to be complete) please see comments inserted Dept/Div: Land Use Engineering Case No.: 1802 Cerrillos Rd Development Plan Case Planner: Alexa Hempel, Senior Planner Conditions of Approval and Technical Corrections Tables Review by this division/department has determined that this application will meet applicable standards if the following Conditions of Approval and Technical Corrections are met: Conditions of Approval: Must be completed by: Applicant Response**: 1. Provide discussion in the drainage narrative of how the stormwater will be directed to the ponding areas. Include how water will be directed from roof drains. Discussion not found. Prior to Recordation 2. Provide flow directional arrows on grading and drainage plan especially showing flow from roof drains to ponding areas. Ponding area volumes must be established for each ponding area showing dimensions. Label each pond with a pond number and the volume. Depressed areas for all landscaped areas are encouraged, but the official ponding areas for the required storage must be verifiable in the future. The conveyance of water to those areas must be shown on the plans and verifiable in the future. Show curb cuts for water to enter landscaped areas. 3. Include pond sections and show how ponds will overflow. Technical Corrections: Must be completed by: Applicant Response**: 1. Include attached notes. 2. A financial guarantee will be required for all public and quasi-public infrastructure. The guarantee must be in place prior to recordation of development plan. 3. Current analysis shows a violation: an increase in peak stormwater flows is not allowed per city code 14-8.2(D)(4) (b)(i) 4. Include 2 additional drainage analysis for the 1-year, 1- hour, and 100-year, 24-hour, required to show compliance for any frequency storm event up to the 100- year, 24-hour. Please See city code 14-8.2(D)(4)(b)(i) “except as otherwise required by this Section 14-8.2, the stormwater runoff peak flow rate discharged from a site shall not exceed pre- development conditions for any frequency storm event up to the one percent chance, twenty-four- hour storm event at each discharge point;” Prior to recordation 5. Show on the drainage and terrain management plans: roof drain pattern and downspouts/canales, and means of Prior to recordation Form Updated: March 2024 stormwater conveyance (swales, catch basins, storm drainpipe, curb cuts, etc.) to stormwater control features 6. Please provide more information on how runoff Coefficients were selected from the NMDOT Manual, include the figure/table number, cover type, % impervious cover, etc. 7. Please Verify how the runoff volumes are calculated, The Rational Method is not an acceptable method to calculate runoff volume per NMDOT Drainage Design Manual, July 2018, section 403, Limitations: “Runoff volumes may not be computed with the Rational Formula Method or Modified Rational Formula Method (not included in this Drainage Design Manual”. 8. Include an acceptable runoff volume analysis for stormwater quality volume for a 0.68-inch (90% percentile, or roughly the 1-year, 1-hour storm) event. This runoff volume must be contained/retained on site, to reduce pollution per EPA NPDES MS4, see city code 14- 8.2(A)(13). This volume must infiltrate in 24 hours per city code 14-8.2(D)(4)(c)(ii), It is encouraged that the Stormwater quality volume design is incorporated into the landscape, to also comply with landscape code rainwater harvesting requirements 14-8.4(E)(1) “The landscaping plan shall include passive water harvesting for landscape irrigation purposes as a minimum requirement” the minimum recess depth for retention and water harvesting areas is 6 inches. Prior to recordation 9. **The Applicant must respond to the condition of approval or technical correction, indicating they have met the requirement and providing a reference in their revised submittals. If the applicant has not met the requirement, they must indicate as much and provide a response. The applicant should be aware that the following code provisions or other requirements will apply to future phases of development of this project: 1. [list any additional items] 2. Explanation of Conditions or Corrections (if needed): See following pages for notes required on plat or plans DRAINAGE FACILITIES MAINTENANCE NOTE ALL DRAINAGE FACILITIES SHALL BE MAINTAINED BY ALL PROPERTY OWNERS. THE PROPERTY OWNERS SHALL ALSO HAVE THE RESPONSIBILITY FOR MAINTENANCE OF THE PUBLIC DRAINAGE EASEMENT. INSPECTIONS SHALL BE CONDUCTED BY A REGISTERED PROFESSIONAL ENGINEER IN THE STATE OF NEW MEXICO OR OTHER QUALIFIED PERSON. INSPECTIONS SHALL BE CONDUCTED ON THE DRAINAGE FACILITIES IN ACCORDANCE WITH THE FOLLOWING SCHEDULE: Form Updated: March 2024 ON OR ABOUT MARCH 15, ON OR ABOUT SEPTEMBER 15, AND AFTER EACH STORM EVENT OF 1-INCH OR GREATER. MAINTENANCE OF THE DRAINAGE FACILITIES SHALL BE CONDUCTED AND DOCUMENTED BY THE ENGINEER OR QUALIFIED PERSON AND THE OWNER. THE OWNER SHALL MAINTAIN A FILE OF THE INSPECTIONS AND REMEDIAL ACTION CONDUCTED ON THE DRAINAGE FACILITIES. WORK SHALL BE CONDUCTED IN ACCORDANCE WITH THE ENGINEER’S RECOMMENDATIONS, AND SHALL INCLUDE, BUT IS NOT LIMITED TO THE FOLLOWING: A. FLUSH ALL CULVERTS, DROP INLETS AND DRAINAGE PIPES TO REMOVE SEDIMENT AND VEGETATION THAT PREVENTS OR HINDERS THE FLOW OF STORM WATER IN THE DRAINAGE STRUCTURE(S). B. REMOVE SEDIMENT IN PONDS THAT IS GREATER THAN 6-INCHES IN DEPTH, AND IF NECESSARY, RESEED WITH NATIVE GRASSES AND INSTALL FILTER FABRIC AND 3 TO 4 INCH COBBLE AS DIRECTED BY THE ENGINEER. C. INSPECT FOR SEDIMENTATION IN ALL SWALES, DITCHES, DRAINGE PONDS AND REMOVE AND STABILIZE AS NECESSARY. D. INSPECT FOR SOIL EROSION AT ALL DRAINAGE PONDS, CUT AND FILL SLOPES, AND REPAIR OR STABILIZE ACCORDINGLY. E. INSPECT THE STRUCTURAL INTEGRITY OF DRAINAGE PONDS, SLOPES, RIP- RAP, GABIONS, DROP INLETS, CULVERTS, ENERGY DISSIPATORS, AND RETAINING WALLS, ROCK PLATING, EROSION CONTROL MATS OR BLANKETS, AND REPAIR OR STABILIZE ACCORDINGLY. GUNNISON’S PRAIRIE DOG NOTE THE PROJECT SHALL COMPLY WITH THE PROVISIONS OF THE GUNNISION’S PRAIRIE DOG ORDINANCE (ARTICLE 14-8.12). DUST CONTROL NOTE All on-site soil disturbing construction activities shall be addressed and provide measures to mitigate or control dust from being transported offsite and polluting neighboring properties. Any person, owner, contractor or operator who conducts earthmoving and/or dust generating activities is responsible for implementing Best Management Practices (BMPs) in order to mitigate off-property transport of fugitive dust emissions. A plan, or storm water prevention plan (SWPPP) when applicable, listing the Best Management Practices (BMPs), shall be provided to the City Engineer, or their designee for review and Form Updated: March 2024 approval. The approved BMPs shall be applied to the graded and/or disturbed soil in order to stabilize the site. The initial BMP shall address how the Contractor will minimize the amount of disturbed soil, and how the Contractor will stabilize the disturbed surface area exposed to wind or vehicle traffic during construction. Some BMPs shall include:  The reduction of vehicle speeds: establish a maximum speed limit or install traffic calming devices to reduce speeds to a rate to mitigate off-property transport of dust entrained by vehicles.  The minimization of drop height: Drivers and operators shall unload truck beds and loader or excavator buckets slowly, and minimize drop height of materials to the lowest height possible, including screening operations.  High winds restriction: temporarily halt work activities during high wind events greater than 30 mph if operations would result in off-property transport.  Restrict access: restrict access to the work area to only authorized vehicles and personnel. In the event the above practices are ineffective to prevent off property transport, the owner or operator shall use at one or more of the following Best Management Practices (BMPs):  Wet suppression: apply water to disturbed soil surfaces, backfill materials, screenings, and other dust generating operations as necessary and appropriate considering current weather conditions, and prevent water used for dust control from entering any public right-of-way, storm water drainage facility, or watercourse.  Wind barrier: construct a fence or other type of wind barrier to prevent wind erosion of the graded or disturbed surface.  Vegetation: plant vegetation appropriate for retaining soils or creating a wind break.  Surface roughening: stabilize an active construction area during periods of inactivity or when vegetation cannot be immediately established.  Cover: install cover materials such as tackifiers, erosion control blankets, gravel, vegetation (when appropriate), cold-millings, etc. during periods of inactivity and properly anchor the cover.  Soil retention: stabilize disturbed or exposed soil surface areas that will be inactive for more than 30 days or while vegetation is being established. ENGINEER’S STORMWATER INFRASTRUCTURE CERTIFICATION I, the undersigned professional engineer in the State of New Mexico, do hereby certify that the record information shown hereon is based on actual field measurements and visual inspections performed by myself or under my direct supervision. I further certify that the record condition as of is in substantial compliance with the approved grading and drainage plan prepared by , dated . Signature NMPE # Date Form Updated: March 2024 Example for pond measurement post Form Updated: April 2024 Development Review Team (DRT) Comment Form DRT Review Schedule – 9-12+ weeks* Initial DRT Comments are due to the case planner within three weeks of the DRT Application Intake meeting. Initial DRT review should confirm that the application is complete (i.e. Water Budget has been submitted) and/or identify additional submittals or corrections (i.e. Water Budget needs revision). The case planner will review and convey all Initial DRT Comments to the applicant via a Review Memo. The applicant must respond to all Initial DRT Comments and submit a revised application for Final Review. Final DRT Comments are due to the case planner within two weeks of receipt of the revised application. The case planner will review and convey all Final DRT Comments to the applicant in a Final Review Memo. The complete DRT Review Timeline can range from 9-12+ weeks, depending on the complexity and quality of the application and the total number of applications under review. Initial DRT Comments Review Memo Revised Application Final DRT Comments Timing of Conditions of Approval + Technical Corrections While all DRT conditions of approval and technical corrections must be met by the applicant, the timing of compliance varies. In the “Must be completed by” column in the following tables, please time your conditions of approval and technical corrections to the following development review stages: a. Prior to Public Hearing – these conditions/technical corrections must be addressed before the case may move forward to the public hearing phase of the Development Review Process. b. Prior to Recordation – these conditions/technical corrections may be resolved after the public hearing but must be addressed before the Development Plan or Subdivision plat is recorded. c. Prior to Building Permit Approval – these conditions/technical corrections can be addressed during the building permit review process, but prior to issuance of the permit. d. During Construction – these conditions/technical corrections can be addressed during construction. Development Review Process Flow Chart *See the 2024 Development Review Schedule for details DRT Review Timeline: Final Review Memo Application Received DRT Application Intake DRT Initial Review Comments Due Form Updated: April 2024 Date: May 1, 2026 DRT Member: Geronimo Griego, Fire Marshal Dept/Div: Fire Prevention Division Case No.: 2025-11753_2025-11756_1802 Cerrillos_EmpireStorage_DP_SUP (3rd Review) Case Planner: Alexa Hempel-Senior Planner Conditions of Approval and Technical Corrections Tables Review by this division/department has determined that this application will meet applicable standards if the following Conditions of Approval and Technical Corrections are met: Case # Conditions of Approval: Must be completed by: Applicant response**: 1. Shall comply with the most currently adopted International Fire Code (IFC) and adopted city ordinances upon building permit approval. Prior to Building Permit Approval 2. Shall maintain access to apparatus access roads in and around construction sites. Complying IFC 2021, Chapter 33 Fire Safety and During Construction and Demolition. During Construction 3. 4. 5. 6. Technical Corrections: Must be completed by: Applicant response**: 1. 2. 3. 4. **The Applicant must respond to the condition of approval or technical correction, indicating they have met the requirement and providing a reference in their revised submittals. If the applicant has not met the requirement, they must indicate as much and provide a response. The applicant should be aware that the following code provisions or other requirements will apply to future phases of development of this project: 1. [list any additional items] 2. Explanation of Conditions or Corrections (if needed): 1.